Questions: A. How much is the Project Construction Cost for the Project Definition Phase? • B. How much should the Client pay you after the Signing of the Service Agreement? ● C. How much should the client pay you after the Design Development Phase? • D: How much should the client pay ● you after the Contract Documents Phase? E. How much is the running total of your RPF after the Bidding and Negotiation Phase? • F. How much is the total RPF for the entire project?

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter13: Pricing Subcontractors' Work
Section: Chapter Questions
Problem 2RQ
icon
Related questions
Question
100%
UPVOTE WILL BE GIVEN. PLEASE WRITE THE COMPLETE SOLUTIONS LEGIBLY. ANSWER IN 2 DECIMAL PLACES. THE TYPE OF SERVICE IS DAEDS.
Bidding and
Negotiation
Phase
Construction
Questions:
Php
40,000,000.00
Php
41,000,000.00
APCC
FPCC
●
A. How much is the Project Construction
Cost for the Project Definition Phase?
• B. How much should the Client pay
you after the Signing of the Service
Agreement?
C. How much should the client pay
you after the Design Development Phase?
D: How much should the client pay
you after the Contract Documents Phase?
.
E. How much is the running total of your
RPF after the Bidding and Negotiation
Phase?
• F. How much is the total RPF for the entire
project?
Transcribed Image Text:Bidding and Negotiation Phase Construction Questions: Php 40,000,000.00 Php 41,000,000.00 APCC FPCC ● A. How much is the Project Construction Cost for the Project Definition Phase? • B. How much should the Client pay you after the Signing of the Service Agreement? C. How much should the client pay you after the Design Development Phase? D: How much should the client pay you after the Contract Documents Phase? . E. How much is the running total of your RPF after the Bidding and Negotiation Phase? • F. How much is the total RPF for the entire project?
PROBLEM (SHOW YOUR SOLUTIONS) : A client hired you
to be the architect for his 3-storey residence. The house
has a total floor area 800 sqm, with an estimated market
cost of PHP 50,000/sqm. The following table shows the
sequence of design phases and project construction costs
for the respective phases.
DESIGN
PHASE
Project
Definition
Phase
Schematic
Design Phase
Design
Development
Phase
Contract
Documents
Phase
PROJECT
CONSTRUCTIO
N COST
Floor Area: 800
sqm
Cost: Php
50,000.00/sqm
Php
40,000,000.00
Php
45,000,000.00
Php
45,000,000.00
PPCC
(Updated)
PPCC
(Updated)
PPCC
(Updated)
PPCC
Transcribed Image Text:PROBLEM (SHOW YOUR SOLUTIONS) : A client hired you to be the architect for his 3-storey residence. The house has a total floor area 800 sqm, with an estimated market cost of PHP 50,000/sqm. The following table shows the sequence of design phases and project construction costs for the respective phases. DESIGN PHASE Project Definition Phase Schematic Design Phase Design Development Phase Contract Documents Phase PROJECT CONSTRUCTIO N COST Floor Area: 800 sqm Cost: Php 50,000.00/sqm Php 40,000,000.00 Php 45,000,000.00 Php 45,000,000.00 PPCC (Updated) PPCC (Updated) PPCC (Updated) PPCC
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Estimation process
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,