Activity ES LS EF LF Slack Activity A 0.00 V 0.00 v 11.00 v 11.00 v 0.00 V Yes v B 0.00 V 7.00 V 10.00 V 17.00 V 7.00 V No v 11.00 V 11.00 V 18.00 x 18.00 x 0.00 V Yes v D. 10.00 V 17.00 V 15.00 V 22.00 V 7.00 v No v 18.00 X 25.00 x 25.00 X Yes v E 18.00 x 0.00 15.00 V 22.00 v 25.00 v 32.00 V No v F 7.00 25.00 x 32.00 V 0.00 V Yes v 25.00 x 32.00 V Determine the critical path in the project network. A-C-E-G V What is the expected duration and variance of the critical path? If required, round your answer to two decimals. Expected duration = 32 v Variance = 2.16 V What is the likelihood that the project will be completed within 30 days? If required, round your answer to four decimals. Note: Use Appendix B to identify the probability. Likelihood = -1.369 x If activity B is delayed by six days beyond its early start time, how does this affect the expected project duration? If required, round your answer to one decimal place. A delay of 6 days to activity B will not affect the time to complete this project because activity B has a slack of 7 v days. JOOL

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
ChapterC: Cases
Section: Chapter Questions
Problem 5.3SA
icon
Related questions
Question
Activity
ES
LS
EF
LF
Slack
Activity
A
0.00
0.00
11.00
11.00
0.00
Yes
В
0.00
7.00
10.00
17.00 V
7.00 V
No
C
11.00
11.00
18.00
X
18.00
0.00 V
Yes
D
10.00
17.00 V
15.00 V
22.00 V
7.00
No v
E
18.00 X
18.00 X
25.00 X
25.00
0.00
Yes v
F
15.00
22.00 V
25.00
32.00 V
7.00
No v
25.00
25.00 X
32.00
32.00
0.00
Yes
c. Determine the critical path in the project network.
A-C-E-G V
d. What is the expected duration and variance of the critical path? If required, round your answer to two decimals.
Expected duration =
32 V
Variance =
2.16 V
e. What is the likelihood that the project will be completed within 30 days? If required, round your answer to four decimals. Note: Use Appendix B to identify the probability.
Likelihood =
-1.369
f. If activity B is delayed by six days beyond its early start time, how does this affect the expected project duration? If required, round your answer to one decimal place.
A delay of 6 days to activity B will not
affect the time to complete this project because activity B has a slack of
7
days.
Transcribed Image Text:Activity ES LS EF LF Slack Activity A 0.00 0.00 11.00 11.00 0.00 Yes В 0.00 7.00 10.00 17.00 V 7.00 V No C 11.00 11.00 18.00 X 18.00 0.00 V Yes D 10.00 17.00 V 15.00 V 22.00 V 7.00 No v E 18.00 X 18.00 X 25.00 X 25.00 0.00 Yes v F 15.00 22.00 V 25.00 32.00 V 7.00 No v 25.00 25.00 X 32.00 32.00 0.00 Yes c. Determine the critical path in the project network. A-C-E-G V d. What is the expected duration and variance of the critical path? If required, round your answer to two decimals. Expected duration = 32 V Variance = 2.16 V e. What is the likelihood that the project will be completed within 30 days? If required, round your answer to four decimals. Note: Use Appendix B to identify the probability. Likelihood = -1.369 f. If activity B is delayed by six days beyond its early start time, how does this affect the expected project duration? If required, round your answer to one decimal place. A delay of 6 days to activity B will not affect the time to complete this project because activity B has a slack of 7 days.
Problem 9-09 (Algorithmic)
At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the
requisite activities and related information in the following table (duration estimates measured in days).
Immediate
Most
Activity
Predecessor(s)
Optimistic
Probable
Pessimistic
A: Negotiate contract with
10
11
12
selected musicians
B: Reserve site
8
10
12
C: Manage travel logistics
A
2
7
9.
for music group
D: Screen & hire
4
security personnel
E: Arrange advertising
C
7
7
7
& ticketing
F: Hire parking staff
А, D
8
9.
16
G: Arrange concession sales
E
7
11
Transcribed Image Text:Problem 9-09 (Algorithmic) At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days). Immediate Most Activity Predecessor(s) Optimistic Probable Pessimistic A: Negotiate contract with 10 11 12 selected musicians B: Reserve site 8 10 12 C: Manage travel logistics A 2 7 9. for music group D: Screen & hire 4 security personnel E: Arrange advertising C 7 7 7 & ticketing F: Hire parking staff А, D 8 9. 16 G: Arrange concession sales E 7 11
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 6 images

Blurred answer
Knowledge Booster
Decision theory
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,