You work for the Brad's Nailer Company which manufactures two types of nailers: a pneumatic model and a cordless model. You have contracted to supply a national retail chain with both pneumatic nailers and cordless nailers. However, Brad's nailer production capability is limited in three departments: production, testing, and packaging. Your answer will be the production hours needed to execute a production plan that minimizes costs - rounded to the nearest whole hour. (The number of nailers may not be a whole number, which is acceptable in this chapter.) Use Scenario 2 Pneum. Cost Pneum. Prod Hrs Pneum. Test Hrs Pneum. Pkg Hrs Pneum. Sales Cordless Cost Cordless Prod Hrs Cordless Test Hrs Cordless Pkg Hrs Cordless Sales Prod Hrs max Testing Hrs max Pkg Hrs max Scenario 1 Scenario 2 Scenario 3 52 0.2 0.3 0.1 22,000 67 0.3 0.4 0.1 15,500 10,000 15,000 4,800 55.50 0.4 0.3 0.1 0.1 38.50 15,500 20,000 18,000 4,200 0.25 0.4 24,500 18,000 69.75 0.3 0.5 0.1 44 0.4 0.4 0.2 14,000 20,000 18,000 5,000

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Chapter2: The Purchasing Process
Section: Chapter Questions
Problem 1GPE
icon
Related questions
Question
You work for the Brad's Nailer Company which manufactures two types of nailers: a
pneumatic model and a cordless model. You have contracted to supply a national retail
chain with both pneumatic nailers and cordless nailers. However, Brad's nailer production
capability is limited in three departments: production, testing, and packaging.
Your answer will be the production hours needed to execute a production plan that
minimizes costs - rounded to the nearest whole hour. (The number of nailers may not be a
whole number, which is acceptable in this chapter.)
Use Scenario 2
Pneum. Cost
Pneum. Prod Hrs
Pneum. Test Hrs
Pneum. Pkg Hrs
Pneum. Sales
Cordless Cost
Cordless Prod Hrs
Cordless Test Hrs
Cordless Pkg Hrs
Cordless Sales
Prod Hrs max
Testing Hrs max
Pkg Hrs max
Scenario 1 Scenario 2 Scenario 3
52
0.2
0.3
0.1
22,000
67
0.3
0.4
0.1
15,500
10,000
15,000
4,800
55.50
0.4
0.3
0.1
24,500
69.75
0.3
0.5
0.1
15,500
20,000
18,000
4,200
38.50
0.25
0.4
0.1
18,000
44
0.4
0.4
0.2
14,000
20,000
18,000
5,000
Transcribed Image Text:You work for the Brad's Nailer Company which manufactures two types of nailers: a pneumatic model and a cordless model. You have contracted to supply a national retail chain with both pneumatic nailers and cordless nailers. However, Brad's nailer production capability is limited in three departments: production, testing, and packaging. Your answer will be the production hours needed to execute a production plan that minimizes costs - rounded to the nearest whole hour. (The number of nailers may not be a whole number, which is acceptable in this chapter.) Use Scenario 2 Pneum. Cost Pneum. Prod Hrs Pneum. Test Hrs Pneum. Pkg Hrs Pneum. Sales Cordless Cost Cordless Prod Hrs Cordless Test Hrs Cordless Pkg Hrs Cordless Sales Prod Hrs max Testing Hrs max Pkg Hrs max Scenario 1 Scenario 2 Scenario 3 52 0.2 0.3 0.1 22,000 67 0.3 0.4 0.1 15,500 10,000 15,000 4,800 55.50 0.4 0.3 0.1 24,500 69.75 0.3 0.5 0.1 15,500 20,000 18,000 4,200 38.50 0.25 0.4 0.1 18,000 44 0.4 0.4 0.2 14,000 20,000 18,000 5,000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 9 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning