There are five activities on a project's critical path and they have standard deviations of 1, 1, 3, 5, 5 days. The standard deviation (in days) of the critical path is: OA. 8.8 OB.9.8 OC.7.8 COD.4.6 O.E. 10.2 OF 10.6
Q: Montaño Manufacturing is considering a purchase of robots to automate their manufacturing system.…
A: Given, The MTBF and MTTR of Providers. All other factors are equal System availability =…
Q: Using the FCFS rule for scheduling, the sequence is 1-2-3. For the schedule developed using the FCFS…
A: Sequencing is an appropriate order of plan as per which the process of operations works. It defines…
Q: What are some of the key elements that make up a service culture?
A: Service is a deed performed by a professional expert to help the user in need. Service unlike…
Q: You are required to implement the production level method for the following scenario. Four products,…
A: Level production strategy refers to the production strategy where the production quantity is fixed…
Q: Supply Chain & Operations Management as you understand it now, could implicate a wide range of…
A: Operations management is a vast field that overlooks all processes, systems, procedures, and other…
Q: Specify the outcome suggested for each of the following criteria: Maximin = Maximax = Minimax Regret…
A: Mathematic models of decision-making help businesses take the correct decision for their operational…
Q: Analyze the SWOT of WALMART
A: To conduct a Walmart SWOT analysis, one must be familiar with the business and its development.…
Q: A normally distributed process uses 66.7% (i.e. the +/- 3 ? from the mean) of the specification…
A: The percentage of specification width is the same as the 1Cp.…
Q: QUESTION 8 You are given the following information, comprising of an individual's expenses for the…
A: Given data-
Q: A during trip inspections should include checking for:
A: 1. Odometer ReadingsOn practically any pre-trip review structure, on an application etc., the…
Q: Voltmeter Ranking Metal Magneto Black Panther Superman Wolverine Iron Man Capt. Marvel Reading 1,…
A: Ans) Formula:
Q: In a recent review meeting, the client has insisted you complete the project on time. You would like…
A: Given data is Earned value (EV) = $176,500 Actual cost (AC) = $223,500 Planned value (PV) = $229,100…
Q: The estimated times and immediate predecessors for the activities in a project at Howard Umrah's…
A: Given data: Time in weeks Immediate Predecessor(s) Activity a m b A 8 10 13 -…
Q: K Manceville Air has just produced the first unit of a large industrial compressor that incorporated…
A: Given data is Time required for first unit = 112 hours Learning curve = 85%
Q: Select all of the common pitfalls in this list related to building a dashboard: Too many colors…
A: Dashboard A dashboard in simple terms is nothing but a visual display of data. The motive of…
Q: Question content area Part 1 A contractor is preparing a bid to install swimming pools at a new…
A: Given data is Time to build first pool = 32 hours Learning curve = 80%
Q: A key factor for success for a retailer is a phenomenal forecasting process and resources (Jack…
A: Forecast accuracy refers to the extent the forecast is near the actual demand/sales. If the forecast…
Q: Problem 15-5 (Algo) A manufacturer has decided to locate a new factory in northwestern United States…
A: Given-
Q: a) Draw the network diagram b) c) d) Calculate the total duration of the project Identify the…
A: Forward Pass:Early Start (ES) = Max EF value from immediate Predecessor(s)Early Finish (EF) = ES +…
Q: Conduct a value chain analysis for Mc Donald's. Identify its primary and secondary activities.…
A: McDonald's primary activities: Inbound logistics: This is the process of transports and distributes…
Q: What does it mean to say that a project network is sensitive and why is that important to a project…
A: An organization's new initiatives or changes are initiated, organized, carried out, and overseen…
Q: Suppose that in month 1, both the retailer and the wholesaler in a supply chain ordered 20,000…
A: Bullwhip effect describes how demand is amplified at all levels of the supply chain. Although the…
Q: At the Qatar 2022 FIFA World Cup’s opening game on 20 November 2022, the iconic Al Bayt Stadium was…
A: The M/M/1 model refers to the single server model with exponential service time. There is no limit…
Q: Why should management be concerned about improving setup time? What do you recommend to Hammond…
A: Setup time is the amount of time required to configure a machine so that it is prepared to handle a…
Q: explain how various parties/players affect the sourcing process give examples?
