a) The cycle time for the production of a PDA= 20 seconds (round your response to two decimal places). 4 b) The theoretical minimum number of workstations that Amelio can achieve in this assembly line= 3 (round your response up to the next whole number). c) For one to assign the tasks to the actual workstations and be able to use the "theoretical minimum" number, the activity assignment should be: Tasks Assigned to Workstation A Workstation # 1
Q: VW culture to blame for silence over emissions scandal, ex-manager says in trial A former Volkswagen…
A: Volkswagen is a German automobile manufacturer renowned for its quality cars across the globe. VW…
Q: Activities' estimated duration and the time intervals at which the actual progress is analyzed…
A: An activity's estimated duration can be defined as the approximated time that will be taken by a…
Q: The optimistic, most likely and pessimistic times for the tasks comprising a project are shown…
A: Expected time te= (to+4*tm+tp)/6 Variance s2t= ((tp-to)/6)2 Task to tm tp A 5 10…
Q: The following data give the ages (in years) of all six members of a family. 58 51 28 27 22 12…
A: The given data is 58, 51, 28, 27, 22 and 12 to calculate the mean. Population Mean is the value of…
Q: Discuss the characteristics and benefits that Electronic Data Interchange (EDI) has to offer an…
A: Electronic data interchange, abbreviated EDI, is undoubtedly the process of sending business…
Q: The units of Manganese Plus available for sale during the year were as follows: Mar. 1 June 16 Nov.…
A: Given data: Unit Cost per unit Amount 1-Mar Inventory 23 29 667 16-Jun Purchases 32 30…
Q: A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If…
A: NOTE: We are allowed to do one question only. Given: Critical path duration (mu) = 105 Variance (v)…
Q: Your supervisor, Lisa Lehmann, has asked that you report on the output of a machine on the factory…
A: Find the Calculation methods below: Upper Control Limit (UCLx) = Ẍ + A2 ṜLower Control Limit (LCLx)…
Q: ABC INVENTORY CLASSIFICATION A company trades with a number of items and the management is…
A: A' items – items account for 85% of the annual consumption value of the items (asked 82% so taken up…
Q: The table below shows the sales figures for a brand of shoe over the last 12 months. Months January…
A: Forecasting method is the method that determines the future values according to the previous years'…
Q: Max Z = 6X1 + 18X2+20X3 Sub to X1 + X2 +X3 = 60 10X1 +15X2 +20X3 = 900 2X1 + 3X2 +3X3≤100…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: What is supplier management in operation management ?
A: Introduction : The practice of managing and improving communications with an organization's vendors…
Q: For the network schedule shown below, which statement is true? a. This is an example of the…
A: Statement c is true because Activities B and C are concurrently occur
Q: 3 LL 4 H 6
A: Given data: Activity Duration A 2 B 4 D 1 E 5 F 4 G 1 H 3
Q: It costs Gordon $1 to move 1 work piece 1 foot. The weekly total material handling cost of the…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: 3. Refer to Table S6.1 - Factors for Computing Control Chart Limits (3 sigma) LOADING... for this…
A: Given data: Overall mean X= = 57.75 lb. Average range R- = 1.54 lb Sample size (n) = 7 Number of…
Q: curement cycle 2. List ways in which each component could be corrupted 3. Identify possible…
A: Procurement is a catch-all phrase for all aspects of purchasing, ranging from vendor selection and…
Q: A public transport corporation has hired 2000 buses for the different routes for the passengers of…
A: Recruitment usually includes the process of identifying interested applicants who've already…
Q: My Happy Feet Company manufactures athletic shoes. The company wants to establish a p chart to…
A: Find the Calculation methods below: Fraction Defectives = Number of DefectivesSample sizeCentral…
Q: Race One Motors is an Indonesian car manufacturer. At its largest manufacturing facility, in…
A: Given Production per day p = 290 / day Annual demand D = 12700 / year d = 12700/250 = 50.8 Working…
Q: Clinic needs to order influenza vaccines for the next flu season. The Clinic charges its patients…
A:
Q: y local in operation manageme
A: Operations management is crucial to corporate operations because it establishes the organizational…
Q: Problem 12-2 (Algo) A local distributor for a national tire company expects to sell approximately…
A: Annual demand = D = 9780 tires Annual carrying cost per tire = H = $18 Ordering cost = S = $85 No.…
Q: a. Using the following, forecast the sales for the months up to january the following year:- i. A…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Cartons of Plaster of Paris are supposed to weigh exactly 32 oz. Inspectors want to develop process…
A: Find the Calculation methods below: Mean Chart: Upper Control Limit (UCL): Ẍ+A2 Ṝ Lower Control…
