WorkPro is a small manufacturer. It uses a job process for production. The following sample of jobs are listed in the order that they were received. Job Due Date Operation Time P 5 1 Q 20 8 R 8 5 S 11 6 T 3 12 When the shortest operating time (SOT) rule is applied to the sample of jobs, the resulting sequence is: A. Choos the following answer choice. T, P, R, S, Q R, S, T, P, Q P, Q, R, S, T P, R, S, Q, T       B. In the WorkPro example above, average flow time for the sample of jobs when sequenced by the shortest operating time (SOT) rule is approximately: 19.8 14.2 4.8 6.4       C. In the WorkPro example above, average lateness for the sample of jobs when sequenced by the earliest due date (EDD) rule is approximately: Group of answer choices 10.4 4.8 7.8 5.8       D. Using the sample of jobs in the WorkPro example above, the shortest operating time (SOT) rule appears more attractive than the earliest due date (EDD) rule when comparing average flow times of the resulting sequences. True False

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter5: Network Models
Section: Chapter Questions
Problem 1C
icon
Related questions
Question

WorkPro is a small manufacturer. It uses a job process for production. The following sample of jobs are listed in the order that they were received.

Job Due Date Operation Time
P 5 1
Q 20 8
R 8 5
S 11 6
T 3 12

When the shortest operating time (SOT) rule is applied to the sample of jobs, the resulting sequence is:

A. Choos the following answer choice.
T, P, R, S, Q
R, S, T, P, Q
P, Q, R, S, T
P, R, S, Q, T
 
 
 

B. In the WorkPro example above, average flow time for the sample of jobs when sequenced by the shortest operating time (SOT) rule is approximately:

19.8
14.2
4.8
6.4
 
 
 
C. In the WorkPro example above, average lateness for the sample of jobs when sequenced by the earliest due date (EDD) rule is approximately:
Group of answer choices
10.4
4.8
7.8
5.8
 
 
 

D. Using the sample of jobs in the WorkPro example above, the shortest operating time (SOT) rule appears more attractive than the earliest due date (EDD) rule when comparing average flow times of the resulting sequences.

True
False
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Optimization models
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,