You have been assigned to be a member of a project review team to determine the “health” of project # WINGS3, and you will have to tell the division manager whether or not you predict that the project will be done according to the plan. The project manager gave you the following data about her program: BAC = 16,000; EAC = 17,500; AC = 13,250; EV = 10,000; Based on Earned Value metrics, what do you tell your manager? a. There are no problems, the project is great. b. The project is not on plan, but will finish on plan if they are about 11% more efficient. c. The Project is slightly behind, but should be able to finish on time. d. The Project is in serious trouble and plan on the infusion of additional funds to finish even close to on time. e. You cannot tell based on the metrics above. f. You have no idea what to say; they asked the wrong person.
You have been assigned to be a member of a project review team to determine the “health” of project # WINGS3, and you will have to tell the division manager whether or not you predict that the project will be done according to the plan. The project manager gave you the following data about her program:
BAC = 16,000;
EAC = 17,500;
AC = 13,250;
EV = 10,000;
Based on Earned Value metrics, what do you tell your manager?
a. There are no problems, the project is great.
b. The project is not on plan, but will finish on plan if they are about 11% more efficient.
c. The Project is slightly behind, but should be able to finish on time.
d. The Project is in serious trouble and plan on the infusion of additional funds to finish even close to on time.
e. You cannot tell based on the metrics above.
f. You have no idea what to say; they asked the wrong person.