ABC Industry operates 6 days a week. There are two 8-hours shifts each day, with a half-hour break for lunch in each shift. The plant is shut down on Sundays for regular maintenance. The weekly demand for the product is 720 units. What is the TAKT time?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question

ABC Industry operates 6 days a week. There are two 8-hours shifts each day, with a half-hour break for lunch in each shift. The plant is shut down on Sundays for regular maintenance.

The weekly demand for the product is 720 units. What is the TAKT time?

 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,