You are provided with the following information for a project, with activity durations given in weeks: Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6
You are provided with the following information for a project, with activity durations given in weeks:
Activity Immediate Optimistic Most Likely Pessimistic
Predecessor Time (a) Time (m) Time (b)
A ____ 2 3 4
B ____ 2 4 6
C A 1 2 3
D B 3 6 9
E C, D 7 8 9
F D 4 7 10
G E 3 4 5
H E, F 6 9 12
- Construct the project network.
- Determine the expected times and variances for the activities.
- Determine the critical path after you have found ES, EF, LS, LF and slack. State the path and time expected to be taken.
- What is the probability that the project would be completed within 27 weeks?
- What time should be allowed such that there is a 95% chance of completion within that time?