6. (Ch10) Job A B C D E F Process Time (days) 2 8 4 10 5 12 Due Time (days) 7 16 4 17 15 18 Days Since Arrival 12 9 8 5 3 2 Use the information in the preceding table and sequence the six jobs using FCFS and EDD. The jobs are listed in the order of their arrival. Calculate the average flow time and average past due. It is now time zero.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section: Chapter Questions
Problem 59P
icon
Related questions
Question
6. (Ch10)
Job
A
B
с
D
E
F
Process Time (days)
2
8
4
10
5
12
Due Time (days)
7
16
4
17
15
18
Days Since Arrival
12
9
8
5
3
2
Use the information in the preceding table and sequence the six jobs using FCFS and EDD. The jobs are
listed in the order of their arrival. Calculate the average flow time and average past due. It is now time
zero.
Transcribed Image Text:6. (Ch10) Job A B с D E F Process Time (days) 2 8 4 10 5 12 Due Time (days) 7 16 4 17 15 18 Days Since Arrival 12 9 8 5 3 2 Use the information in the preceding table and sequence the six jobs using FCFS and EDD. The jobs are listed in the order of their arrival. Calculate the average flow time and average past due. It is now time zero.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,