Given the following line balance data in the table below. For eight hours of operating time per day and a desired output rate of 960 units per day, what is the percentage of idle time which assign tasks in order of most following tasks. The percentage of idle time is %. (Write the answer as 57.00,6.90,1.01) * Task Predecessor Time (seconds) none 15 14 V 7 W 6. V 8. y W, X 10 y 21

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
100%
What is the line balancing
Given the following line balance data in the table below. For eight hours of
operating time per day and a desired output rate of 960 units per day, what is
the percentage of idle time which assign tasks in order of most following tasks.
The percentage of idle time is
%. (Write the answer as 57.00 , 6.90 , 1.01) *
Task
Predecessor Time (seconds)
none
15
u
14
V
7
W
6.
V
8.
y
W, X
10
y
21
Transcribed Image Text:Given the following line balance data in the table below. For eight hours of operating time per day and a desired output rate of 960 units per day, what is the percentage of idle time which assign tasks in order of most following tasks. The percentage of idle time is %. (Write the answer as 57.00 , 6.90 , 1.01) * Task Predecessor Time (seconds) none 15 u 14 V 7 W 6. V 8. y W, X 10 y 21
Given the following line balance data in the table below. What is the appropriate
cycle time for eight hours of operating time per day and a desired output rate of
seconds. (Write the answer as 57.00,
960 units per day? The cycle time is
6.90, 1.01) *
Task
Predecessor
Time (seconds)
none
15
u
t
14
V
t.
u
6.
W
V
8.
W, X
10
y
21
Transcribed Image Text:Given the following line balance data in the table below. What is the appropriate cycle time for eight hours of operating time per day and a desired output rate of seconds. (Write the answer as 57.00, 960 units per day? The cycle time is 6.90, 1.01) * Task Predecessor Time (seconds) none 15 u t 14 V t. u 6. W V 8. W, X 10 y 21
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,