Concept explainers
Determine material requirements plans for pans N and V and subassembly I as described in Solved Problem 3 for each of the following:
a. Assume that there are currently 100 Ns on hand and scheduled receipts of 40 Is and 10 Vs at the beginning of week 3. No Es are on hand: 120 Es are needed at the start of week 5.
b. Assume on-hand and scheduled receipts as in part a. Now suppose that 100 Es are needed at the stmt of week 5 and 55 at the start of week 7. Also, use multiples of these order sizes: N, 800; V, 200. Use lot-for-lot ordering for I.
C. Using your answer to part b, update the MRP for V, using the following additional information for each of these cases: (1) one week has elapsed (making it the start of week 2), and (2) three weeks have elapsed (making it the start of week 4).
The updated master
a)
To prepare A Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which is used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Scheduled receipts is 40 units of Component I and 10 units of Component C would arrive at the beginning of Week 3. 120 units of Component E are needed at the beginning of Week 5.
Product structure tree:
Prepare master schedule:
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Quantity | 120 |
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 120 units of End item E, which must be shipped at the start of week 5.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 120 units (120-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 120 units in the beginning of week 5. Hence, they need to order for 120 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 40 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 200 units on week 4 (240-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 200 units in the beginning of week 4. Hence, they need to order for 200 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 100 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 700 units on week 3 (800-100).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 700 units in the beginning of week 3. Hence, they need to order for 700 units (as the lot size is lot-for-lot) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 10 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 190 units on week 3 (200-10).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 700 units in the beginning of week 3. Hence, they need to order for 700 units (as the lot size is lot-for-lot) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 0 units. Calculation is as follows:
b)
To prepare A Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Scheduled receipts is 40 units of Component I and 10 units of Component C would arrive at the beginning of week 3. 100 units of Component E are needed at the beginning of week 5 and 55 units needed at the beginning of week 7. Lot size is multiple of 800 for Component N, multiples of 200 for Component V, and lot-for-lot for Component E and Component I.
Product structure tree:
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 100 units of End item E in the start of week 5 and 55 units of End item E in the start of week 7.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units in week 5 (100-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 100 units in the beginning of Week 5. Hence, they need to order for 100 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 40 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 160 units on week 4 (200-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 160 units in the beginning of week 4. Hence, they need to order for 160 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 100 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 540 units on week 3 (640-100).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 540 units in the beginning of week 3. Hence, they need to order for 800 units (as the lot size is multiples of 800) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 260 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 620 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 10 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 150 units on week 3 (160-10).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 150 units in the beginning of week 3. Hence, they need to order for 200 units (as the lot size is multiples of 200) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 50 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 140 units. Calculation is as follows:
c)
1)
To prepare: Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Scheduled receipts is 800 units of Component N and 200 units of Component V would arrive at the beginning of week 3. Lot size is multiple of 800 for Component N, multiples of 200 for Component V, and lot-for-lot for Component E and Component I.
Week 1 has elapsed. Hence, plan has to be prepared from week 2 through week 9. 100 units of Component E are needed at the beginning of week 5 and 55 units needed at the beginning of week 7. In addition to that, 100 units of End item E are needed in week 9.
Product structure tree:
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 100 units of End item E in week 5, 55 units in week 7, and 100 units in week 9.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units (100-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 100 units in the beginning of week 5. Hence, they need to order for 100 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 40 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 160 units on week 4 (200-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 160 units in the beginning of week 4. Hence, they need to order for 160 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 100 units.
- Scheduled receipt is 800 units at the beginning of week 3
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 180 units on week 5 (440-260).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 180 units in the beginning of week 5. Hence, they need to order for 800 units (as the lot size is multiples of 800) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 4 is 260 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 620 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 210 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 60 units on week 5 (110-50).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 700 units in the beginning of week 3. Hence, they need to order for 700 units (as the lot size is lot-for-lot) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 50 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 140 units. Calculation is as follows:
1)
To prepare: Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Scheduled receipts is 800 units of Component N and 200 units of Component V would arrive at the beginning of week 3. Lot size is multiple of 800 for Component N, multiples of 200 for Component V, and lot-for-lot for Component E and Component I.
Week 1 has elapsed. Hence, plan has to be prepared from week 2 through week 9. 100 units of Component E are needed at the beginning of week 5 and 55 units needed at the beginning of week 7. In addition to that, 100 units of End item E are needed in week 9.
Product structure tree:
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 100 units of End item E in week 5, 55 units in week 7, and 100 units in week 9.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units (100-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 100 units in the beginning of week 5. Hence, they need to order for 100 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 40 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 160 units on week 4 (200-40).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 160 units in the beginning of week 4. Hence, they need to order for 160 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 100 units.
- Scheduled receipt is 800 units at the beginning of week 3
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 180 units on week 5 (440-260).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 180 units in the beginning of week 5. Hence, they need to order for 800 units (as the lot size is multiples of 800) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 3.
- Projected on hand inventory for week 4 is 260 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 620 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 0 units.
- Scheduled receipt is 210 units at the beginning of week 3.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 60 units on week 5 (110-50).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 700 units in the beginning of week 3. Hence, they need to order for 700 units (as the lot size is lot-for-lot) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 1.
- Projected on hand inventory for week 4 is 50 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 140 units. Calculation is as follows:
2)
To prepare: Material requirement plan for the given information.
Introduction: Materials Requirement Planning (MRP) is the planning or scheduling system, which can be used in the manufacturing process. It is used to plan the number of items required to produce one unit of finished goods (end item).
Explanation of Solution
Given information:
On-hand balances are 100 units of Component N and 0 units of Component E. Lot size is multiple of 800 for Component N, multiples of 200 for Component V, and lot-for-lot for Component E and Component I.
Two weeks (week 2 and week 3) has elapsed. Hence, plan has to be prepared from week 4 through week 11. 100 units of Component E are needed at the beginning of week 5 and 55 units needed at the beginning of week 7. In addition to that, 100 units of End item E are needed in week 9.
Planned order releases from 2nd and 3rd week should be used as scheduled receipt units. Scheduled receipt are 160 units of Component I at the start of 4th week, 800 units of Component N at the start of 5th week, and 200 units of Component V at the start of 5th week.
Product structure tree:
Develop a material requirement planning for End item E:
- It is given that Person X has received an order to deliver 100 units of End item E in week 5, 55 units in week 7, and 100 units in week 9.
- Beginning inventory is given as 0 units.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units at week 5 (100-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 100 units in the beginning of week 5. Hence, they need to order for 100 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 4.
Develop a material requirement planning for Component I (2):
- End item E is the parent item of Component I (2). Hence, the planned order release of E is the gross requirement for Component I (2). As number of units required is 2 for Component I, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component I.
- Beginning inventory is given as 40 units.
- Scheduled receipt is 160 units at the beginning of week 4.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 100 units on week 6 (110-0).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 1 week. Company requires 110 units in the beginning of week 6. Hence, they need to order for 110 units (as the lot size is lot-for-lot) on previous week (as the lead-time is 1 week). Thus, company need to order the required units in week 5.
- Projected on hand inventory for week 5 is 0 units. Calculation is as follows:
Develop a material requirement planning for Component N (4):
- Component I (2) is the parent item of Component N (4). Hence, the planned order release of Component I (2) is the gross requirement for Component N (4). As number of units required is 4 for Component N, the planned order release row should be multiplied with 2 to attain the gross requirement column of Component N.
- Beginning inventory is given as 260 units.
- Scheduled receipt is 800 units at the beginning of week 3
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 180 units on week 7 (800-620).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 180 units in the beginning of week 7. Hence, they need to order for 800 units (as the lot size is multiples of 800) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 5.
- Projected on hand inventory for week 5 is 1,060 units. Calculation is as follows:
- Projected on hand inventory for week 6 is 620 units. Calculation is as follows:
Develop a material requirement planning for Component V:
- Component I (2) is the parent item of Component V. Hence, the planned order release of Component I (2) is the gross requirement for Component V. As number of units required is 1 for Component V, the planned order release row should be multiplied with 1 to attain the gross requirement column of Component V.
- Beginning inventory is given as 50 units.
- Scheduled receipt is 200 units at the beginning of week 5.
- Net requirement can be calculated by subtracting the projected on-hand from the gross requirement. Hence, the net requirement is 60 units on week 7 (200-140).
- Planned order release is the order given by the company and planned order receipts is the order received by the firm.
- Lead-time is given as 2 weeks. The company requires 60 units in the beginning of week 7. Hence, they need to order for 200 units (as the lot size is multiples of 200) two weeks before (as the lead-time is 2 weeks). Thus, company need to order the required units in week 5.
- Projected on hand inventory for week 6 is 140 units. Calculation is as follows:
Want to see more full solutions like this?
