A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 180 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and Grespectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks Dand E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.4, 2.2,0.9, 1.0, 1.2, 1.8, are 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What is the idleness in percentage? O a. 81.82 O b. 20.83 Oc 32.5 O d. None is the correct answer 31 34
Q: An assembly department has six jobs waiting to be processed. It is now time zero and all jobs are…
A:
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data; Output = 60 units Available time = 8 hrs or 8*60 = 480 min
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given, Time par day- 8 hours Demand - 180 units/day
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.4 B 2.2 C 0.9 D 1 E 1.2 F 1.8 G 1.5…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: About Assignment Short-Term Scheduling The following table shows the contribution of benefits…
A: Given,
Q: Three jobs are to be scheduled on two machines A & B . Assume that the jobs are processed in the…
A: A Gantt chart is a kind of bar chart that represents a project schedule, Gantt charts enable the…
Q: In the winter, Scott works four 10-hour days instead of five 8-hour days, so he has a long weekend…
A: A workweek is a 168-hour period that occurs on a weekly basis. A workweek is defined as seven…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Formula to be used; Cycle time = Available time / Output
Q: A schedule for two processors has been created for the following project which has a finishing time…
A: A network diagram along with activity timings is given:
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: 8 hours per day = 28800 seconds and want to produce 100 units/ day cycle time = 28800/100 = 288…
Q: An independent accountant is planning to prepare tax returns for six of her clients.Prior to her…
A: Step 1: Initially, the minimum number should be selected by considering both the columns. Here, 0.5…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: At the campus copy shop, six jobs have arrived in the order shown (A, B, C, D, E, and F) at the…
A: note: since only d and e are asked, the same are being answered. Given data: Job Due time…
Q: The Earliest Due date (EDD) rule for sequencing a given set of jobs usually ____________ Select…
A: Scheduling is a technique for allocating precious computational resources typically processor time,…
Q: Five jobs must be scheduled for batch processing on a mainframe computer system. The processing…
A:
Q: The maximum cycle time is the sum of all task times when the tasks are running in series (one by…
A: a. True
Q: 3. The Fix-it Shop has just received four new repair projects that must be repaired quickly, i.e.,…
A: Linear programming for the assignment problem includes objective function and constraints. For this,…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given data is Demand = 80units/day Working hours = 8
Q: FILE UPLOAD: Draw a flowchart for customers fueling their cars at a gas station, starting with the…
A: A flowchart is a sort of outline that addresses a work process or cycle. A flowchart can likewise be…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Assembly line balancing is the process of assigning each task to a workstation in order to meet the…
Q: Given a set ?? = {??1,??2, … ,????} of tasks, where ???? requires ???? units of processing time to…
A: question 1:the goal of attaning minimum waiting time will come when we select shortest job and…
Q: ct planning, one of the key scheduling functions is task scheduling. The sequence of tasks may have…
A: When two tasks rely on one other, it is referred to as a "task dependence" or "task connection."…
Q: in an assignment problem involving 8 workers and 8 jobs, total number of assignments possible are…
A: One of the properties of assignment problems is that only one job can be assigned to a worker. So,…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Find the Given details below: Given details: Task Immediate Predecessors Time(mins) A - 2.4…
Q: Dan is a member of a four person sales team in a gourmet kitchen shop. All of the sales team members…
A: Working in a team is like working together on the same goal and work collaboratively in order to…
Q: The following table shows jobs to be processed at a machine. Determine the processing sequence that…
A: Find the given details below: Given details: Job Processing time (days) Due date (days) A 3 4…
Q: The job that should be scheduled last when usingJohnson’s rule is the job with the:a) largest total…
A: Johnson’s rule in operations management is a method or technique that schedules a job in two work…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: The flow diagram for the product is shown below.
Q: In an evaluation of labor assignment rules when workers are not perfectly interchangeable, Paul. M.…
A: Here the rows represent the workers and the columns represent the work centers.
Q: Suppose we have a school building project. According to the breakdown structure, twenty work…
A: Suppose we've got a faculty building project. in keeping with the breakdown structure, twenty work…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: The detailed solution is given in Step 2.
