Sturgill Manufacturing Inc. needs to predict the numbers of machines and employees required to produce its planned production for the coming year. The plant runs three shifts continuously during the workweek, for a total of 120 hours of capacity per week. The shop efficiency (the percent of total time available for production), which accounts for setups, changeovers, and maintenance, averages 70% with a standard deviation of 5%, which reduces the weekly capacity. Six key parts are produced, and the plant has three different types of machines to produce each part. The machines are not interchangeable as they each have a specific function. The time to produce each part on each machine varies. The mean time and standard deviation (in hours) to produce each part on each machine are shown below: Mean Time Part Type Machine A Machine B Machine C 1 3.5 2.6     8.9 2 3.4 2.5  8 3 1.8 3.5 12.6 4 2.4 5.8 12.5 5 4.2 4.3 28  6 4    4.3 28  Standard Deviation Part Type Machine A Machine B Machine C 1 0.15 0.12 0.15 2 0.15 0.12 0.15 3 0.1   0.15 0.25 4 0.15 0.15 0.25 5 0.15 0.15 0.5   6 0.15 0.15 0.5   The forecasted demand is shown below. Part Type Demand (Parts/Week) 1 42 2 18 3  6 4  6 5  6 6  6 Machines A and B require only one person to run two machines. Machine C requires only one person per machine. Develop a simulation model to determine how many machines of each type and number of employees will be required to meet the forecasted demand. Use 200 trials for each data table and compute summary statistics only

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section4.8: Data Envelopment Analysis (dea)
Problem 42P
icon
Related questions
Question
  1. Sturgill Manufacturing Inc. needs to predict the numbers of machines and employees required to produce its planned production for the coming year. The plant runs three shifts continuously during the workweek, for a total of 120 hours of capacity per week. The shop efficiency (the percent of total time available for production), which accounts for setups, changeovers, and maintenance, averages 70% with a standard deviation of 5%, which reduces the weekly capacity. Six key parts are produced, and the plant has three different types of machines to produce each part. The machines are not interchangeable as they each have a specific function. The time to produce each part on each machine varies. The mean time and standard deviation (in hours) to produce each part on each machine are shown below:

    Mean Time

    Part Type

    Machine A

    Machine B

    Machine C

    1

    3.5

    2.6

        8.9

    2

    3.4

    2.5

     8

    3

    1.8

    3.5

    12.6

    4

    2.4

    5.8

    12.5

    5

    4.2

    4.3

    28 

    6

    4   

    4.3

    28 

    Standard Deviation

    Part Type

    Machine A

    Machine B

    Machine C

    1

    0.15

    0.12

    0.15

    2

    0.15

    0.12

    0.15

    3

    0.1  

    0.15

    0.25

    4

    0.15

    0.15

    0.25

    5

    0.15

    0.15

    0.5  

    6

    0.15

    0.15

    0.5  

    The forecasted demand is shown below.

    Part Type

    Demand (Parts/Week)

    1

    42

    2

    18

    3

     6

    4

     6

    5

     6

    6

     6

    Machines A and B require only one person to run two machines. Machine C requires only one person per machine. Develop a simulation model to determine how many machines of each type and number of employees will be required to meet the forecasted demand. Use 200 trials for each data table and compute summary statistics only.

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,