Activity Predecessor Activity Time (month) 30 A 8 B 8 B 5 2 D,E 25 A 10 Η GG 3 5 A 5 1,J 15 F,K 2

Foundations of Business - Standalone book (MindTap Course List)
4th Edition
ISBN:9781285193946
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Chapter11: Building Customer Relationships Through Effective Marketing
Section: Chapter Questions
Problem 24CC
icon
Related questions
icon
Concept explainers
Topic Video
Question

1)Draw the project network.

2)Calculate the early start, early finish, late start, late finish times of the project.

3)Find the critical path of the project.

4)Calculate the time required to complete the project.

5)Calculate the free time in the project network.

(Also, show the times you want on the table you will create.)

Activity
Predecessor Activity
Time (month)
A
30
B
A
8
В
8
D
B
E
2
F
D,E
25
G
A
10
H
C,G
3
E
5
5
K
1,J
15
F,K
2
Transcribed Image Text:Activity Predecessor Activity Time (month) A 30 B A 8 В 8 D B E 2 F D,E 25 G A 10 H C,G 3 E 5 5 K 1,J 15 F,K 2
Expert Solution
steps

Step by step

Solved in 2 steps with 3 images

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Foundations of Business - Standalone book (MindTa…
Foundations of Business - Standalone book (MindTa…
Marketing
ISBN:
9781285193946
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning
Foundations of Business (MindTap Course List)
Foundations of Business (MindTap Course List)
Marketing
ISBN:
9781337386920
Author:
William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:
Cengage Learning