a) The cycle time for the production of a PDA= 20 seconds (round your response to two decimal places). 4 b) The theoretical minimum number of workstations that Amelio can achieve in this assembly line= 3 (round your response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Tasks Assigned to Workstation A Workstation # 1

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as
follows:
Task
A
BCDE
Time
(sec)
12
14
Workstation #
1
8
5
20
Amelio's goal is to produce 180 PDAs per hour.
a) The cycle time for the production of a PDA = 20 seconds (round your response to two decimal places).
Immediate
Predecessor
A
A
B, C
D
b) The theoretical minimum number of workstations that Amelio can achieve in this assembly line = 3 (round your response up to the next whole number).
c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be:
Tasks Assigned to Workstation
A
Transcribed Image Text:Amelio Rodriguez Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task A BCDE Time (sec) 12 14 Workstation # 1 8 5 20 Amelio's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = 20 seconds (round your response to two decimal places). Immediate Predecessor A A B, C D b) The theoretical minimum number of workstations that Amelio can achieve in this assembly line = 3 (round your response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Tasks Assigned to Workstation A
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,