The machine shop of Reliable Manufacturing has to schedule eight jobs that are to be sent to final assembly for an important customer order. Currently, all eight jobs are in department X and must be routed to department Y after processing. The processing times (in days) for each job in each department follow: Dept/Job Dept. X Dept. Y A B D E F G H 2 2 5 4 7 5 4 10 3 6 3 8 6 6 Develop two schedules for operations in both departments. For your first schedule, use the SPT priority rule (based on X). Your second schedule should be based on Johnson's Rule. Compare the two schedules using average flow time, makespan, and average WIP inventory. Use a Gantt chart to display your schedules (i.e. a timeline).
Q: 8. Operations times of servicing of Washing Machines are given below. The first operation involves…
A: a.
Q: How does the theory of constraints differ from traditional scheduling?
A: 1)The Framework is a technique that identifies bottleneck, i.e., constraint that comes in the way of…
Q: Sunny Park Tailors has been asked to make three different types of wedding suits for separate…
A: First come first serve (FCFS) scheduling calculation just timetables the positions as per their…
Q: Two jobs must be processed through four machines in the same order. The processing times in the…
A: One of the most prominent and useful ways of demonstrating activities (tasks or events) shown…
Q: Develop separate schedules by using the FCFS and EDD rules.
A: FCFS scheduling stands for First come first serve, under which the jobs are arranged in the order of…
Q: Categorize different scheduling procedures for various types of service operations, such as…
A: Scheduling is vital not only for the companies who manufactures goods but also for the service…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Given table; Task Performance Time(Min) A 2.4 B 2.2 C 0.9 D 1 E 1.2 F…
Q: The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 30) at its…
A: Given data is
Q: The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its…
A: Given - Job Time Since Order Arrived(days ago) Processing Time (days) Due Date (days…
Q: Al Jassar LLC is an Omani pipe manufacturing firm has recently offered a contract for cement…
A: Given data, Processes A B C D Welding 7 6 3 5 Cement overlaying 6 4 3 6 Painting/Coating…
Q: De Law Construction has a gotten some construction jobs to build some starter housing units in a few…
A: Simplify the given data to determine the due dates as shown below:
Q: The following set of seven jobs is to be processed through two work centers at George Heinrich’s…
A: #Note: "Since you have posted a question with multiple sub-parts, we will solve the first three…
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: Formula to be used; Cycle time = Available time / Output
Q: Consider the following single machine problem h2 Ja Ja s J6 P53 2 6 4 d10 6 18 15 12 16 20. Find the…
A: Given data is
Q: A manufacturer is designing a product layout for a new product production. It plans to use a…
A: A workstation appraisal limits dangers to DSE clients by guaranteeing workstations are hazard…
Q: Six jobs are to be processed through a two-step opera- tion. The first operation involves sanding,…
A: JOB OPERATION 1 (HOURS) OPERATION 2 (HOURS) A 10 5 B 7 4 C 5 7 D…
Q: As a production supervisor, Joe decides on Friday afternoon how many units of output his employees…
A: Controlling - Controlling is a role of management that supports to check faults in command to take…
Q: There are 6 jobs which go through two machines A and B in the order A-B. Processing time in hours)…
A: The optimal sequences of processing jobs are
Q: (a) The following tasks are to be completed on vehicles at a service station: To A B с D E F A 139…
A: Since you have not mentioned the specific questions, as per guidelines, we have answered the first…
Q: Five jobs must be scheduled for batch processing on a mainframe computer system. The processing…
A:
Q: Ron Satterfield's excavation company uses both Gantt scheduling charts and Gantt load charts. Today,…
A:
Q: Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of…
A: THE ANSWER IS AS BELOW:
Q: The following set of seven jobs is to be processed through two work centers at George Heinrich's…
A: NOTE: We are allowed to do first three sub-parts only.
Q: The following jobs are waiting to be processed at thesame machine center. Jobs are logged as they…
A: a) FCFS (First come first served) Job Due date Duration (days) A 313 8 B 312 16 C 325 40…
Q: Five jobs are ready for processing at time zero through a workstation. The details of the processing…
A: EDD: Earliest due date means that the jobs will be processed as per their due dates. That means the…
Q: Describe Short -term Scheduling, Finite Capacity Scheduling and Constraint Theory Through your own…
A: Short -term Scheduling Booking is the way toward masterminding, controlling and upgrading work and…
Q: Different scheduling methods for different types of service activities, such as restaurants,…
A: Scheduling is critical not only for manufacturing firms, but also for service operations. It also…
Q: A production line is to be designed for a job with three tasks. The task times are 0.3 minutes, 1.4…
A: Answer: In this mentioned problem, a job has three elemental tasks. Cycle time is the maximum amount…
Q: Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of…
A: The FCFS and EDD analysis is as follows:
Q: The operations manager of an assembly and paint shop has five trucks to schedule for repair. He…
A: Solution: Truck A B C D E Assembly (hours) 7 9 8 4 12 Paint (hours) 10 3 7 4 5
Q: Sunny Park Tailors has been asked to make three different types of wedding suits for separate…
A: Given, SUIT CUT AND SEW DELIVER 1 7 2 2 4 3 3 5 6
Q: Compare the differences between flow classification and flow scheduling?
A: The two concepts i.e. flow classification and flow scheduling are closely related, and both are…
Q: The framing department has six jobs waiting to be processed as shown in Table 3 below. It is now…
A: Given that: Jobs Processing Time Due Date A 5 12 B 7 18 C 8 14 D 3 10 E 9 22 F 12 17
Q: Why is managing bottlenecks so important in work center scheduling?
A: A bottleneck is a single process in a chain process whose limited capacity affects the overall…
Q: Suppose we have a school building project. According to the breakdown structure, twenty work…
A: Suppose we've got a faculty building project. in keeping with the breakdown structure, twenty work…
Q: Job Printing(hrs) Binding(hrs) T 15 3 U 7 9 V 4 10 W 7 6 X 10 9 Y 4 5 Z 7 8…
A: Presentation: A methodology that diminishes the handling time for sequencing a bunch of tasks…
Q: How many minimum numbers of workstations are needed? a. 1 b. 6 c. None is correct d. 3 e. 5
A: Demand is the total quantity of goods and services for which the consumers are ready to pay…
Q: The Mowry Machine Shop still has five jobs to be processed as of 8 A.M. today (day 23) at its…
A: Given, Job Time Since Order Arrived (days ago) Processing Time (days) Due Date…
Q: Qus 1: Find the FCFS Schedule? Qus 2: Find the SOT Schedule? Qus 3:Find the DDate Schedule? Qus…
A: The job scheduling process is a time-consuming and complicated task. It requires a lot of time and…
Q: Six jobs are to be processed through a two-step operation. The first operation involves sanding, and…
A: In operations, Johnson's rule is a technique of scheduling jobs in two work centers. Its primary…
Q: Compute the cycle time and minimum number of workstations required b- Draw the precedence diagram
A: Note - Since you have posted a question with multiple sub-parts, we will solve first three subparts…
Q: A local toy manufacturer is using a production line that runs 8 hours per day and producesa toy that…
A: Production is the process of manufacturing the finished products and services using raw materials…
Q: A nursing home must schedule nurses in a manner that balances providing adequate patient care while…
A: Given data, Shift Time Minimum number of nurses 1 12 am -4 10 2 4 am- 8 6 3 8 am -12 8…
Q: Ron Satter field's excavation company uses bothGantt scheduling charts and Gantt load charts.a)…
A: A Gantt chart refers to a management tool used to visualize a project to help in its planning and…
Q: Twelve tasks, with times and precedence requirements as shown in the following table, are tobe…
A:
Q: Why is managing bottlenecks so important in workcenter scheduling?
A: A bottleneck can be characterized as any assignment or cycle in many undertakings with the end goal…
Q: Six jobs are to be processed through a two-stepoperation. The first operation involves sanding, and…
A: Optimal sequence: E D C A B F
Q: Question: Balance this line using the longest task time heuristic.
A: The longest-time heuristic method ensures that the most difficult tasks to fit into a station are…
Q: Ron Satterfield’s excavation company uses bothGantt scheduling charts and Gantt load charts.a)…
A: Using the above information following derivation can be done:
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 7 images
- Sunny Park Tailors has been asked to make three dif-ferent types of wedding suits for separate customers. The table below highlights the time taken in hours for (1) cutting and sewingand (2) delivery of each of the suits. Which schedule finishes sooner:first come, first served (123) or a schedule using Johnson’s rule?Times Taken for Different Activities (hours)SUIT CUT AND SEW DELIVER14 227 736 5On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order. Time Required (hours) Job Mill Drill 216 7 11 327 6 10 462 8 4 519 5 8 258 3 5 617 12 15 Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - - - - - . Choose the correct Gantt chart with the minimum makespan schedule. The correct graph is .Sunny Park Tailors has been asked to make threedifferent types of wedding suits for separate customers. Thetable below highlights the time taken in hours for (1) cuttingand sewing and (2) delivery of each of the suits. Which schedulefinishes sooner: first come, first served (123) or a schedule usingJohnson’s rule?
- The fixed drilling machine is a bottleneck operation in one production system. Currently, five tasks are waiting to be processed. See below the available operations data. Suppose the current date week R and that the number and time of operation the rest include operation on the fixed drilling machine. Assignment Time to processing Date of delivery Operations remaining Time to remaining operation (week) AA 4 10 3 4 BB 8 16 4 6 CC 13 21 10 9 DD 6 23 3 12 EE 2 12 5 3 Assignment Release time Size of the lot Time to processing (h / unit) Time to preparation (H) Delivery date 1 9am monday 50 0,06 4 21h monday 2 10am monday 120 0,05 3 22h monday 3 11h monday 260 0,03 5 23h monday 4 12h monday 200 0,04 2 2h Tuesday 1. Specify the priority for each task if the system shop floor control systems use each of the following sequencing rules: SPT, S / RO, EDD. 2. For each sequencing rule, calculate the time flow rate per task…K Using the FCFS rule for scheduling, the sequence is 1-2-3 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) = hours (enter your response as a whole number). Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Times Taken for Different Activities (hours) Cut and Sew Suit 1 2 3 7 4 5 Deliver 2 3 6 Assume that orders for suits have been listed in the above table in the order in which they were received DGardinIT performs home gardening jobs. The required jobs are shown in the following tableJob Preparing Area (days) Planting(days) once job is startedR 3 2S 1 3T 4 5U 8 5V 6 4W 4 3a- Which scheduling method would be best overall from (SPF, EDD, FCFS as in table)b- If job U was required to be made first then EDD will be used with eh rest, what would be thechange in average delay and…
- A group of six jobs is to be processed through a two-machine flow shop. The first operation involves cleaning and the second involves painting. Determine a sequence that willminimize the total completion time for this group of jobs. Processing times are as follows:PROCESSING TIME (hours)Job Work Center 1 Work Center 2A 5 5B 4 3C 8 9D 2 7E 6 8F 12 15 To employ Johnson’s rule, create a “blank” sequence first, such as:mhhe.com/stevenson13eEXAMPLE 41st 2nd 3rd 4th 5th 6thNow you are being hired as a scheduler in the manufacturing unit of surgical instruments. Your job is to schedule four jobs on the two machines. The job processing time in minutes for the four jobs is given below: A с D Machine 1 Machine 2 3.43 0.11 B 1.58 0.46 3.62 2.29 4.05 4.52 The optimal schedule using Johnson method and makespan for the jobs is: (A)BCBA, 12.79 minutes (B) ABCD, 5.41 minutes (C) DCBA, 12.79 minutes (D) CDBA, 5.41 minutesA nursing home must schedule nurses in a manner that balances providing adequate patient care while keeping costs down. From historical records, administrators can project the minimum number of nurses to have on hand during each day/time slot. This data is shown below. Shift Time Slot Minimum number of nurses needed 1 12 am-4 10 2 4 am-8 6 3 8 am-12 8 4 12 pm-4 12 5 4 pm-8 10 6 8 pm-12 14 Nurses must start work at the beginning of one of the four-hour shifts (starting as early as 12 am midnight or as late as 8pm evening) and work for eight hours. Nurses who begin working at 8 pm will work until 4 am the next morning. Formulate and solve the nurse-scheduling problem so as to minimize excess stagging while satisfying minimum staffing requrements. What is the value of total excess staffing?
- On Monday morning, Baxter Industries has the following jobs waiting for processing in two departments, milling, and drilling, in that order. Time Required (hours) Job Mill Drill 216 7 6 327 4 10 462 6 3 519 5 8 258 8 7 617 9 10 Develop a minimum makespan schedule using Johnson's rule. The schedule using Johnson's rule is - - - - - . Choose the correct Gantt chart with the minimum makespan schedule.The following jobs are waiting to be processed at Rick Solano’s machine center. Solano’s machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a workday). Job names refer to names of clients and contract numbers. Job Date job received Productiondays needed Date job due BR-02 228 15 300 CX-01 225 25 270 DE-06 230 35 320 RG-05 235 40 360 SY-11 231 30 310 a. Complete the following table. (Show your supporting calculations.) b.Which dispatching rule has the best score for flow time? c. Which dispatching rule would you select? Support your decision.A manutacturer is designing a product layout for a new product production. It plans to use a production line for B hours per day in order to meet forecasted demand of 100 units per day. The product requires 7 lasks in total. These tasks are namely, A, 8, CD, E, F, and G respectively. Task A does not have any predecessor to start. To start Task B, it requires Task A to be completed Starting tasks Cneeds, the tack B to be completed. Also, starting task D needed task B to be completed Task E can only start upon completion of Task C. Whescas starting lask F needs the completion of both the tasks D and E Finally, starting task G needed, task Fto be completed. 1the processing times for tasks, A BC D, E F, andG are 28, 2.1, 0.9, 1.0, 1.2, 1.8, are 4.7 minutes respectively. Applying the most following tasks nule for balancing the assembly line, with ties broken according to longest task time first, the tasks that will be assigned to the FIRST workstation are Select one OaAB, and C ODAB Oc None…