The AB/C ratio is Select site (Click to select)

Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
14th Edition
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Chapter17: Long-term Investment Analysis
Section: Chapter Questions
Problem 10E
icon
Related questions
Question
The city engineer and economic development directors are evaluating two sites for construction of a multipurpose sports arena. The
sites are downtown (DT) and southwest (SW) of the metropolitan area. The city already owns enough land at the DT site; however, the
land for a parking garage will cost $1 million, and construction costs will be $14.00 million for the parking garage, infrastructure
relocation, and drainage. The SW site is 30 km from downtown, but the land will be donated by a developer who knows that an arena
at this site will dramatically increase the value of the remainder of his land holdings. Because of its centralized location, there will be
greater attendance at most of the events held at the DT site. This will result in more revenue to vendors and local merchants in the
amount of $550,000 per year. Additionally, the average attendee will not have to travel as far, resulting in annual benefits of $400,000
per year. All other costs and revenues are expected to be the same at either site. If the city uses a discount rate of 8.00% per year, and
will construct at one site or the other, which site should be selected? Use a 30-year study period. (Round the final answer to three
decimal places.)
The AB/C ratio is
Select site (Click to select)
Transcribed Image Text:The city engineer and economic development directors are evaluating two sites for construction of a multipurpose sports arena. The sites are downtown (DT) and southwest (SW) of the metropolitan area. The city already owns enough land at the DT site; however, the land for a parking garage will cost $1 million, and construction costs will be $14.00 million for the parking garage, infrastructure relocation, and drainage. The SW site is 30 km from downtown, but the land will be donated by a developer who knows that an arena at this site will dramatically increase the value of the remainder of his land holdings. Because of its centralized location, there will be greater attendance at most of the events held at the DT site. This will result in more revenue to vendors and local merchants in the amount of $550,000 per year. Additionally, the average attendee will not have to travel as far, resulting in annual benefits of $400,000 per year. All other costs and revenues are expected to be the same at either site. If the city uses a discount rate of 8.00% per year, and will construct at one site or the other, which site should be selected? Use a 30-year study period. (Round the final answer to three decimal places.) The AB/C ratio is Select site (Click to select)
Expert Solution
steps

Step by step

Solved in 3 steps with 6 images

Blurred answer
Knowledge Booster
Opportunity Cost
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning