1. Draw network diagram neatly using this chart provided:

Activity

Predecessor

Normal time

Normal cost

Crash time

Crash cost

Max Crash Time

Slope

A

 

5

$200

4

$350

   

B

A

8

$220

8

$220

   

C

B

6

$250

4

$650

   

D

A

9

$500

5

$600

   

E

A,C

10

$150

9

$500

   

F

E

10

$500

9

$650

   

G

D,F

8

$400

6

$900

   
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing