EXERCISE 10-4 Direct Labor and Variable Manufacturing
Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows:
Standard | Standard Rate | Standard |
Hours | per Hour | Cost |
18 minutes | $17.00 | $5.10 |
During August 5,750 hours of direct labor time were needed to make 20,000 units of the Jogging Mate. The direct labor cost totaled $102,350 for the month.
Required:
- What is the standard labor-hours allowed (SH) to makes 20,000 Jogging Mates?
- What is the
standard labor cost allowed (SH x SR) to make 20,000 Jogging Mates? - What is the labor spending variance?
- What is the labor rate variance and the labor efficiency variance?
- The budgeted variable manufacturing overhead rate is $4 per direct labor-hour. During August, the company incurred $21,850 in variable
manufacturing overhead cost. Compute the variable overhead rate and efficiency variances for the month.
Requirement1:
The standard labour hours allowed for producing actual output of 20,000jogging mates (units).
Answer to Problem 4E
Solution: TheStandard Labour hours allowed for producing actual output of 20,000 unit shall be as under:
Standard Labour hours allowed (SH) = Actual Output × Standard labour hours allowed per unit of output
Standard Labour hours allowed (SH) = 20,000 units × 0.30 hour per unit = 6,000 hours
Explanation of Solution
Given: The following information is available in the given problem;
Actual output: 20,000 units
Standard labour hours allowed per unit of output: 18 minutes (i.e. 18/60) =0.30 hour per unit
Formula: The formula used in the given problem is as follows:
Standard Labour hours allowed (SH) = Actual Output × Standard labour hours allowed per unit of output
Calculation: The Standard Labour hours allowed for producing actual output of 20,000 unit shall be ass under:
Standard Labour hours allowed (SH) = Actual Output × Standard labour hours allowed per unit of output
Standard Labour hours allowed (SH) = 20,000 units × 0.30 hour per unit = 6,000 hours
The Standard Labour hours allowed for actual output is computed by multiplying the actual output with the standard labour hours allowed per unit of output.
Requirement2:
Standard Labour cost for actual output.
Answer to Problem 4E
Solution: The standard cost for actual output shall be calculated as follows:
Standard cost for actual output = Standard Labour hours allowed for actual output × Standard rate per hour
Standard cost for actual output = 6,000 hours × $17 per hour = $102,000
Explanation of Solution
Given: The following information is available in the given problem;
Actual output: 20,000 units
Standard labour hours allowed for actual output: 6,000 hours
Standard rate per hour: $17.00 per hour
Formula: The formula used in the given problem is as follows:
Standard cost for actual output = Standard Labour hours allowed for actual output × Standard rate per hour
Calculation: The standard cost for actual output shall be calculated as follows:
Standard cost for actual output = Standard Labour hours allowed for actual output × Standard rate per hour
Standard cost for actual output = 6,000 hours × $ 17.00 per hour = $102,000
The Standard labour cost for actual output shall be computed by multiplying the standard labour hours allowed with standard labour rate per hour.
Requirement3:
Labour spending variance to be computed.
Answer to Problem 4E
Solution: The Labour spending variance shall be computed as under:
Labour Spending variance = Standard labour cost allowed for actual output- Actual labour cost
Labour Spending Variance = $102,000- $102,350 = $350 Unfavorable
Explanation of Solution
Given: The following information is available in the given problem;
Actual cost for output: $102,350
Standard cost allowed for actual output: $102,000
Formula: The formula used in the given problem is as follows:
Labour Spending variance = Standard labour cost allowed for actual output- Actual labour cost
Calculation: The Labour spending variance shall be computed as under:
Labour Spending variance = Standard labour cost allowed for actual output- Actual labour cost
Labour Spending Variance = $102,000- $102,350= $350 Unfavorable
The Labour spending variance is the difference between standard labour cost and actual cost incurred on labour. If the difference is positive, it will be favorable situation and if it is negative, it will be unfavorable situation.
Requirement4:
Labour rate and Labour efficiency variance to be computed.
Answer to Problem 4E
Solution: The Labour rate and labour efficiency variance shall be computed as under:
Labour rate variance = Actual Labour hours worked (Standard rate per hour − Actual rate per hr)
- =5,750 hours ($17.00 per hour - $17.80 per hour) = $4,600 unfavorable
= $17.00 per hour (6,000 hours − 5,750 hours) = $ 4,250 favorable
Explanation of Solution
Given: The following information is available in the given problem;
Actual cost for output: $102,350
Standard cost allowed for actual output: $102,000
Actual hours used: 5,750 hours
Standard hours allowed: 6,000hours
Standard rate per hour: $17.00 per hour
Formula: The formula used in the given problem is as follows:
Labour rate variance = Actual Labour hours worked (Standard rate per hour − Actual rate per hr)
Labour Efficiency Variance = Standard rate per hour (Standard hours - Actual labour hours)
Calculation: The Labour rate and labour efficiency variance shall be computed as under:
Labour rate variance = Actual Labour hours worked (Standard rate per hour − Actual rate per hr)
- =5,750 hours ($17.00 per hour - $17.80 per hour) = $4,600 unfavorable
= $17.00 per hour (6,000 hours − 5,750 hours) = $ 4,250 favorable
The Labour rate variance recognize the difference due to labour rate and Efficiency variance recognizes the difference of hours worked. The sum of both the variance shall be equal to labour spending variance.Note: Actual labour rate per hour shall be computed as follows:
Actual Labour rate per hour: Actual labour cost ÷ Actual hours worked
= $102,350 ÷ 5,750 hours = $17.80 per hour
Requirement5:
Variable overhead rate and efficiency variance to be computed.