Q: snip
A: Given that: Job Processing Time (in weeks) Alpha 2 Beta 3
Q: Five sorority sisters plan to attend a social function. Each requires hair styling andfitting for a…
A: The schedule of the work of five people is used for minimizing the total expected time required for…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: To utilize the product layout, the complete work to be performed should be dividable into little…
Q: A market research firm has three clients who have each requested that the firm conduct a sample…
A: The given table is: Statistician Client Client Client A B C 1 150 210 270 2 170 230 220…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A:
Q: Six jobs are to be processed through a two-step operation. The first operation involves sanding, and…
A: In operations, Johnson's rule is a technique of scheduling jobs in two work centers. Its primary…
Q: simple and explicit enough and must be typed with the use of a computer keyboard only!
A: Providing the answers with an explanation as is why the particular option is correct.
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.4 B 2.2 C 0.9 D 1 E 1.2 F 1.8 G 1.5…
Q: Three jobs are to be scheduled on two machines A and B. Assume that the jobs are processed in the…
A: GIVEN,
Q: Six ships are docked in a harbor awaiting unloading. The times required to unload the ships are…
A:
Q: The first five columns of the following table contain information about a set of four jobs that just…
A: Solution a) Using CR to schedule the machine, we divide the time remaining until the due date by the…
Q: Ron Satterfield’s excavation company uses bothGantt scheduling charts and Gantt load charts.a)…
A: Using the above information following derivation can be done:
Step by step
Solved in 2 steps with 1 images
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 80 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of workstations are needed? Select one: a. None is the correct answer b. 5 C. 6 d. 3 e. 1A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 90 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C D E F and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed, Starting tasks needs the task to be completed. Also starting task D, needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F. and G are 28.2.1,0.9, 10, 1.2.1.8 are 4.7 minutes respectively. How many minimum numbers of workstations are needed? a. 1 b. 6 c. None is correct d. 3 e. 5 please I neef answer along with the formula don't put it on excelA manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely. A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task Fneeds the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the THIRD workstation are Select one: a. D, E,…
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D. E. F. and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.3, 2.1, 0.9, 1.0, 1.2, 1.8, and 1.5 minutes respectively. Applying the most remaining tasks rule for balancing the assembly line, with ties broken according to longest task time first. What will be the idle time for the FOURTH Workstation? O a. 1.0 O b. 1.4 C. 0.9 O…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 90 units per day. The product requires 7 tasks in total. These tasks are namely, A. B, C, D. E,F. and Grespectively. Task A does not have any predecessor to start. To start Task B. it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C Whereas starting task F needs the completion of both the tasks Dand E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A. B. C. D. E.F. and Gare 2.8.21,0.9.1.0, 1.2. 1.8, and 4.7 minutes respectively. How many minimum numbers of workstations are needed? Oa 3 Ob. None is the correct answer Oc 5 Od. 1 Oe 6A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 80 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. What should be the (calculated) cycle time in minutes? Select one: Oa. 4.5 Ob. 0.9 Oc. None is the correct answer O d. 6.0 Oe. 4.4 Next pa nd Windows
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of workstations are needed? Select one: O a.2 O b. None is the correct answer O c.6 O d. 8 O e. 4A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the SECOND workstation are Select one: Oa. B and…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, and 4.7 minutes respectively. How many minimum numbers of workstations are needed? O a. 6 O b. None is the correct answer O c. 8 O d. 2 O e. 4
- A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line with ties broken according to longest task time first, the tasks that will be assigned to the SECOND workstation are: a. B,C and D b. C…A manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks D andE. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and G are 2.8, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. How many minimum numbers of workstations are needed? Select one: O a. 6 Ob. 2 Oc.4 O d. None is the correct answer O e. 8 Next page Immp toA manufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 tasks in total. These tasks are namely, A, B, C, D, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed. Starting tasks C needs, the task B to be completed. Also, starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks Dand E. Finally, starting task G needed, task F to be completed. The processing times for tasks, A, B, C, D, E, F, and Gare 2.8, 2.1,0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks rule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are O a. A, B, and C Ob. None…