Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in d in the fo a following table: Activity A 8 С D E Normal Time Crash Time Normal (weeks) (weeks) Cost $2,200 3 $2,200 $600 $2,500 2 3 1 3 4 3 2 2 $1,000 $3,400 $1,400 a) Based on the given information regarding the activities for the project, the project length 16 weeks. b) The total cost required for completing this project on normal time = $13300 c) For reducing the duration of the project by one week, the activity that should be crashed first in activity D The cost of the project based on the first activity selected for crashing will increase by $ 80 weeks d) The maximum weeks by which the project can be reduced by crashing Total cost of crashing the project to minimum (or maximum weeks possible) Total Cost with Immediate Crashing Predecessor(s). $2,800 $2,800 $600 $2,820 $1,450 $4,000 $1,900 A B DE

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question
please solve all parts within 30 minutes.
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this
project are listed in the following table:
Activity
A
8
C
D
E
F
G
Normal Time Crash Time Normal
(weeks)
49
Cost
2
3
8
Total Cost
with
Immediate
Crashing Predecessor(s)
$2,800
$2,800
$600
$600
$2,500
$2,820
$1,000 $1,450
$3,400
$4,000
$1,400
$1,900
(weeks)
3
1
3
4
3
2
2
d) The maximum weeks by which the project can be reduced by crashing
Total cost of crashing the project to minimum (or maximum weeks possible) $
$2,200
$2,200
a) Based on the given information regarding the activities for the project, the project length - 16 weeks.
b) The total cost required for completing this project on normal time = $13300
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D
The cost of the project based on the first activity selected for crashing will increase by $ 80-
weeks
D, E
Transcribed Image Text:Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity A 8 C D E F G Normal Time Crash Time Normal (weeks) 49 Cost 2 3 8 Total Cost with Immediate Crashing Predecessor(s) $2,800 $2,800 $600 $600 $2,500 $2,820 $1,000 $1,450 $3,400 $4,000 $1,400 $1,900 (weeks) 3 1 3 4 3 2 2 d) The maximum weeks by which the project can be reduced by crashing Total cost of crashing the project to minimum (or maximum weeks possible) $ $2,200 $2,200 a) Based on the given information regarding the activities for the project, the project length - 16 weeks. b) The total cost required for completing this project on normal time = $13300 c) For reducing the duration of the project by one week, the activity that should be crashed first is activity D The cost of the project based on the first activity selected for crashing will increase by $ 80- weeks D, E
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,