Chapter 12 Solutions
EBK OPERATIONS MANAGEMENT
Additional Business Textbook Solutions
Business in Action (8th Edition)
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Principles Of Operations Management
Operations Management: Processes and Supply Chains (11th Edition)
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Operations Management: Sustainability and Supply Chain Management (12th Edition)
- A factory has just received an order for 100 units of an end item, which are to be shipped at the start of week 8. Relevant information of the end item and the components is as follows. Item Lead Time (weeks) On Hand Inventory Scheduled receipts Order Policy Direct Components End item 2 30 lot for lot A(4), B(3), C(2) A 3 20 54 at week 3 lot for lot D(2) B 2 10 68 at week 4 lot for lot D(5) C 1 100 multiple of 60 D 1 20 min. of 500 Develop the material requirements plan (please print out an empty MRP table to work with), and determine what the "projected available balance" is for component D at week 8. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardProblem 9-11 (Algo) Assume that Product Z is made of two units of A and three units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty five units of Product Z are required in Period 10. (Assume that there is currently no inventory on-hand of any of these items.) b. Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave the cells blank, whenever zero (0) is required.) Item: Z OH: 0 LT: 2 SS: 0 Q: L4L Item: A OH: 0 LT: 1 SS: 0 Q: L4L Item: B OH: 0 LT: 1 SS: 0 Q: L4L Period: Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Gross…arrow_forwardA firm that produces electric golf carts has just received an order for 200 carts, which must be ready for delivery at the start of week 8. Information concerning the product structure, lead times, and quantities on hand is shown in the following table. Use this information to do each of the following: a. Develop a material requirements plan that will provide 200 golf carts by week 8, assuming lot-for-lot ordering. (Excel)arrow_forward
- Complete the following MRP table below, note the following: 1) Beginning inventory is 35 2) Order lot size is 40 3) Lead time is one week 2 3 4 5 30 40 week 1 6 7 8 9 10 Gross requirement 35 10 40 30 30 55 Schedule receipts Projected on hand (35) Net requirement Planned order receipts Planned order releasesarrow_forwardDiscuss the advantages and disadvantages of including safety stock in MRP lot-sizing calculations. Do you think a production control manager would be reluctant to build to safety stock if he or she is behind schedule?arrow_forwardGiven the following information, develop a material requirements plan for end item A and its components. 50 and 80 units of A are needed at the beginning of week 6 and 8, respectively. On-Order Item A B с D E Item A BUDE C C(2) Week 3: 50 On-Hand 20 60 150 10 On-Hand 20 60 150 10 Week 3:30, Week 5:80 Week 3:50, Week 5:100 B Week 4: 50, Week 6: 100 Week 3: 50, Week 5: 80 D(3) The planned order release for Product B is: E 200 (Week 2) On-Order 200 (Week 2) A E D(3) Lead Time 1 wk 2 wks 1 wk 2 wks 1 wk Lead Time 1 wk 2 wks 1 wk 2 wks 1 wk C Order Size lot-for-lot 50 100 200 lot-for-lot Order Size lot-for-lot 50 100 200 lot-for-lot C Earrow_forward
- On which factors does the costs of short stacks depends?arrow_forwardWhat would be the weekly gross requirements of B and C, respectively, for weeks 11-16?arrow_forwardItem STUVWX>N Y 2. The demand for assembly S is 100 units and it is due in Week 15. Each unit of S requires one unit of T and 0.5 units of U. Each unit of T requires one unit of V, two units of W, and one unit of X. Finally, each unit of U requires 0.5 units of Y and three units of Z. Z Item S T U V W X Y Z a) Calculate the planned orders for all the items. b) Use time phasing to determine an overall schedule. S OH Gross Requirements Inv 100 20 20 10 30 30 15 25 10 2 1 1 1 2 2 1 Lead Time Due Date (weeks) (week) 15 1 T W (2) X Net Requirements Release Date U (0.5) Y (0.5) Planned Order Z (3) Lot Size Policy L4L X10 X5 Min 50 F100 X50 F100 Min 100arrow_forward
- Canvas → x CO D Given the following information, develop a material requirements plan for end item A and its components. 50 and 80 units of A are needed at the beginning of week 6 and 8, respectively. Item On-Hand On-Order Lead Time Order Size A 20 1 wk lot-for-lot B. 2 wks 50 60 1 wk 100 150 200 (Week 2) 2 wks 200 10 1 wk lot-for-lot В C(2) C D(3) E E D(3) E The planned-order release for product A is:arrow_forwardGiven the following MRP matrix for Item D, the planned order receipt for period 4 is ITEM: D Period Lot Size: Mul 100 LT: 1 1 2 3 4 6 Gross Requirements Schedule Receipts Project on Hand Net Requirements Planned Order Receipts 60 90 150 150 180 270 120 120 Planned Order Releases 100 200 220 DELLarrow_forwardDevelop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the startof week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are inproduction and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.