Q: Prior to conducting double exponential smoothing a simple linear regression is conducted and the…
A: Double exponential smoothing computes a trend equation through the data using a special weighting…
Q: 2. Find the initial basic feasible solution of the following Transportation Problem by NWCR. The…
A: The northwest corner method is a problem-solving technique that is used in operations management.…
Q: She must travel to Kenya to check on quality and transportation. The trip will cost $2,500. The…
A: Cost of the trip (C) = 2500 Cost of handbag (S) = 10 Shipping cost through the postal system (P) = 2…
Q: Role of cGMP in the Quality Control unit in the pharmaceutical industry please define this…
A: Quality if the utmost priority in pharmaceutical products as they are directly related to health. To…
Q: If Amazon had ships to transport cargo, where in the shipping cycle would they take risks and maybe…
A: The shipping cycle is a concept that explains the response of shipping companies to supply and…
Q: vering the following critical aspects; 1. Identify the risks to start preparing a risk register and…
A: All undertakings have a certain amount of risk, which presented both possibilities and hazards for…
Q: Sycamore Plastics (SP) is a manufacturer of polyethylene plastic pellets used as a raw material by…
A: Solver constraints:
Q: What are the importance of Quality control department for the national and international…
A: The quality control department is the one who is responsible for the quality of products and…
Q: 5. Consider the transportation problem having the following parameter table: Destination 1…
A: Problem Table is D1 D2 D3 Supply S1 3 2.7 0 5 S2 2.9 2.8 0 4 Demand 3 4 2…
Q: Jack Ltd is a market leader in the manufacture of apple juice. They operate a reorder level system…
A: Inventory is the raw material that is particularly used in the production of goods. Inventory is the…
Q: Table 4.1 shows his list of the various activities needed for replacing an existing boiler with an…
A: Path with the longest duration is the critical path. Activities which have 0 slack value denotes the…
Q: what do I mean when I say that inventory costing methods are not related to the physical flow of…
A: The price per unit of goods acquired might vary. Hence it is crucial for retailing, manufacturing,…
Q: Mr. Jack is in the process of expanding his manufacturing business. He decided to open a plant in…
A: i) Total Cost (Location A) = 60000+30x Total Cost (Location B) = 80000+20x Total Cost (Location C) =…
Q: Compute the labor time required to produce 8 and 16 units. b. Assume that labor time costs $125 per…
A: In operations management, the learning rate is used to measure the efficiency of inventory…
Q: a. Identify the possible effects of the components of the procurement cycle
A: Procurement cycle refers to the process of selecting the vendor, buying goods from them and taking…
Q: Inquiries of warehouse personnel concerning possibly obsolete or slowmoving inventory items provide…
A: Answer (A) is incorrect because inquiries of warehouse personnel concerning possible obsolete or…
Q: You are shipping 3000 boxes to Malta. Each box is 35x32x18 inches, Each box weighs 88 kg How many…
A: Given: Dimensions of 20' container = 232*90*90 Dimensions of box = 35*32*18
Q: A teller at a drive-up window at a bank had the following service times (in minutes) for 20 randomly…
A: Find the Given details below: Samples Observations 1 2 3 4 1 4.5 4.6 4.5 4.7 2 4.2 4.5 4.6…
Q: I only need help Question 4 please!! A large insurance company maintains a central computing…
A: Given data: Arrival rateλ = 44 calls per hour Service rate μ= 24 calls per hour
Q: Instruction: 1. Solve the problem on Linear Programming Model Using (a) Graphical Method, and (b)…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: Item A has a gross requirement of 2,400 in week 6. Currently, there are 200 Item A's on hand with…
A: Given, Gross requirement in week 6 = 2400 On hand inventory in week 1 = 200 Scheduled receipts in…
Q: فعالیات انجاز مشروع والمطلوب اعدا تحديد المسار الحرج باستخدام الزمن المـ
A: The critical path is the series of steps that must be completed in order to complete a project.…
Q: Problem 9a: Jones Surgicenter uses 90,000 bags of IV solution annually. The optimal safety stock…
A: Given, Annual demand D = 90000 Order cost S = $15 Holding cost H = 20% of $1.5 = $0.3
Q: South Beach University is conducting an online exam. There are 1,200 students taking this exam.…
A: Little’s Law: Little’s Law is defined as the long-term average number of customers…
Q: An M/M/4 system has an arrival rate of 15 customers per hour. Each server has a service rate of 7…
A: Given, Arrival rate a = 15 cust / hr Service rate s = 7 cust / hr Number of servers m= 4
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 5 images