A: We can relate the terminology "sourcing process" with just how sourcing operates. We are all…
Q: quetion 1 a)What is a burn-down chart? What purpose does it serve? b)Why should a project manager…
A: A burn-down chart represents the work left and the time left to complete the work. It is a work left…
Q: In many industries that have a process manufacturing operation, the production process is of a…
A: Many sectors will see units lost as a result of evaporation, shrinkage, spillage, or other issues…
Q: 18/hr 1 4 10/hr 20/hr Current capacity 5 12/hr 19/hr 8/hr The diagram describes a service process…
A: The capacity of a process is determined by the bottleneck step i.e. step having the highest cycle…
Q: University of Florida football programs are printed 1 week prior to each home game. Attendance…
A: Underestimating costs is a common issue in economics. It happens when decision-makers or planners…
Q: different control
A: Different control structure Sequence control refers to user actions and computer logic that…
Q: Several airlines, such as Air Asia, are pursuing a strategy to become a “retailer” of travel/tourism…
A: The airline industry has a global presence and therefore it is considered a large market but the…
Q: At the Dartmouth Assessment Centre, good students have an 85% learning curve and can do a task in 18…
A: Use the following formula: Tn=T1×Unit time factor For unit time factor, standard table for learning…
Q: Evaluate the statistical ROP when you have probabilistic demand and constant lead time, with…
A: While calculating ROP, the uncertainty of demand is considered as an important factor. It impacts…
Q: Which of the following is an effective way to reduce guest walk (select all that apply) If an…
A: Reducing guest walks or skips refers to the technique or wherein the management ensures that no…
Q: a. Complete the analysis, determining the optimal solution for shipping at the Mosier Clothing…
A: The transportation model is used to calculate the minimum cost of the route by selecting different…
Q: Courtney is a programmer receiving requests each week to analyze a large data base. Five jobs were…
A: Given-
Q: You have just been hired as a planner for the municipal school system, and your first assignment is…
A: The objective is to minimize the cost of the meal. Let each food be in terms of 'x', starting with…
Q: Explain 'Decision Management' and 'Decision Control' and the 4 elements that make up the…
A: Decision Management refers to coming up with a strategy to make the business more advanced and swift…
Q: Note: Note: you are required to provide a paraphrased understanding of the types of purchases…
A: Choosing the supplier that offers the best deal for the products that an organization must purchase…
Q: the product is $325 per unit in either case. Use the following information to determine which…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: The following payoff table shows profit for a decision analysis problem with two decision…
A: Given data: Decision Alternative State of nature S1 S2 S3 d1 260 110 35 d2 110 110 85…
Q: Can you please send me an excel file for the solver you have used. My professor told there will be 9…
A: Hit and trial method is a way of finding a solution that can give the desired output by trying out…
Q: I. The Northridge Company tends to keep the inventory low. At the same time, it is important to…
A: Find the Calculation methods below: Requirement (Maximum value of Demand and Customer order)…
Q: One of the main outputs of project cost management is cost estimate. Project managers normally…
A: Estimating the cost of a project: Estimation of cost in a project is finished at beginning of it,…
Q: Suppose you have a choice of three projects to choose from. Here the expected profits from these…
A: a)
Q: 1. Explain the use of charts to investigate the sources of process variation: Tom Sharkey is the…
A: Given data: Complaint Frequency Problem not corrected 38 Error on invoice 8 Unfriendly…
Q: Bloom's Jeans is searching for new suppliers, and Debbie Bloom, the owner, has narrowed her…
A: Given data: Option 1: Unique-event risk=5%.Nationwide event risk =2.3%.Purchasing and…
Q: You should choose vendor ▼ Donna Inc. Either Kay Corp. or Donna Inc. Kay Corp. , with a weighted…
A: Given, K means Kay corp and D means Donna Each attribute is given with its weight for each table.…
Q: The Universal Computer Company uses a newly developed A1 chip in the manufacturer of their tablet…
A: Ans) EOQ Formula: EOQ = Sqrt ( (2*D*Ordering Cost)/(Holding Cost) ) So, D = 12000*320/365 = 10667…
Q: Implement the linear optimization model and find an optimal solution. Interpret the optimal…
A: Decision variable: L= Laser top model S = Speedbuster model
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
- Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 45-week completion date requested by the owner. The Mueller project manager prepared the following project network. Start A B F H 0 D E Finish Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows. Activity Optimistic Most Probable A 4 8 Pessimistic 12 B 6 7 8 C 6 12 18 D 3 5 7 E 6 9 18 F 5 8 17 G 10 15 20 H 5 6 13A company is willing to develop their rocket before the end of current financial year which is now 28 weeks away. The chief engineer of the company has decided to use PERT technique in order to plan, schedule and control program of development for the data given in table below. What is the probability that the program will be completed by the end of the current financial year? (all durations are in weeks). (i) G) Optimum Duration Most likely duration Pesimistic duration 1 2 3 8 13 3 2 8 4 3 8 10 4 7 10 3 6. 3 8 4 9 10 4 8. 4 9. 5 7 9. 12 6. 5 11 7 9. 14 8 4. 00 2.The Farmer's American Bank of Leesburg is planning to install a new computerized accounts system. Bank management has determined the activities required to complete the project, the precedence relationships of the activities, and activity time estimates, as shown in the following table. Use POM- QM to analyze this project. According to the result of POM-QM, the expected project completion time is (type number only, no text) Activity a b C d C f 8 k Activity Description Position recruiting System development System training Equipment training Manual system test Preliminary system changeover Computer-personnel interface Equipment modification Equipment testing System debugging and installation Equipment changeover Activity Predecessor a a b, c b, c d, e d, e h f.g a 5 3 4 5 I 1 3 Time Estimates (weeks) 1 1 2 5 m 8 12 7 8 I 4 6 2.5 1. 2 8 b 17 15 10 23 1 13 9 7 1 2 11
- What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Activity Time (days) Time (days) A B C The total cost of crashing the project by 4 days is $. (Enter your response as a whole number.) E 5 8 6 5 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) 4 6 5 3 Activity A B C D E Normal Cost $800 $200 $600 $750 $1,200 Total Cost with Crashing Immediate Predecessor(s) $1,100 $400 $650 $1,500 $1,650 Each Activity Should be Reduced BY (days) ACA project has a critical path with an expected duration of 22 and variance of 14. What is the probability it will be completed within 20-25 weeks (inclusive)? (the range of the answers account for rounding errors) Group of answer choices Between 55% and 58% Between 17% and 20% Between 47% and 52% Between 64% and 67% Between 60% and 63%Suppose that a task in a project has the following time estimates: to=optimistic completion time=10 weeks tm=most likely completion time=17 weeks tp=pessimistic completion time=19 weeks Compute the expected task variance. The task expected task variance is _____ weeks. (Enter your response rounded to two decimal places.)
- Which of the following statements regarding PERT analysis is TRUE? Select one: O a Project variance is the sum of all activity variances. O b. Project standard deviation is the sum of all critical activity standard deviations. O c. Each activity has two estimates of its duration. O d. Only critical activities contribute to the project varianceThe expected number of days to completion for a different project is E(x) = 3.32 The variance of days to completion is var(x) = 1.22 The project cost involves A fixed cost (in thousands of dollars) of FC = $83.783 A variable cost for each day taken to complete the project ($000) VC = $9.774 16 The standard deviation of the project cost is $________. a 13.041 b 12.245 c 11.497 d 10.796A project has the following tasks and duration estimates given. These three tasks are done in succession on a project. Task Optimistic Estimate Most Likely Estimate Pessimistic Estimate Alpha 30 days 40 days 50 days Beta 20 days 25 days 28 days Charlie 4 days 10 days 12 days Delta 25 days 30 days 50 days What is the expected duration for the project? (3 points) What is the variance for the project? (3 points) What is the standard deviation of the project? (3 points) What is the range of the duration of the project given 3 sigma? (3 points)
- Identify the term being described for each of the following: (a). A sequence of activities in a project. (b). The longest time sequence of activities in a project. (c). Used when two activities have the same starting and finishing points. (d). The difference in time length of any path and the critical path. (e). The statistical distribution used to describe variability of an activity time. (f). The statistical distribution used to describe path variability. (g). Shortening an activity by allocating additional resources.You are given the following data for an activity: ES = 10 EF = 15 LS = 16 Which of the following can you determine from this data? A. The activity's float and duration B. Only the activity float C. Only the activity duration D. Neither the activity's float nor its duration2:30 PM ě 0.3KB/s 1ll 54 4G+ 00:15:12 Remaining Multiple Choice The primary difference between PERT and CPM is that CPM uses probabilities on the activity times and PERT does not. O. PERT considers activity costs and CPM does not. PERT can assign probabilities to activity times and CPM does not. CPM considers activity costs and PERT does not. 5 of 20 II