A steel workshop wants to improve its productivity by making small metal hooks by changing the layout of the workshop into a workstation. The workshop has made observations on the activities of its workers in the workshop and arranged these activities in the form of the table below. Activities Duration (in seconds) Predecessor A 17 None B 15 A C 18 B D 8 B E 12 B F 6 C,D,E G 14 F The workshop aims to produce 225 small metal hooks for 2 hours. Based on this information, please answer the questions below. Sketch a precedence diagram of the above activity Calculate cycle time and the minimum number of workstations to be made Make a grouping of the workstations Calculate the efficiency of the work with the workstation
A steel workshop wants to improve its productivity by making small metal hooks by changing the layout of the workshop into a workstation. The workshop has made observations on the activities of its workers in the workshop and arranged these activities in the form of the table below. Activities Duration (in seconds) Predecessor A 17 None B 15 A C 18 B D 8 B E 12 B F 6 C,D,E G 14 F The workshop aims to produce 225 small metal hooks for 2 hours. Based on this information, please answer the questions below. Sketch a precedence diagram of the above activity Calculate cycle time and the minimum number of workstations to be made Make a grouping of the workstations Calculate the efficiency of the work with the workstation
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
Related questions
Question
(Layout Strategies)
A steel workshop wants to improve its productivity by making small metal hooks by changing the layout of the workshop into a workstation. The workshop has made observations on the activities of its workers in the workshop and arranged these activities in the form of the table below.
Activities |
Duration (in seconds) |
Predecessor |
A |
17 |
None |
B |
15 |
A |
C |
18 |
B |
D |
8 |
B |
E |
12 |
B |
F |
6 |
C,D,E |
G |
14 |
F |
The workshop aims to produce 225 small metal hooks for 2 hours. Based on this information, please answer the questions below.
- Sketch a precedence diagram of the above activity
- Calculate cycle time and the minimum number of workstations to be made
- Make a grouping of the workstations
- Calculate the efficiency of the work with the workstation
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 5 steps with 1 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,