A company produces 148,000 speakers per week and effective capacity of the company is 175,000 speakers. The company operates 8 hours per shift and has 3 shift per day and there is 7 working days per week. If company produces 1,200 speakers per hour means what is the Design capacity and Utilization rate?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section4.8: Data Envelopment Analysis (dea)
Problem 42P
icon
Related questions
Question
A company produces 148,000 speakers per week and effective capacity of the company is 175,000
speakers. The company operates 8 hours per shift and has 3 shift per day and there is 7 working
days per week. If company produces 1,200 speakers per hour means what is the Design capacity
and Utilization rate?
200,160 Speakers, 86.8%
200,000 Speakers, 64.3 %
1200 Speakers, 87%
201,600 Speakers, 73.4%
Transcribed Image Text:A company produces 148,000 speakers per week and effective capacity of the company is 175,000 speakers. The company operates 8 hours per shift and has 3 shift per day and there is 7 working days per week. If company produces 1,200 speakers per hour means what is the Design capacity and Utilization rate? 200,160 Speakers, 86.8% 200,000 Speakers, 64.3 % 1200 Speakers, 87% 201,600 Speakers, 73.4%
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,