Answer to Problem 4E
Solution: The Variable overhead rate and efficiency variance shall be computed as under:
Variable Overheads rate variance = Actual hours worked (Standard overhead rate per hour − Actual overhead rate per hour)
=5,750 hours ($4.00 per hour - $3.80 per hour) = $1,150 favorable
= $4.00 per hour (6,000 hours − 5,750 hours) = $ 1,000 favorable
Explanation of Solution
Given: The following information is available in the given problem;
Actual cost for output: $21,850
Standard overhead cost allowed per hour: $4.00 per hour
Actual hours used: 5,750 hours
Standard hours allowed: 6,000hours
Formula: The formula used in the given problem is as follows:
Variable Overheads rate variance = Actual hours worked (Standard overhead rate per hour − Actual overhead rate per hour)
Variable overhead Efficiency Variance = Standard rate per hour (Standard hours - Actual hours)
Calculation: The Variable overhead rate and efficiency variance shall be computed as under:
Variable Overheads rate variance = Actual hours worked (Standard overhead rate per hour − Actual overhead rate per hour)
=5,750 hours ($4.00 per hour - $3.80 per hour) = $1,150 favorable
= $4.00 per hour (6,000 hours − 5,750 hours) = $ 1,000 favorable
The Variable overhead rate variance recognize the difference due to overhead rate and Efficiency variance recognize the difference of hours worked. The sum of both the variance shall be equal to Variable overhead spending variance.
Note: Actual variable overheads rate per hour shall be computed as follows:
Actual Variable overhead rate per hour: Actual variable overheads cost ÷ Actual hours worked
= $21,850 ÷ 5,750 hours = $3.80 per hour
To conclude, it can be said that thespending variance is the sum total of both the factors i.e. rate variance and efficiency variance.
Want to see more full solutions like this?
Chapter 10 Solutions
Managerial Accounting
- Problem Set: Module 5 1. PR.08.02B 2. TMM.09.02 3. BE.09.02.EXCEL.ALGO 4. BE.09.01.EXCEL.ALGO 5. TMM.08.01 engagenow.com Direct labor variances Bellingham Company produces a product that requires 3 standard direct labor hours per unit at a standard hourly rate of $20.00 per hour. 15,000 units used 63,300 hours at an hourly rate of $19.55 per hour. Open spreadsheet + This information has been collected in the Microsoft Excel Online file. Open the spreadsheet, perform the required analysis, and input your answers in the questions below. 42 a. Direct labor rate variance b. Direct labor time variance c. Direct labor cost variance What is the direct labor (a) rate variance, (b) time variance, and (c) cost variance? Round your answers to the nearest dollar. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. $arrow_forwardExercise 11-4 Direct Labor and Variable Manufacturing Overhead Variances [LO11-2, LO11-3] Erie Company manufactures a small mp3 player called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate mp3 player are as follows: StandardHours Standard Rateper Hour StandardCost 27 minutes $5.40 $2.43 During August, 9,410 hours of direct labor time were needed to make 19,400 units of the Jogging Mate. The direct labor cost totaled $49,873 for the month. Required: 1. According to the standards, what direct labor cost should have been incurred to make 19,400 units of the Jogging Mate? By how much does this differ from the cost that was incurred? (Round Standard labor time per unit and Standard direct labor rate to 2 decimal places.) 2. Break down the difference in cost from (1) above into a labor rate variance and a labor efficiency variance. (Indicate the effect of each variance by selecting…arrow_forwardQuestion Content AreaApril Industries employs a standard costing system in the manufacturing of its sole product, a park bench. They purchased 60,000 feet of raw material for $360,000, and it takes 5 feet of raw materials to produce one park bench. In August, the company produced 11,000 park benches. The standard cost for material output was $110,000, and there was an unfavorable direct materials quantity variance of $7,000. A. What is April Industries’ standard price for one unit of material? Standard cost per unit $fill in the blank 1B. What was the total number of units of material used to produce the August output? Actual quantity feet fill in the blank 2 UnitsC. What was the direct materials price variance for August? Direct materials price variance $ fill in the blank 3arrow_forward
- Activity Rates and Product Costs using Activity-Based Costing Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows: Budgeted Activity Activity Cost Activity Base Casting $215,160 Machine hours Assembly 189,550 Direct labor hours Inspecting 30,520 Number of inspections Setup 39,730 Number of setups Materials handling 36,960 Number of loads Corporate records were obtained to estimate the amount of activity to be used by the two products. The estimated activity-base usage quantities and units produced follow: Activity Base Entry Dining Total Machine hours 5,180 4,600 9,780 Direct labor hours 4,460 6,690 11,150 Number of inspections 1,660 520 2,180 Number of setups 230 60 290 Number of loads 700 180 880 Units produced 10,400 5,200 15,600 a. Determine the activity rate for each activity. If required, round the rate to the…arrow_forwardQuestion 3 Owen plc