A) Draw Precedence diagram (PD). B) Calculate completion data, what is completion data. C) Identify all the path in the project PD.
Q: 1. Prepare the Activity Node Diagram and identify the Critical Path 2. Prepare Gantt Chart Thankss
A: Given data is
Q: . Draw a precedence diagram using AOA. b. Find the critical path. c. Determine the expected length…
A: Below is the solution:-
Q: a. Construct a CPM network for the design project. b. Compute the EF, LF, and slack for each…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: SESSION 2– Individual exercise (for marks) Given the following activity precedence table, please…
A: The question is related to Critical Path Analysis. The details are given.
Q: A senior MIS design class project team has developed the following schedule of activities for their…
A: The project network is expressed as below:
Q: Define WBS and work package. Draw WBS for a TV prototype manufacture project. How does WBS help the…
A: Note- Only three parts have been answered as per the guidelines of Bartleby. A work package refers…
Q: Activity Description Preceded bDy Time (WKS) Feasibility Study Estimate production volumes Market…
A: i) the AOA format, the possible path activities would look like:
Q: a. Sketch the whole network. b. Find out critical path by analysing and showing ES, EF, LS, LF and…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: a. Construct AON diagram for the following data. b. Identify critical path. c. Conduct CPM analysis…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: a. Determine the expected activity completion times, te. b. Identify the critical path. c. What's…
A: The first four subparts (a), (b), (c), and (d) are answered below.
Q: Draw the Network Diagram and determine the Critical Path and duration of the project (in days).…
A: Given Information:
Q: H.W(1):- Draw Gantt chart for the following project and determine the duration of the project…
A: A Gantt chart is a type of bar chart. It shows the schedule of a project. It was invented by Henry…
Q: Q:2 Draw AOA and AON network diagrams and gantt chart for the project, calculate TE for each…
A: Below is the solution:-
Q: a. Calculate ALL the missing (?) data points. b. Draw the PERT network from the given data. c.…
A: NOTE: We are allowed to do the first three sub-parts only. PERT is a project management tool used…
Q: Path QRT will take how many days? ( Select] The critical path is? [ Select] The duration of the…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Janice Eliassen must complete the activities in the following table to fin ish her consulting…
A: Given data is
Q: 1. Construct the activity-on-node network. 2. Identify the critical path. 3. Compute the duration of…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: A2 A4 A5 Task Duration (days) 3 A1 A2 A3 3 Aa A5 days What is the late finish time for activity A,?
A: Using the Forward path, Early Start of the activity = Early Finish of predecessor activity Early…
Q: [6 marks] Carefully draw an AON network diagram for the project, and perform both the forward and…
A: THE ANSWER IS AS BELOW:
Q: Consider the following data for a project to install a newserver at the Northland Pines High School:…
A: The critical path method, or critical path analysis, refers to an algorithm which is used for…
Q: Given the activities whose sequence is described by thefol lowing table, draw the appropriate…
A: Critical path refers to the stage sequences, that require maximum time for the project completion.
Q: Define project Work breakdown structure (WBS) and a work package? Provide a brief example of a…
A: THE ANSWER IS AS BELOW:
Q: a)Construct AON diagram for the following data. b) Identify path, path duration and critical path c)…
A: Below is the solution:-
Q: The Omega department is planning to bid on large project for the development of a new communication…
A:
Q: . CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL…
A: Activity-on-node is a therm related to project management. It directs to a precedence diagramming…
Q: a) Draw the AON project network diagram. b) Calculate the expected time of each activity? (Round…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: (a) Draw the network diagram. Please add drawing here (photo may be added if hand drawn) (b) Using…
A: A project network is the graphical representation of project activities and their duration to…
Q: Enrichment Exercise 7.2 Promoter of championship boxing match must perform the task shown in the…
A: An approach is a better way of looking at teaching and learning concepts. An approach gives rise to…
Q: Activity Predecessor Time(weeks) A 8 B A 6 4 D E A 11 F B 3 D, E, F 1 Using Table A, what is the…
A: Network Diagram,
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: Task time estimates for the modificat ion of an assembly line at Jim Goodale's Carbondale, Illinois,…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Answered all given questions as below. Value for A and B will be determined by your unique id as per…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(a, b,…
Q: a. Draw a precedence diagram using AOA , AON and Gantt chart. b. Find the critical path using CPM.…
A: Below is the solution:-
Q: Task time estimates for a production line setup project at XYZ Company are as follows; Activity Time…
A: We are authorized to answer three subparts at a time since you have not mentioned which part you are…
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: completion
A: The Time Estimation Formula To figure how long the activity will take, complete this equation, with…
Q: The following Table 1 contains a list of activities, with precedence requirements and crash costs.…
A: The network diagram is shown below
Q: Task bme estimates for the modification of an assembly line at Jim Goodale's Carbondale, linois,…
A: A Gantt chart usually practiced in project management, is the most widespread and helpful means of…
Q: Instructions: 1. Make the project network diagram 2. Find the project duration 3. Solve for 4.…
A: For each non-critical activity, the total float, free float, and independent float calculations are…
Q: 1. For cach of the following network diagrams, determine both the critical path and the expected…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Instructions: 1. Make the project network diagram 2. Find the project duration 3. Solve for…
A: Note: - Since we can answer only up to three subparts we will answer only the first three subparts…
Q: Immediate Activity Predecessor Time (days) 8 в 20 33 18 D E 20 F B B.C 10 H D EF G, H, I 4 (End) a)…
A: A network diagram is a visual representation of a project which helps to identify the project…
Q: 4. For each of the following network diagrams, determine both the critical path and the expected…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: Target Completion B. Critical Path Method C. Create 2 ways of network Diagram D. Conclusion
A: The answer is as below:
Q: Activity Resources Duration (days) Precedence activity A Sub-con 10 Direct labour, Material Supplier…
A: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: Draw the project network diagram. 1. What is the total time required to complete the project if no…
A: Network analysis (NA) could be a set of integrated techniques to depict relations among actors and…
Q: A senior MIS design class project team has developed the following schedule of activities for their…
A: The project network diagram helps in finding the duration of the project. It can also help in…
Q: a. Construct the project network b. Determine the critical path c. Find the completion time of the…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Draw a project network given the information below. Time (Days) Predecessor Description First…
A: A network diagram is the pictorial representation of all the activities in the project in…
Q: Consider a project having the following seven activities: Normal Normal Crash Crash Maximum Time…
A: A network diagram is a visual representation of a project which helps to identify the project…
Step by step
Solved in 2 steps with 1 images
- Activity A B D E F H I Dependency A A B C D E F,G,H Duration (week) LO 5 4 3 7 3 4 3 2 4 a. Draw a project network diagram then show the calculation for Early Start (ES), Early Finish (EF), Late Start (LS) and Late Finish (LF). b. Find the critical path for the projectPERT-CPM 1. Consider a project involving the following activities and precedence relationship. The cost of each activity is listed. The following activity time estimates have been provided for a preparation involving an MIS project. a. Draw the AON and AOA Diagram. b. Perform a Program Evaluation and Review Technique (PERT) to determine the expected total duration of the project. [Note: Use the diagramming convention agreed in class and tabulate the results for each activity's ES, EF, LS, LF, slack time and indication if it's in the critical path Note: Expected (Ave Time) = (0ptimistic Time + 4*Most Likely Time + PessimisticTime) / 6 = ( OT + 4MLT + PT ) / 6 c. If the project exceeds 11 weeks, there is an additional miscellaneous costs around Php 30,000. Will the company opt to speed up the project? Activity Predecessors Optimistic Most Pessimistic Crash Normal Crashed Likely Time Cost Cost A 2 4 6. 2 11,000 6,000 3,000 7,000 4,000 13,000 9,000 4,000 5,000 3,000 3 17.000 В 1 3 5 1…A project consisting of the following activities: Activities predece.Activities day TE M K J H G E C B G KJ G I,F D D E,C B,A| B,A A 1 3 4 6. 5 2 3 9 6 2 4 3 5 1- Draw the network diagram of the project 2- Calculate (Es) and (Lc) the project events 3- Select the critical path 4 - What is the minimum time required to complete the project?
- 3. (1) Define critical path, ES, EF, LS, LF, dummy activity and slack. (2) Cables By Us is bringing a new product on line to be manufactured in their current facility in existing space. The owners have identified 11 activities and their precedence relationships. (a) Draw the network diagram of this project (b) Calculate the project completion time (c) Identify the critical path Immediate Duration Activity Description Predecessar (weeks) A Develop product specifications B None 4 Design manufacturing process C A Source & purchase materials Source & purchase tooling & equipment Receive & install tooling & equipment A В 6 E 14 F Receive materials C Pilot production run Evaluate product design Evaluate process perfommance Write documentation report Transition to manufacturing E&F 2 G G J H&I 4 K Ja) Construct a Gantt chart using MS Project 2016b) Assuming the default 5-day workweek, calculate the critical path of the project.c) Calculate the project duration.Reliable Garage is completing production of the J2000 kit car.The following data are available for the project:Activity Activity Time (days) Immediate Predecessor(s)A 2 —B 6 AC 4 BD 5 CE 7 CF 5 CG 5 FH 3 D, E, Ga. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?
- Start 10 16 18 20 Weeks after start 4. For each of the following network diagrams, determine both the critical path and the expected project duration! The numbers on the arrows represent expected activity times. a) AOA (Activity-On-Arrow) diagram 5 9 2 10 3 7 8 12 10 3 11 BM HL Assignment 1- Due Date 24 March 2022 b) AON (Activity-On-Node) Diagram 3 18 4 10 6 5 13 2 11 c) AOA (Activity-On-Arrow) Diagram 14 13 5 12 6 15 14 13 ן1 3 16 13 14 15 8. 11 10- Draw the project network diagram. - What completion date would you recommend?Given is a Project with network diagram and activity times as shown below. Activity Time (wks) A 13 B 5 Start с 14 A c) The Slack time of Activity C = Blank 3 weeks D D a) The Earliest Start (ES) time of Activity I = Blank 1 weeks 9 b) The Latest Start (LS) time of Activity B = Blank 2 weeks f) The Project Completion time = Blank 6 weeks d) The Earliest Finish (EF) time of Activity H = Blank 4 weeks e) The Latest Finish (LF) time of Activity B = Blank 5 weeks B F E 12 E F LL 17 H G 9 J H 15 - 15 J 2
- The activities involved in a project are listed in the following table. Construct the project network and use CPMto find the critical path Ac tivity Content Predece ssor(s) Duration (days) A Initial research B Studysite selection Prepare research plan Contact the surveysite Training staff Prepare the form Field re search Write the re search report Meeting Summary A 2 A 4 B 2 E B, C 3 F C 1 G D, E, F G 5 2 I H 3Please answer all parts Activity Preceding activity Activity duration A - 6 B - 3 C - 1 D A, B 2 E A, C 5 F D, E 2 G D, F 6 Draw an AON diagram based on the activities and their relationships given in the table. Find the earliest start time (ES), earliest finish time (EF), latest start time (LS), latest finish time (LF), and Slack time for each activity of the project. Determine the slack time for each path. Find the critical activities and critical path. Determine the length of the project.1. Activity Preceding activity Activity duration A - 6 B - 3 C B 1 D A, C 2 E B 5 F D 2 G E, F 6 Draw an AOA diagram based on the activities and their relationships given in the table. Find the earliest start time (ES), earliest finish time (EF), latest start time (LS), latest finish time (LF), and Slack time for each activity of the project. Determine the slack time for each path. Find the critical activities and critical path. Determine the length of the project.