XYZ Mutual Fund is seeking to invest $80 million in real estate projects with high potential returns. The fund has identified several investment opportunities, each with a specific investment cost and expected economic benefit (see the table below). The goal is to maximize the total economic benefit by selecting a combination of projects to invest in while staying within the budget mentioned above. However, there are several constraints to consider, including the requirement to invest in at least four projects in total, with at least two of them being environmentally friendly (projects that are considered environmentally friendly are: 3, 5, 9, and 10). Additionally, if project 3 is selected, then project 4 must also be chosen, but project 4 can be chosen independently of project 3. The fund cannot make partial or fragmented investments, and projects cannot be purchased multiple times as each project is unique. The challenge is to determine the optimal combination of projects that will maximize the total economic benefit while adhering to these constraints. Investment cost ($ millions) Expected economic benefit ($ millions) Project 1 21 49 Project 2 18 48 Project 3 20 33 Project 4 25 45 Project 5 13 36 Project 6 10 47 Project 7 22 50 Project 8 24 35 Project 9 21 43 Project 10 24 30
XYZ Mutual Fund is seeking to invest $80 million in real estate projects with high potential returns. The fund has identified several investment opportunities, each with a specific investment cost and expected economic benefit (see the table below). The goal is to maximize the total economic benefit by selecting a combination of projects to invest in while staying within the budget mentioned above. However, there are several constraints to consider, including the requirement to invest in at least four projects in total, with at least two of them being environmentally friendly (projects that are considered environmentally friendly are: 3, 5, 9, and 10). Additionally, if project 3 is selected, then project 4 must also be chosen, but project 4 can be chosen independently of project 3. The fund cannot make partial or fragmented investments, and projects cannot be purchased multiple times as each project is unique. The challenge is to determine the optimal combination of projects that will maximize the total economic benefit while adhering to these constraints.
|
Investment cost ($ millions) |
Expected economic benefit ($ millions) |
Project 1 |
21 |
49 |
Project 2 |
18 |
48 |
Project 3 |
20 |
33 |
Project 4 |
25 |
45 |
Project 5 |
13 |
36 |
Project 6 |
10 |
47 |
Project 7 |
22 |
50 |
Project 8 |
24 |
35 |
Project 9 |
21 |
43 |
Project 10 |
24 |
30 |
Trending now
This is a popular solution!
Step by step
Solved in 1 steps