- Canine Kernels Company (CKC) manufactures two differenttypes of dog chew toys (A and B, sold in 1,000-count boxes)that are manufactured and assembled on three differentworkstations (W, X, and Y) using a small-batch process (seeFigure 5.12). Batch setup times are negligible. The flowchartdenotes the path each product follows through the manu-facturing process, and each product’s price, demand perweek, and processing times per unit are indicated as well.Purchased parts and raw materials consumed during pro-duction are represented by inverted triangles. CKC can makeand sell up to the limit of its demand per week; no penaltiesare incurred for not being able to meet all the demand. Eachworkstation is staffed by a worker who is dedicated to workon that workstation alone, and is paid $6 per hour. Totallabor costs per week are fixed. Variable overhead costs are$3,500/week. The plant operates one 8-hour shift per day, or40 hours/week. Which of the three workstations, W, X, or Y,has the highest…The project manager of the gas station project shown inFigure 7.3 needs to change the project’s WBS so that itcan be compared with cost and productivity informationcollected by the company. Level II should be changedto General Field Administration, Earthwork, ConcreteWork, Masonry Work, Metal Work, Carpentry, and Others.Complete the WBS of this project using this new arrangementfor Level II.DEFINE CONWIP (CONstant Work-In-Process)
- Suppose that a firm is considering moving from a batch process to an assembly-line process to better meet evolving market needs. What concerns might the following functions have about this proposed process change: marketing, finance, human resources, accounting, and information systems?Th3 task is pr0vided in th3 pictur3. (creat3 a DATA FLOW DIAGRAM for the Creat3 a DATA FLOW DIAGRAM for the CASH RECEIPTS SYSTEM that is pr0vided in the pictur3 I WILL RAT3 TH3 TUT0R H3LPFUL IF ANSW3RED ASAPd. What is the efficiency of your line balance? Use the theoretical minimum number of workstations in your calculation. (Round your answer to 1 decimal place.) Efficiency
- A manufacturing firm that produces a standardized product, not made of discrete parts, with little-to-no customization, with high demand, is most likely to use this type of process. Select one: a. project b. flow shop € job shop d. continuous flowHow to split task between operational routines (repetitive tasks, business as usual) and dynamic routines (transformations, NPD, innovation etc.) for different functions (sales, manufacturing, HR, etc.)?An assembly line is to be designed to operate 13 hours per day and supply a steady demand of 325 units per day. Here are the tasks and their performance times: TASK PRECEDINGTASKS PERFORMANCE TIME (SECONDS) TASK PRECEDINGTASKS PERFORMANCETIME (SECONDS) a — 48 g d 43 b — 58 h e 38 c — 73 i f 23 d a 63 j g 33 e b 88 k h, i 53 f c 23 l j, k 67 A) What is the efficiency of your line balance? B) Suppose demand increases by 10 percent. How would you react to this? Assume that you can operate only 13 hours per day in regular time. (Round your answers to the nearest whole number.)
- Tasty Tim’s Tasty Tim’s is a specialty taco restaurant. The following tasks are required for the successful assembly of a Tasty taco (times are in seconds per taco): Chop and trim meat – 30 Chop vegetables – 20 Grill meat – 240 Grill vegetables – 180 Prepare toppings - Lettuce - 10 - Tomato - 15 - Guacamole - 40 Assemble taco - Add meat - 5 - Add vegetables - 5 - Add cheese - 5 - Add toppings - 10 Wrap taco - 20 During the lunch hour, Tasty Tim’s encounters demand for 120 tacos. A) What is the labor content of one of Tasty Tim’s tacos? B) What is the Takt time (in seconds/unit) takt time for Tasty Tim’s taco shop? C) In an ideal world, how many workers should Tim hire to make tacos? D) During off-peak afternoon hours, demand at Tasty Tim’s drops to 40 tacos each hour. How many employees should Tim schedule to work during the afternoon? Again, ignore any effects of idle time or inefficiency due to poor line balancing.2) Regarding Data Flow Diagram (DFD), which of the following statement is/are TRUE? Data flows must be an input or output of a Process Box. Physical flows are sometimes represented by a dotted line. Data Flow diagram (DFD) is a type of diagram that represents the sequences of a process or workflow. External entities (people, place or organizations) are sources or destinations of data that are lying outside the context of the system. Data stores can hold permanent, temporary, historical or extract data. Files receive inputs and outputs only from Processes, NOT from Externals or other Files. None of the above.What does the activity ratio measure in the Value Stream? The percentage of time spent on value-added activitiesThe percentage of time spent on delays to the number of processes in the Value StreamThe percentage of time spent on non-value-added activitiesThe percentage of time spent on manual activities