In what sequence will the jobs be completed if the DDATE rule is used? Group of answer choices a) A-C-D-B b) C-A-D-B c) A-B-C-D d) C-D-A-B

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question

33) Workstation #1

Given the following queue of 4 jobs to be processed at Workstation #1:

Job Processing Time (Days) # Days Until Due
A 5 12
B 11 20
C 7 10
D 9 14

In what sequence will the jobs be completed if the DDATE rule is used?

Group of answer choices
a) A-C-D-B
b) C-A-D-B
c) A-B-C-D
d) C-D-A-B
 
34)What is the average completion time if the FCFS rule is used?
 
Group of answer choices
a) 76
b) 72
c) 31
d) 18
e) 19
f) 56
 
 
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Optimization models
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,