Question No: 03 wnich is day 241. Job No Date Job Production Days Date Job Received Needed Due BR-02 228 15 300 СХ-01 225 35 270 DE-06 235 25 320 RG-05 230 40 360 SY-11 231 30 310 a. For EDD, SPT and FCFS dispatching rules (show all calculations)- Which dispatching rule has the best score for flow time, the utilization matric, and average lateness? b. Describe Critical ratio, and its uses.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter5: Network Models
Section: Chapter Questions
Problem 1C
icon
Related questions
Question

2

Question No: 03
wnich is day 241.
Job No
Date Job
Production Days
Date Job
Received
Needed
Due
BR-02
228
15
300
СХ-01
225
35
270
DE-06
235
25
320
RG-05
230
40
360
SY-11
231
30
310
a. For EDD, SPT and FCFS dispatching rules (show all calculations)- Which dispatching rule has the best score for
flow time, the utilization matric, and average lateness?
b. Describe Critical ratio, and its uses.
Transcribed Image Text:Question No: 03 wnich is day 241. Job No Date Job Production Days Date Job Received Needed Due BR-02 228 15 300 СХ-01 225 35 270 DE-06 235 25 320 RG-05 230 40 360 SY-11 231 30 310 a. For EDD, SPT and FCFS dispatching rules (show all calculations)- Which dispatching rule has the best score for flow time, the utilization matric, and average lateness? b. Describe Critical ratio, and its uses.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,