d. Determine the probability that the team and the contractor will be in place and the project started within: (i) 7 months (about 30 weeks), (ii) 9 months (about 39 weeks). e. Find the period (in weeks) by which you would be 90% sure of completing the process.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Time (weeks)
Optimistic Most Likely
Pessimistic
Activity
A
Description
Select project manager
Develop team recruitment plan
Implement team recruitment plan
Staff needs assessment
Staff recruitment advertising
Staff selection evaluation procedures
Select project team members
Develop contractor bid requirements
Develop contractor bid evaluation procedure
Staff applicant evaluation and selection
Solicit contractor bids
Predecessor
m
1
1
3
C
6.
В
1
3
E
D
1
1
1
F
1
2
4
G
4
6.
H.
1
6.
G, H
E, F, G
I, J
3
4
K
4
10
Contractor bid evaluation
K
3
6.
8.
M
Select contractor and complete negotiations
2
3
||ABBABCA
Transcribed Image Text:Time (weeks) Optimistic Most Likely Pessimistic Activity A Description Select project manager Develop team recruitment plan Implement team recruitment plan Staff needs assessment Staff recruitment advertising Staff selection evaluation procedures Select project team members Develop contractor bid requirements Develop contractor bid evaluation procedure Staff applicant evaluation and selection Solicit contractor bids Predecessor m 1 1 3 C 6. В 1 3 E D 1 1 1 F 1 2 4 G 4 6. H. 1 6. G, H E, F, G I, J 3 4 K 4 10 Contractor bid evaluation K 3 6. 8. M Select contractor and complete negotiations 2 3 ||ABBABCA
d. Determine the probability that the team and the contractor will be in place and the project
started within: (i) 7 months (about 30 weeks), (ii) 9 months (about 39 weeks).
e. Find the period (in weeks) by which you would be 90% sure of completing the process.
Transcribed Image Text:d. Determine the probability that the team and the contractor will be in place and the project started within: (i) 7 months (about 30 weeks), (ii) 9 months (about 39 weeks). e. Find the period (in weeks) by which you would be 90% sure of completing the process.
Expert Solution
steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.