You're managing a project using the earned value management for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual cost (AC) is $150,000. What is the cost variance (CV) for the project?
You're managing a project using the earned value management for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual cost (AC) is $150,000. What is the cost variance (CV) for the project?
Chapter6: Proudction Costs
Section: Chapter Questions
Problem 8SQP
Related questions
Question
You're managing a project using the earned value management for cost management. The project planned value (PV) is $200,000. The project earned value (EV) is $100,000. The actual cost (AC) is $150,000. What is the cost variance (CV) for the project?
a.
-50,000
b.
100,000
c.
-100,000
d.
150,000
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning