Assembly-Line Balancing The time to perform each task and the tasks that must be immediately preceded are shown below: Task Time (Minutes) Immediate Predecessors A 0.25 - B 0.08 A C 0.12 B D 0.17 B E 0.06 C, D F 0.05 E G 0.09 E H 0.11 E I 0.16 F, G, H J 0.08 I If 150 products are needed per hour and 50 minutes per hour are productive. Calculate the following: (a) Use the longest-task-time heuristic to balance the production line. (b) What is the efficiency of this assembly line balancing?
Assembly-Line Balancing
The time to perform each task and the tasks that must be immediately preceded are shown
below:
Task Time (Minutes) Immediate Predecessors
A 0.25 -
B 0.08 A
C 0.12 B
D 0.17 B
E 0.06 C, D
F 0.05 E
G 0.09 E
H 0.11 E
I 0.16 F, G, H
J 0.08 I
If 150 products are needed per hour and 50 minutes per hour are productive.
Calculate the following:
(a) Use the longest-task-time heuristic to balance the production line.
(b) What is the efficiency of this assembly line balancing?