manufactures one product, and the entire product is sold as soon as it is produced. The company operates a standard costing system and analysis of variances is made every month. The standard cost card for a product is as follows. Materials (4 Kg at £4 per Kg) Labour (4 Hours at £5 per hr) Variable overheads (5 hrs at £2 per hr) Fixed overheads (6 hrs at £3 per hr) Budgeted selling price is £80 per unit Budgeted production Budgeted sales There is no opening inventory The actual results are as follows: Sales: 8,400 units for £613,200 Production: 9,900 units Actual costs: Materials (35,464 kg): £163,455 Labour: £ 234,515 Variable overheads: £97,348 Fixed overheads: £ 144,074 £ per Unit 16 20 10 18 £64 8.900 units 8,200 units Required: a) Prepare a flexed budget and calculate the total variances b) Using the data, analyse each of the cost variances: Materials; Labour; Variable Overheads and; Fixed Overheads c) Using data, calculate the Sales price variance and the Sales…arrow_forwardQuestion Content Area April Industries employs a standard costing system in the manufacturing of its sole product, a park bench. They purchased 60,000 feet of raw material for $240,000, and it takes 5 feet of raw materials to produce one park bench. In August, the company produced 10,000 park benches. The standard cost for material output was $100,000, and there was an unfavorable direct materials quantity variance of $7,000. A. What is April Industries’ standard price for one unit of material? Standard cost per unit $fill in the blank 1 B. What was the total number of units of material used to produce the August output? Actual quantity feet fill in the blank 2 Units C. What was the direct materials price variance for August? Direct materials price variance $ fill in the blank 3arrow_forward
- Question Content Area The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of actual production are as follows: Standard Costs Line Item Description Value Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.70 per hour Variable overhead 3 hours per unit at $1.93 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $8,200 The fixed factory overhead volume variance is a. $0 b. $728 unfavorable c. $910 unfavorable d. $728 favorablearrow_forwardQ # 3 UT- Sports Company uses standard cost system. The cost data for various elements of cost for the manufacture of 20,000 cricket bats is as follows: STANDARDS ACTUAL Direct Material 5,000 units @ Rs. 70 4,800 units @ Rs. 75 Direct Labor 2,000 hours @ Rs. 100 2,300 hours @ Rs. 110 Factory Overhead 80% of Direct Labor Rs. 127,000 All costs are charged to work in process at standard and separate variances accounts are established. There is no beginning or ending inventory of work in process Required Entries in general journal to record the above information Compute the actual cost of one Cricket Bat with its standard cost.arrow_forwardQ # 3 UT- Sports Company uses standard cost system. The cost data for various elements of cost for the manufacture of 20,000 cricket bats is as follows: STANDARDS ACTUAL Direct Material 5,000 units @ Rs. 70 4,800 units @ Rs. 75 Direct Labor 2,000 hours @ Rs. 100 2,300 hours @ Rs. 110 Factory Overhead 80% of Direct Labor Rs. 127,000 All costs are charged to work in process at standard and separate variances accounts are established. There is no beginning or ending inventory of work in process Required Material Price Variance and Material Quantity Variance Labor Rate Variance and Labor Time Variance Overhead Variance Entries in general journal to record the above information Compute the actual cost of one Cricket Bat with its standard cost.arrow_forward
- Direct Labor and Variable Manufacturing Overhead Variances Erie Company manufactures a mobile fitness device called the Jogging Mate. The company uses standards to control its costs. The labor standards that have been set for one Jogging Mate are as follows: During August. 5,750 hours of direct labor time were needed to make 20,000 units of the Jogging Mate. The direct labor cost totaled $102,350 for the month. Required: 1. What is the standard labor-hours allowed (SH) to makes 20,000 Jogging Mates? 2. What is the standard labor cost allowed (SH × SR) to make 20,000 Jogging Mates? 3. What is the labor spending variance? 4. What is the labor rate variance and the labor efficiency variance?arrow_forward--/1 Question 16 View Policies Current Attempt in Progress Clark Company manufactures a product with a standard direct labor cost of two hours at $18 per hour. During July, 1400 units were produced using 3200 hours at $18.30 per hour. The labor quantity variance was port O $7320 U. O $7320 F. O $7200 U. O $6480 U. hp ins fiu f10 prt s fg f7 f8 f6 f5 +. & 96. 80 7 %D Y н TO 96arrow_forwardCOVID 19 Co produces two different products (Product Y and Product B) using two different activities Machining, which uses machine hours as an activity driver, and Inspection, which uses number of batches as an activity driver. The cost of Machining is $so0.000, while the cost of Inspection is $30.000. Product Y uses z0% of total machine hours and 75% of total batches What is the total Machining cost assigned to Product B Select one a. 5400.000 b. S22.500 C3375.000 d.57.500arrow_forward
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub