Marissa Manufacturing is presented with the following two mutually exclusive projects. The required return for both projects is 17 percent. Year 0 Project M -$ 142,000 Project N -$ 353,000 1 63,300 153,500 2 81,300 178,000 3 72,300 4 58,300 138,500 108,000 a. What is the IRR for each project? Note: Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16. b. What is the NPV for each project? Note: Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16. c. Which, if either, of the projects should the company accept? a. Project M Project N b. Project M Project N c. Accept project % %

EBK CONTEMPORARY FINANCIAL MANAGEMENT
14th Edition
ISBN:9781337514835
Author:MOYER
Publisher:MOYER
Chapter10: Capital Budgeting: Decision Criteria And Real Option
Section: Chapter Questions
Problem 15P
Question
Marissa Manufacturing is presented with the following two mutually exclusive projects. The required return for both
projects is 17 percent.
Year
0
Project M
-$ 142,000
Project N
-$ 353,000
1
63,300
153,500
2
81,300
178,000
3
72,300
4
58,300
138,500
108,000
a. What is the IRR for each project?
Note: Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places,
e.g., 32.16.
b. What is the NPV for each project?
Note: Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.
c. Which, if either, of the projects should the company accept?
a. Project M
Project N
b. Project M
Project N
c. Accept project
%
%
Transcribed Image Text:Marissa Manufacturing is presented with the following two mutually exclusive projects. The required return for both projects is 17 percent. Year 0 Project M -$ 142,000 Project N -$ 353,000 1 63,300 153,500 2 81,300 178,000 3 72,300 4 58,300 138,500 108,000 a. What is the IRR for each project? Note: Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16. b. What is the NPV for each project? Note: Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16. c. Which, if either, of the projects should the company accept? a. Project M Project N b. Project M Project N c. Accept project % %
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
Financial Management: Theory & Practice
Financial Management: Theory & Practice
Finance
ISBN:
9781337909730
Author:
Brigham
Publisher:
Cengage