You are the project manager of a project that has $142590 as the budget at completion. 65% of the work was planned to be completed at the end of month seven but only 53% has been completed as at today with an actual cost of $78352. The project's Estimate To Completion (ETC) is closest to? O 104223 O Skip this question to avoid any negative score! O None of the given answers O 52111 O 138964 69482

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
icon
Concept explainers
Topic Video
Question
You are the project manager of a project that has $142590 as the budget at completion. 65% of the work was
planned to be completed at the end of month seven but only 53% has been completed as at today with an actual
cost of $78352. The project's Estimate To Completion (ETC) is closest to?
104223
Skip this question to avoid any negative score!
None of the given answers
52111
O 138964
• 69482
Transcribed Image Text:You are the project manager of a project that has $142590 as the budget at completion. 65% of the work was planned to be completed at the end of month seven but only 53% has been completed as at today with an actual cost of $78352. The project's Estimate To Completion (ETC) is closest to? 104223 Skip this question to avoid any negative score! None of the given answers 52111 O 138964 • 69482
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Inventory management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,