The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time stockout costs for lost sales of $125 per unit, inventory carrying costs of $30 per unit per month, and zero beginning and ending inventory, evaluate the following plan on an incremental cost basis: Plan A: Produce at a steady rate (equal to minimum requirements) of 1,000 units per month and subcontract additional units at a $60 per unit premium cost. Subcontracting capacity is limited to 800 units per month. (Enter all responses as whole numbers). Subcontract Ending Demand Production Inventory Month (Units) 1 July 1000 1,000 2 August 1200 1,000 3 September 1400 1,000 4 October 1800 1,000 5 November 1800 1,000 December 1600 1,000

Marketing
20th Edition
ISBN:9780357033791
Author:Pride, William M
Publisher:Pride, William M
Chapter19: Pricing Concepts
Section: Chapter Questions
Problem 6DRQ
icon
Related questions
Question
The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time stockout costs for lost sales of $125 per unit,
inventory carrying costs of $30 per unit per month, and zero beginning and ending inventory, evaluate the following plan on an incremental cost basis:
Plan A: Produce at a steady rate (equal to minimum requirements) of 1,000 units per month and subcontract additional
units at a $60 per unit premium cost. Subcontracting capacity is limited to 800 units per month. (Enter all responses as whole numbers).
Subcontract
Ending
Demand Production Inventory
Month
1 July
(Units)
1000
1,000
2 August
1200
1,000
3 September
1400
1,000
4 October
1800
1,000
5 November
1800
1,000
6 December
1600
1,000
Overtime Capacity
Subcontract Cap
Month Demand Regular Time Capacity
July
August 1200
September
October 1800
1000
800
1,000
1,000
800
1400
1,000
800
1,000
800
November
1800
1,000
800
December
1600
1,000
800
Transcribed Image Text:The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time stockout costs for lost sales of $125 per unit, inventory carrying costs of $30 per unit per month, and zero beginning and ending inventory, evaluate the following plan on an incremental cost basis: Plan A: Produce at a steady rate (equal to minimum requirements) of 1,000 units per month and subcontract additional units at a $60 per unit premium cost. Subcontracting capacity is limited to 800 units per month. (Enter all responses as whole numbers). Subcontract Ending Demand Production Inventory Month 1 July (Units) 1000 1,000 2 August 1200 1,000 3 September 1400 1,000 4 October 1800 1,000 5 November 1800 1,000 6 December 1600 1,000 Overtime Capacity Subcontract Cap Month Demand Regular Time Capacity July August 1200 September October 1800 1000 800 1,000 1,000 800 1400 1,000 800 1,000 800 November 1800 1,000 800 December 1600 1,000 800
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
MARKETING 2018
MARKETING 2018
Marketing
ISBN:
9780357033753
Author:
Pride
Publisher:
CENGAGE L