7. The internal rate of return (IRR) is the point at which a project's NPV equals 0. If the cost of capital were 5% (move the slider so that is the case), then a. Project S is the better project because it has the higher IRR. b. Project L is the better project because it has the higher NPV. c. It depends because there is a conflict between IRR and NPV. -Select- 8. If the cost of capital was greater than the point at which the two projected NPVs are equal, then a. It depends because there is a conflict between IRR and NPV. b. There is no conflict because Project S has both a higher NPV and a higher IRR than Project L. c. There is no conflict because Project L has both a higher NPV and a higher IRR than Project S. -Select-

Managerial Accounting
15th Edition
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:Carl Warren, Ph.d. Cma William B. Tayler
Chapter12: Capital Investment Analysis
Section: Chapter Questions
Problem 1CMA
icon
Related questions
Question
The blue curve (labeled "L") depicts the NPV for a project with larger cash flows later of -$1,000, $100, $300, $400, and $675. The red curve (labeled "S") depicts the NPV for a project with larger cash flows sooner of -$1,000, $500, $400, $300, and $100. Drag on the graph either left or right to
change the cost of capital interest rate at which the NPV is evaluated for the two projects.
NPV ($)
500-
400
300
200-
100.40100-
78.82
0
-100-
Project S: NPV = CF₁+N CF₁
-=1 (1+r)
N CF₂
Project L: NPV = CF₁ + Σ = 1 (1+r) ²
+ ΣΜ = = -S1, 000 +
²
L
¡=-$1,000+
S
15
$500
$400
$300
$100
(1+0.1000)¹ (1+0.1000)² (1+0.1000)³ (1+0.1000)*
20
+
Cost of Capital (%)
$100
$300
$400
$675
(1+0.1000)¹ (1+0.1000) (1+0.1000)³ (1+0.1000)*
+
+
+
+
+
= $78.82
= $100.40
Transcribed Image Text:The blue curve (labeled "L") depicts the NPV for a project with larger cash flows later of -$1,000, $100, $300, $400, and $675. The red curve (labeled "S") depicts the NPV for a project with larger cash flows sooner of -$1,000, $500, $400, $300, and $100. Drag on the graph either left or right to change the cost of capital interest rate at which the NPV is evaluated for the two projects. NPV ($) 500- 400 300 200- 100.40100- 78.82 0 -100- Project S: NPV = CF₁+N CF₁ -=1 (1+r) N CF₂ Project L: NPV = CF₁ + Σ = 1 (1+r) ² + ΣΜ = = -S1, 000 + ² L ¡=-$1,000+ S 15 $500 $400 $300 $100 (1+0.1000)¹ (1+0.1000)² (1+0.1000)³ (1+0.1000)* 20 + Cost of Capital (%) $100 $300 $400 $675 (1+0.1000)¹ (1+0.1000) (1+0.1000)³ (1+0.1000)* + + + + + = $78.82 = $100.40
7. The internal rate of return (IRR) is the point at which a project's NPV equals 0. If the cost of capital were 5% (move the slider so that is the case), then
a. Project S is the better project because it has the higher IRR.
b. Project L is the better project because it has the higher NPV.
c. It depends because there is a conflict between IRR and NPV.
-Select-
8. If the cost of capital was greater than the point at which the two projected NPVs are equal, then
a. It depends because there is a conflict between IRR and NPV.
b. There is no conflict because Project S has both a higher NPV and a higher IRR than Project L.
c. There is no conflict because Project L has both a higher NPV and a higher IRR than Project S.
-Select-
Transcribed Image Text:7. The internal rate of return (IRR) is the point at which a project's NPV equals 0. If the cost of capital were 5% (move the slider so that is the case), then a. Project S is the better project because it has the higher IRR. b. Project L is the better project because it has the higher NPV. c. It depends because there is a conflict between IRR and NPV. -Select- 8. If the cost of capital was greater than the point at which the two projected NPVs are equal, then a. It depends because there is a conflict between IRR and NPV. b. There is no conflict because Project S has both a higher NPV and a higher IRR than Project L. c. There is no conflict because Project L has both a higher NPV and a higher IRR than Project S. -Select-
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Corporate Fin Focused Approach
Corporate Fin Focused Approach
Finance
ISBN:
9781285660516
Author:
EHRHARDT
Publisher:
Cengage