Activity A B C D E F G H I J K L Duration 5 6 5 3 3 4 4 7 8 2 3 2 IPA A A A B B, C D B,C,G E, F F H, J I, J
Activity A B C D E F G H I J K L Duration 5 6 5 3 3 4 4 7 8 2 3 2 IPA A A A B B, C D B,C,G E, F F H, J I, J
Chapter16: Moment-distribution Method
Section: Chapter Questions
Problem 22P
Related questions
Question
For the following schedule, draw the node network, perform the CPM calculations,
mark the critical path, and complete the table.