Question
Book Icon
Chapter 14, Problem 29P

(a)

Summary Introduction

Interpretation:

The time period required on an average to finish the job.

Concept Introduction:

Schedule the job on the basis of the FCFS . Then determine the average flow time for the each job. Calculate the average flow time that is required to finish the each job. Then calculate the average tardiness by adding the delay time of the order.

(a)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in HM Catering Company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

Schedule the jobs based on the first come first served:

    Hours12345678910
    JobWXYZ

From the table, it is observed that the flow time of the job W is 4 hours which due in 5 hours. Thus, W has no delay in job.

The flow time of the job X is 7 hours which due in 9 hours. Thus, X has no delay in job.

The flow time of the job Y is 9 hours which due in 2 hours. Thus, X has 7 hours delay in job.

In order of the job Y :

The flow time of the job Z is 10 hours which due in 1 hour. Thus, it has a delay of 9 hours.

In order of the job Z :

Thus, calculate the average flow time that is required to finish the each job:

  4hours+7hours+9hours+10hours4=7.5hours

Now, calculating the average tardiness, adding the delay time of the order and divide it by the number of the orders;

  AT=0+0+7+94AT=4hours

(b)

Summary Introduction

Interpretation:

The job that will be late and the average job tardiness.

Concept Introduction:

Schedule the job on the basis of the SPT . Then determine the average flow time for the each job. Calculate the average flow time that is required to finish the each job. Then calculate the average tardiness by adding the delay time of the order.

(b)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

Schedule the jobs based on the SPT ,

    Hours12345678910
    JobZYXW

From the table, it can be observed that Z has the 1 hour flow time which due in 1 hour. Z will be deliver on time.

  Y has the 3 hour flow time which due in 2 hour. Y will be delay 1 hour of the job.

  X has the 6 hour flow time which due in 9 hour. There will be no delay in order of the job X .

  W has the 10 hours flow time which due in 5 hours. Thus, there is delay of 5 hours on job order of W

Thus, calculate the average flow time that is required to finish the each job:

  1hours+3hours+6hours+10hours4=4hours

Now, calculating the average tardiness, adding the delay time of the order and divide it by the number of the orders;

  AT=0+1+0+54AT=1.5hours

(c)

Summary Introduction

Interpretation:

The job that will be late and the average job tardiness.

Concept Introduction:

Schedule the job on the basis of the EDD . Then determine the average flow time for the each job. Calculate the average flow time that is required to finish the each job. Then calculate the average tardiness by adding the delay time of the order.

(c)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

Schedule the jobs based on the EDD ,

    Hours12345678910
    JobZYWX

From the table, it can be observed that Z has the 1 hour flow time which due in 1 hour. Z will be no delay.

  Y has the 3 hour flow time which due in 2 hour. Y will be delay 1 hour of the job.

  W has the 7 hour flow time which due in 5 hour. There will be delay of 2 hours for the job.

  X has the 10 hour flow time which due in 9 hours. There will be delay of 1 hour in order of the job X .

Now, calculating the tardiness, adding the delay time of the order and divide it by the number of the orders;

  AT=0+1+2+14AT=1hour

Thus, calculate the average flow time that is required to finish the each job:

  1hour+3hours+7hours+10hours4=5.25hours

(d)

Summary Introduction

Interpretation:

The most efficient sequence from the FCFS,SPT,EDD .

Concept Introduction:

The efficiency can be measured as the average tardiness or the number of jobs delayed and the average flow time.

(d)

Expert Solution
Check Mark

Explanation of Solution

Given information:

The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:

    JobProcessing Time
    (hrs)
    Due (hrs)
    W45
    X39
    Y22
    Z11

The efficiency can be measured as the average tardiness or the number of jobs delayed and the average flow time.

Average flow time:

By comparing the average flow time, it is observed that SPT method gives the lowest average flow time.

Average tardiness:

By comparing the average tardiness, it is observed that EDD method gives the lowest average tardiness.

Number of jobs delayed:

Both FCFS and SPT have the lower number of the jobs delayed as compared to the EDD method.

Therefore, it depends on the owner which gives the priority to the most efficient method will vary.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
The following jobs are waiting to be processed at Rick Solano’s machine center. Solano’s machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a workday). Job names refer to names of clients and contract numbers. Job Date job received Productiondays needed Date job due BR-02 228 15 300 CX-01 225 25 270 DE-06 230 35 320 RG-05 235 40 360 SY-11 231 30 310 a. Complete the following table. (Show your supporting calculations.) b.Which dispatching rule has the best score for flow time? c. Which dispatching rule would you select? Support your decision.
Using the FCFS rule for scheduling, the sequence is 1-2-3 For the schedule developed using the FCFS rule, the total length of time taken to complete the three suits (including delivery) : hours (enter your response as a whole number). = G Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits. Times Taken for Different Activities (hours) Cut and Sew 3 5 6 Suit 1 2 7 3 Deliver 4 2 ∞ N 8 Assume that orders for suits have been listed in the above table in the order in which they were received.
What are the benefits and drawbacks of the shortest processing time rule (SPT)?
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY