A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 70 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D. E. F and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, and 4.7 minutes respectively. What should be the cycle time in minutes? O a. 4,4 Ob. 7.5 O c. 4.7 O d. 6.86 O e. None is the correct answer
Q: An assembly department has six jobs waiting to be processed. It is now time zero and all jobs are…
A:
Q: . Use the assignment method to obtain a plan that will minimize the processing costs in th ollowing…
A: The assignment problem is finding the optimal outcomes with the objective of having the least…
Q: Sunny Park Tailors has been asked to make three different types of wedding suits for separate…
A: First come first serve (FCFS) scheduling calculation just timetables the positions as per their…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data: Production line = 8 hours per day Demand = 90 units per day Task Task time Immediate…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: The entries in the table denote the costs of assigning a task to a particular person. The plant…
A: Here, I would apply the Hungarian method to this assignment problem, we could see the cost element…
Q: Five jobs must be scheduled for batch processing on a mainframe computer system. The processing…
A:
Q: c) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to…
A: SPT: Sequence Job 1 B 2 A 3 C 4 D 5 E
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.8 B 2.1 C 0.9 D 1 E 1.2 F 1.8 G 4.7…
Q: An independent accountant is planning to prepare tax returns for six of her clients.Prior to her…
A: Step 1: Initially, the minimum number should be selected by considering both the columns. Here, 0.5…
Q: Six jobs are to be processed through a two-step opera- tion. The first operation involves sanding,…
A: JOB OPERATION 1 (HOURS) OPERATION 2 (HOURS) A 10 5 B 7 4 C 5 7 D…
Q: As a production supervisor, Joe decides on Friday afternoon how many units of output his employees…
A: Controlling - Controlling is a role of management that supports to check faults in command to take…
Q: The Earliest Due date (EDD) rule for sequencing a given set of jobs usually ____________ Select…
A: Scheduling is a technique for allocating precious computational resources typically processor time,…
Q: Five jobs must be scheduled for batch processing on a mainframe computer system. The processing…
A:
Q: The maximum cycle time is the sum of all task times when the tasks are running in series (one by…
A: a. True
Q: The times required to complete each of eight jobs in a two-machine flow shop are shown in thetable…
A: A)
Q: FILE UPLOAD: Draw a flowchart for customers fueling their cars at a gas station, starting with the…
A: A flowchart is a sort of outline that addresses a work process or cycle. A flowchart can likewise be…
Q: a) Using the FCFS (first come, first served ) decision The following jobs are waiting to be…
A: In FCFS (First come, First served) decision method for arranging the tasks, the order is the…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Find the Given details below: Given details: Task Immediate Predecessors Time(mins) A - 2.4…
Q: A production line is to be designed for a job with three tasks. The task times are 0.3 minutes, 1.4…
A: Answer: In this mentioned problem, a job has three elemental tasks. Cycle time is the maximum amount…
Q: The operations manager of an assembly and paint shop has five trucks to schedule for repair. He…
A: Solution: Truck A B C D E Assembly (hours) 7 9 8 4 12 Paint (hours) 10 3 7 4 5
Q: Dan is a member of a four person sales team in a gourmet kitchen shop. All of the sales team members…
A: Working in a team is like working together on the same goal and work collaboratively in order to…
Q: The following table shows jobs to be processed at a machine. Determine the processing sequence that…
A: Find the given details below: Given details: Job Processing time (days) Due date (days) A 3 4…
Q: Use the assignment method to obtain a plan that will minimize the processing costs inthefollowing…
A: Find the Given Details below: Given Details: Machine A B C D E Job 1 14 18 20 17 18 2…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: The flow diagram for the product is shown below.
Q: In an evaluation of labor assignment rules when workers are not perfectly interchangeable, Paul. M.…
A: Here the rows represent the workers and the columns represent the work centers.
Q: Suppose we have a school building project. According to the breakdown structure, twenty work…
A: Suppose we've got a faculty building project. in keeping with the breakdown structure, twenty work…
Q: Task 6 is done by Select an answer starting at time Task 7 is done by Select an answer v starting at…
A: The answer is as below:
Q: The constraints governing the jobs are as fo1lows: A and B are start jobs; A controls C, D and E; B…
A: Given data is
Q: Five sorority sisters plan to attend a social function. Each requires hair styling andfitting for a…
A: The schedule of the work of five people is used for minimizing the total expected time required for…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data; Output per day = 70 units per day Available time = 8 hrs or 8*60 = 480min
Q: A market research firm has three clients who have each requested that the firm conduct a sample…
A: The given table is: Statistician Client Client Client A B C 1 150 210 270 2 170 230 220…
Q: Six jobs are to be processed through a two-step operation. The first operation involves sanding, and…
A: In operations, Johnson's rule is a technique of scheduling jobs in two work centers. Its primary…
Q: The following jobs are waiting to be processed at the same machine center. Jobs are logged as they…
A:
Q: Show your step-by-step process using the SPECIAL PURPOSE LINEAR PROGRAMMING: ASSIGNMENT METHOD to…
A: Linear programming, often known as linear optimization, is a method for obtaining the best result…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and producesa toy that…
A: Production is the process of manufacturing the finished products and services using raw materials…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given Information: Available time per day = 8 hours = 480 minutes Forecasted Demand = 100 units per…
Q: A nursing home must schedule nurses in a manner that balances providing adequate patient care while…
A: Given data, Shift Time Minimum number of nurses 1 12 am -4 10 2 4 am- 8 6 3 8 am -12 8…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.4 B 2.2 C 0.9 D 1 E 1.2 F 1.8 G 1.5…
Q: Jse the given tasks and predecessors for this problem. The required cycle time is 25 seconds and…
A: None, Workstation 1 should only have task A assigned
Q: * A group of six jobs is to be processed through a two-machine flow shop. The first operation…
A: For decreasing the inactive time for N occupations booking on two workstations Johnson's Rule is…
Q: A group of six jobs is to be processed through a two-machine flow shop. The first operation involves…
A:
Q: Six jobs are to be processed through a two-stepoperation. The first operation involves sanding, and…
A: Optimal sequence: E D C A B F
Q: Which statement is correct? O a. There could be more than one critical path in a network of…
A: Even if each task is important, just a few are critical. The critical route is a set of…
Q: Question: Balance this line using the longest task time heuristic.
A: The longest-time heuristic method ensures that the most difficult tasks to fit into a station are…
Step by step
Solved in 2 steps
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks Cneeds, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task Fneeds the completion of both the tasks Dand E. Finally,. starting task G needed, task F to be completed. The processing times for tasks. A, B. C, D, E, F. and G are 2.3, 2.1,0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the mostremaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What is the idleness in percentage? a None is the correct answer O b. 81.82 O c. 32.5 O…A manutacturer is designing a product layout for a new product production. It plans to use a production line for B hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 lasks in total. These tasks are namely, A, 8, CD, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed Starting tasks Cneeds, the tack B to be completed. Also, starting task D needed task B to be completed Task E can only start upon completion of Task C. Whescas starting lask F needs the completion of both the tasks D and E Finally, starting task G needed, task Fto be completed. 1the processing times for tasks, A BC D, E F, andG are 28, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks nule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are Select one OaAB, and C ODAB Oc None…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 90 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C D E F and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed, Starting tasks needs the task to be completed. Also starting task D, needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F. and G are 28.2.1,0.9, 10, 1.2.1.8 are 4.7 minutes respectively. How many minimum numbers of workstations are needed? a. 1 b. 6 c. None is correct d. 3 e. 5 please I neef answer along with the formula don't put it on excel
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely. A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task Fneeds the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the THIRD workstation are Select one: a. D, E,…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D. E. F. and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.3, 2.1, 0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What will be the idle time for the FOURTH Workstation? O a. 1.0 O b. 1.4 C. 0.9 O…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. What should be the (calculated) cycle time in minutes? O a. 4.8 Ob. 4.4 None is the correct answer O d. 0.9 O e. 4.5
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of workstations are needed? Select one: O a.2 O b. None is the correct answer O c.6 O d. 8 O e. 4A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the SECOND workstation are Select one: Oa. B and…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, and 4.7 minutes respectively. How many minimum numbers of workstations are needed? O a. 6 O b. None is the correct answer O c. 8 O d. 2 O e. 4
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line with ties broken according to longest task time first, the tasks that will be assigned to the SECOND workstation are: a. B,C and D b. C…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. What should be the (calculated) cycle time in minutes? а. 4.5 O b. None is the correct answer С. 0.9 d. 4.8 е. 4.4A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D andE. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of workstations are needed? Select one: O a. 6 Ob. 2 Oc.4 O d. None is the correct answer O e. 8 Next page Immp to