In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract as follows: Cost incurred during the year Estimated costs to complete as of year-end 2024 2025 $ $ 2,610,000 3, 162,000 6,390,000 2,028,000 2026 2,230, 800 0

CONCEPTS IN FED.TAX.,2020-W/ACCESS
20th Edition
ISBN:9780357110362
Author:Murphy
Publisher:Murphy
Chapter3: Income Sources
Section: Chapter Questions
Problem 88P
icon
Related questions
Question
Do not give answer in image formet and hand writing
Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9]
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa
Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is
as follows:
Costs incurred during the year
Estimated costs to complete as of
year-end
Revenue
Gross profit (loss)
2024
2024
Cost incurred during the year
Estimated costs to complete as of
year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
2025
$
2,610,000 3,162,000 2,230, 800
6,390,000 2,028,000
0
2025
$
Problem 6-10 (Algo) Part 5
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming
the following costs incurred and costs to complete information.
Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar
amount. Loss amounts should be indicated with a minus sign.
2024
$ 2,610,000
6,390,000
2026
$
2,100,000 3,672,000 4,228,000
1,850,000 3,000,000 5,150,000
2026
2025
$ 3,850,000
4,200,000
2026
$ 4,050,000
0
Transcribed Image Text:Problem 6-10 (Algo) Long-term contract; revenue recognition over time [LO6-8, 6-9] [The following information applies to the questions displayed below.] In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Costs incurred during the year Estimated costs to complete as of year-end Revenue Gross profit (loss) 2024 2024 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. 2025 $ 2,610,000 3,162,000 2,230, 800 6,390,000 2,028,000 0 2025 $ Problem 6-10 (Algo) Part 5 5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information. Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign. 2024 $ 2,610,000 6,390,000 2026 $ 2,100,000 3,672,000 4,228,000 1,850,000 3,000,000 5,150,000 2026 2025 $ 3,850,000 4,200,000 2026 $ 4,050,000 0
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L