A certain job shop specializes in one-of-a-kind orders dealing with parts of medium-to-high complexity. A typical part is processed sequentially through 10 machines in batch sizes of 1. The shop contains a total of eight conventional machine tools and operates 40 hr/wk of pro duction time. Average time values on each part per machine are: machining time = 0.5 hr, work handling time = 0.3 hr, tool change time = 0.2 hr, setup time = 3 hr, and non operation time = 12 hr. A new programmable machine is being considered that can per form all 10 operations in a single setup. The programming of the machine for this part will require 20 hr; however, the programming can be done off-line, without tying up the machine. Setup time will be just 2 hr because simpler fixtures will be used. Total machining time will be reduced to 80% of its previous value due to advanced tool control algorithms; work han dling time will be the same as for one machine; and total tool change time will be reduced by 50% because tools will be changed automatically under program control. For the one machine, nonoperation time is expected to be 12 hr, same as for each conventional machine. (a) Determine the manufacturing lead time for the conventional machines and for the new programmable machine. (b) Compute the plant capacity for the following alternatives: (i) a job shop containing the eight traditional machines, and (ii) a job shop containing two of the new programmable machines. Assume the typical jobs are represented by the data given above. (c) Determine the average level of work-in-process for the two alternatives in part (b), if the alternative shops operate at full capacity

Elements Of Electromagnetics
7th Edition
ISBN:9780190698614
Author:Sadiku, Matthew N. O.
Publisher:Sadiku, Matthew N. O.
ChapterMA: Math Assessment
Section: Chapter Questions
Problem 1.1MA
icon
Related questions
Question

A certain job shop specializes in one-of-a-kind orders dealing with parts of medium-to-high

complexity. A typical part is processed sequentially through 10 machines in batch sizes of 1.

The shop contains a total of eight conventional machine tools and operates 40 hr/wk of pro

duction time. Average time values on each part per machine are: machining time = 0.5 hr,

work handling time = 0.3 hr, tool change time = 0.2 hr, setup time = 3 hr, and non

operation time = 12 hr. A new programmable machine is being considered that can per

form all 10 operations in a single setup. The programming of the machine for this part will

require 20 hr; however, the programming can be done off-line, without tying up the machine.

Setup time will be just 2 hr because simpler fixtures will be used. Total machining time will

be reduced to 80% of its previous value due to advanced tool control algorithms; work han

dling time will be the same as for one machine; and total tool change time will be reduced

by 50% because tools will be changed automatically under program control. For the one

machine, nonoperation time is expected to be 12 hr, same as for each conventional machine.

(a) Determine the manufacturing lead time for the conventional machines and for the new

programmable machine. (b) Compute the plant capacity for the following alternatives: (i) a

job shop containing the eight traditional machines, and (ii) a job shop containing two of the

new programmable machines. Assume the typical jobs are represented by the data given

above. (c) Determine the average level of work-in-process for the two alternatives in part

(b), if the alternative shops operate at full capacity

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps

Blurred answer
Knowledge Booster
Automation of Manufacturing Processes
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Elements Of Electromagnetics
Elements Of Electromagnetics
Mechanical Engineering
ISBN:
9780190698614
Author:
Sadiku, Matthew N. O.
Publisher:
Oxford University Press
Mechanics of Materials (10th Edition)
Mechanics of Materials (10th Edition)
Mechanical Engineering
ISBN:
9780134319650
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Thermodynamics: An Engineering Approach
Thermodynamics: An Engineering Approach
Mechanical Engineering
ISBN:
9781259822674
Author:
Yunus A. Cengel Dr., Michael A. Boles
Publisher:
McGraw-Hill Education
Control Systems Engineering
Control Systems Engineering
Mechanical Engineering
ISBN:
9781118170519
Author:
Norman S. Nise
Publisher:
WILEY
Mechanics of Materials (MindTap Course List)
Mechanics of Materials (MindTap Course List)
Mechanical Engineering
ISBN:
9781337093347
Author:
Barry J. Goodno, James M. Gere
Publisher:
Cengage Learning
Engineering Mechanics: Statics
Engineering Mechanics: Statics
Mechanical Engineering
ISBN:
9781118807330
Author:
James L. Meriam, L. G. Kraige, J. N. Bolton
Publisher:
WILEY