The machine shop of Reliable Manufacturing has to schedule eight jobs that are to be sent to final assembly for an important customer order. Currently, all eight jobs are in department X and must be routed to department Y after processing. The processing times (in days) for each job in each department follow: Dept/Job Dept. X Dept. Y A B D E F G H 2 2 5 4 7 5 4 10 3 6 3 8 6 6 Develop two schedules for operations in both departments. For your first schedule, use the SPT priority rule (based on X). Your second schedule should be based on Johnson's Rule. Compare the two schedules using average flow time, makespan, and average WIP inventory. Use a Gantt chart to display your schedules (i.e. a timeline).

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
3)
to final assembly for an important customer order. Currently, all eight jobs are in department X and
must be routed to department Y after processing. The processing times (in days) for each job in each
department follow:
The machine shop of Reliable Manufacturing has to schedule eight jobs that are to be sent
Dept/Job
Dept. X
Dept. Y
A
B
C
D
E
F
G
H
2
4
7
5
4
10
3
3
8
2
6
5
Develop two schedules for operations in both departments. For your first schedule, use the SPT priority
rule (based on X). Your second schedule should be based on Johnson's Rule. Compare the two
schedules using average flow time, makespan, and average WIP inventory. Use a Gantt chart to display
your schedules (i.e. a timeline).
Transcribed Image Text:3) to final assembly for an important customer order. Currently, all eight jobs are in department X and must be routed to department Y after processing. The processing times (in days) for each job in each department follow: The machine shop of Reliable Manufacturing has to schedule eight jobs that are to be sent Dept/Job Dept. X Dept. Y A B C D E F G H 2 4 7 5 4 10 3 3 8 2 6 5 Develop two schedules for operations in both departments. For your first schedule, use the SPT priority rule (based on X). Your second schedule should be based on Johnson's Rule. Compare the two schedules using average flow time, makespan, and average WIP inventory. Use a Gantt chart to display your schedules (i.e. a timeline).
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 7 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,