2. Answer the following questions based on the chart. What is the critical path based on 0 float times? b. Which activities have float times? c. Can resource from activity B be used to help activity C? Why? d. Can resource from activity D be used to help activity F? Why?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
2. Answer the following questions based on the chart.
a. What is the critical path based on 0 float times?
b.
Which activities have float times?
c. Can resource from activity B be used to help activity
C? Why?
d. Can resource from activity D be used to help activity
F? Why?
Transcribed Image Text:2. Answer the following questions based on the chart. a. What is the critical path based on 0 float times? b. Which activities have float times? c. Can resource from activity B be used to help activity C? Why? d. Can resource from activity D be used to help activity F? Why?
Below is a project listed in a table with:
activity,
predecessor, and
duration.
Activity
A
B
с
D
E
F
G
H
Predecessor
none
A
A
с
B
B
D, E, F
G
Fill in the chart below by filling in:
early start (ES),
early finish (EF),
☐late start (LS),
A
late finish (LF),
duration (D), and
float (F).
Then, answer the questions based on the chart.
Hint: You can use the Word tools to fill in the chart, or you can draw the chart by hand,
then photograph or scan your graph to submit it.
1. Fill in the chart below.
B
Duration (weeks)
C
5
3
8
13
7
9
10
7
-
D
E
F
G
H
Transcribed Image Text:Below is a project listed in a table with: activity, predecessor, and duration. Activity A B с D E F G H Predecessor none A A с B B D, E, F G Fill in the chart below by filling in: early start (ES), early finish (EF), ☐late start (LS), A late finish (LF), duration (D), and float (F). Then, answer the questions based on the chart. Hint: You can use the Word tools to fill in the chart, or you can draw the chart by hand, then photograph or scan your graph to submit it. 1. Fill in the chart below. B Duration (weeks) C 5 3 8 13 7 9 10 7 - D E F G H
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.