Standard Quantity 15 sq. ft. 10 hrs. Standard Price (Rate) $ 5 per sq. ft. $15 per hr. Standard Unit Cost $ 75.00 Direct materials (fiberglass) Direct labor 150.00 Variable manufacturing overhead (based on direct labor hours) Fixed manufacturing overhead ($24, 000 + 300 units) 10 hrs. $ 6 per hr. 60.00 80.00 Rip Tide has the following actual results for the month of June: Number of units produced and sold Number of square feet of fiberglass used Cost of fiberglass used Number of labor hours worked 329 5,090 $27,995 3,230 $50,711 $14,090 $25,450 Direct labor cost Variable overhead cost Fixed overhead cost Required: 1. Calculate the direct materials price, quantity, and total spending variances for Rip Tide. 2. Calculate the direct labor rate, efficiency, and total spending variances for Rip Tide. 3. Calculate the variable overhead rate, efficiency, and total spending variances for Rip Tide. 4. Calculate the fixed overhead spending (budget) and volume variances for Rip Tide.

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter5: Process Costing
Section: Chapter Questions
Problem 2PB: The following product costs are available for Kellee Company on the production of eyeglass frames:...
icon
Related questions
icon
Concept explainers
Topic Video
Question
Standard
Standard Price
Standard
Quantity
15 sq. ft.
(Rate)
$ 5 per sq. ft.
$15 per hr.
Unit Cost
Direct materials (fiberglass)
$ 75.00
Direct labor
10 hrs.
150.00
Variable manufacturing overhead
(based on direct labor hours)
Fixed manufacturing overhead
($24, 000 + 300 units)
10 hrs.
$ 6 per hr.
60.00
80.00
Rip Tide has the following actual results for the month of June:
Number of units produced and sold
Number of square feet of fiberglass used
Cost of fiberglass used
Number of labor hours worked
329
5,090
$27,995
3,230
$50,711
$14,090
$25,450
Direct labor cost
Variable overhead cost
Fixed overhead cost
Required:
1. Calculate the direct materials price, quantity, and total spending variances for Rip Tide.
2. Calculate the direct labor rate, efficiency, and total spending variances for Rip Tide.
3. Calculate the variable overhead rate, efficiency, and total spending variances for Rip Tide.
4. Calculate the fixed overhead spending (budget) and volume variances for Rip Tide.
Transcribed Image Text:Standard Standard Price Standard Quantity 15 sq. ft. (Rate) $ 5 per sq. ft. $15 per hr. Unit Cost Direct materials (fiberglass) $ 75.00 Direct labor 10 hrs. 150.00 Variable manufacturing overhead (based on direct labor hours) Fixed manufacturing overhead ($24, 000 + 300 units) 10 hrs. $ 6 per hr. 60.00 80.00 Rip Tide has the following actual results for the month of June: Number of units produced and sold Number of square feet of fiberglass used Cost of fiberglass used Number of labor hours worked 329 5,090 $27,995 3,230 $50,711 $14,090 $25,450 Direct labor cost Variable overhead cost Fixed overhead cost Required: 1. Calculate the direct materials price, quantity, and total spending variances for Rip Tide. 2. Calculate the direct labor rate, efficiency, and total spending variances for Rip Tide. 3. Calculate the variable overhead rate, efficiency, and total spending variances for Rip Tide. 4. Calculate the fixed overhead spending (budget) and volume variances for Rip Tide.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 6 images

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College