Question
Chapter 6, Problem 13ME
To determine
Compute the revenue, expense, and income for each year 2019 through 2021.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Bartov Corporation agreed to build a warehouse for $2,500,000. Expected (and actual) costs for the warehouse follow : 2019, $400,000; 2020, $1,000,000; and 2021, $500,000. The company completed the warehouse in 2021. Compare revenues, expenses, and income for each year 2019 through 2021 assuming that Bartov’s performance obligation for the warehouse is fulfilled over time and that the costs incurred provide a close approximation of the value conveyed to the customer.
Research and development cost for Herald Corporation for the year ended December 31, 2018:
Project A - Expected total revenues P7,000,000, starting in early 2018. Expected total costs will be
P5,000,000. Costs incurred to date, all in 2019, are P2,200,000.
Project B - Expected total revenues P6,000,000. Costs incurred to date are P3,500,000. Expected
total costs are P4,500,000. The commencement of commercial sales is uncertain due to problems in
raising funds to cover the final development costs.
Project C - Expected total revenues, P3,500,000 with P1,000,000 of revenue already earned in 2018.
Total development costs incurred, all in 2018, were P3,800,000.
Research projects. Total costs spend in 2018 were P1,500,000.
What total amount should be charged against income in 2018 related to the research and
development costs?
Bartov Corporation agreed to build a warehouse for $2,500,000. Expected (and actual) costs for the warehouse follow: 2019, $400,000; 2020, $1,000,000; and 2021, $500,000. The company completed the warehouse in 2021. Compute revenues, expenses, and income for each year 2019 through 2021 assuming that Bartov’s performance obligation for the warehouse is fulfilled over time and that the costs incurred provide a close approximation of the value conveyed to the customer.
Round percentages to the nearest whole percent. Use rounded percentages to calculate subsequent answers.
Chapter 6 Solutions
FINANCIAL ACCOUNTING
Knowledge Booster
Similar questions
- On March 1, 2019, Elkhart enters into a new contract to build a specialized warehouse for 7 million. The promise to transfer the warehouse is determined to be a performance obligation. The contract states that if the warehouse is usable by November 30, 2019, Elkhart will receive a bonus of 600,000. For every week after November 30 that the warehouse is not usable, the bonus will decrease by 150,000. Elkhart provides the following completion schedule: Required: 1. Assume that Elkhart uses the expected value approach. What amount should Elkhart use for the transaction price? 2. Assume that Elkhart uses the most likely amount approach. What amount should Elkhart use for the transaction price? 3. Next Level What is the purpose of assessing whether a constraint on the variable consideration exists?arrow_forwardA price company from time to time embarks on a research program when a special project seems to offer possibilities in 2019 the company expands $325,000 on a research project, but by the end of 2019, it is possible to determine whether any benefits will be driven from it. What account should be charged from 325,000 and how should be shown in the financial statement? Additional engineering and consulting costs incurred in 2021 are required to advance the design of the project in the manufacturing stage. Total $60,000. These costs enhance the design of the product considerably. Discuss the proper account treatment for this cost.arrow_forwardPaul Constructions has entered into a contract beginning January 1, 2020, to build a pool. It has been estimated that the pool will cost P300,000, and will take three years to construct. The pool will be billed to the purchasing at P450,000. The following data pertain to the construction period. 2020 135,000 165,000 2021 210,000 90,000 2022 0 Cost to date: Estimated cost to complete. Progress billing to date. Cash collected to date 135.000 120.000 275.000 250,000 450,000 450.000 During 2020, Costs incurred include P15,000 standard materials stored at the site to be used in 2022 to complete the project. Using the percentage of completion method, compute the recognize gross profit for 2022: a. 52,500 b. 45,000 c. 97.500 d. 150,000 2. The CIP net of Progress billing is a. 27.500 current liability b. 32,500 current asset c. 167,500 current asset. d. 102,500 current liabilityarrow_forward
- Recording Long-Term Construction: Recognize Revenue at a Point in Time and Over Time Watson Construction Company contracted to build a plant for $500,000. Construction started in January 2020 and was completed in November 2021. Watson uses the cost-to-cost method to measure the completion of its performance obligations. Data relating to the contract follow. 2020 2021 Costs incurred during year $290,000 $120,000 Estimated additional costs to complete 125,000 0 Billings during year 270,000 230,000 Cash collections during year 250,000 250,000 Revenue Recognized at a Point in Time Revenue Recognized Over Time a. Provide the 2020 and 2021 journal entries for Watson assuming revenue is recognized at a point in time. Provide entries for (1) construction costs incurred, (2) progress billings, (3) cash collections, and (4) revenues and expenses. Note: If a journal entry isn't required for the transaction, select "N/A" as the account names and leave the Dr. and Cr.…arrow_forwardDuring 2019, Gulf Co. started a construction project with a total contract price of $3,500,000. Additional information is given below: 2019 2020 Actual costs incurred during the S1,350,000 S1,525,000 year Estimated remaining costs Billings to customers Collected from customers 1,350,000 1,200,000 2,300,000 1,000,000 2,400,000 What amount of gross profit should be recognized in 2020?arrow_forwardGinebraCorporation recognizes construction revenue and cost using the percentage of completion method. During 2021, a single long-term project was begun which continued through 2021. Information on the project follows: 2021. 2022 Partial billing on contract 1,000,000. 4,200,000 Accounts receivable 1,000,000 3,000,000 Construction cost 1,050,000 1,920,000 Construction in progress 1,220,000 3,640,000 What is the gross profit recognized from this long-term construction contract in year 2021 and 2022, respectively? 2021 2022 A.220,000. 2,280,000 B.170,000. 500,000 C.220,000. 1,000,000 D.170,000. 1,280,000arrow_forward
- Swifty Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $894,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $263,120 $412,620 $607,000 Estimated costs to complete 334,880 185,380 –0– Progress billings to date 272,000 545,000 894,000 Cash collected to date 242,000 495,000 894,000 (a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period. (If answer is 0, please enter 0. Do not leave any fields blank.) Gross profit recognized in 2020 $ Gross profit recognized in 2021 $ Gross profit recognized in 2022 $ (b) Using the completed-contract method, compute the estimated…arrow_forwardDetermining Classification of Software Costs During 2019, Accounting Software Inc. incurred $200,000 developing a working model of a new software program. During calendar 2020, an additional $50,000 of costs is incurred on the final coding and testing of the product masters. The product is available for sale as of the beginning of 2021 and is expected to have a four-year economic life. Costs incurred in 2021 pertaining to the production of the software and training materials totaled $210,000. Determine how the costs would initially be recorded: (1) research and development expense, (2) non-research and development expense, or (3) intangible asset. Classification Amount 1. Research and development expense 2. Non-research and development expense 3. Intangible asset 2$arrow_forwardIn 2021, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2021 (from construction progress billings) $ 37.5 Actual construction costs incurred in 2021 $ 135 Cash collected on project during 2021 $ 105 Construction in progress, 12/31/2021 $ 207 Estimated percentage of completion during 2021 60 % How much cash remains to be collected by CCC on the project?arrow_forward
- Shanahan Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $609,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $896,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $266,640 $412,080 $617,000 Estimated costs to complete 339,360 193,9200 –0– Progress billings to date 270,000 545,000 896,000 Cash collected to date 240,000 495,000 896,000 A/ Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period. Gross profit recognized in 2020: Gross profit recognized in 2021: Gross profit recognized in 2022: B/ Using the completed-contract method, compute the estimated gross profit that would be recognized during each year of the construction period. Gross profit recognized in 2020: Gross profit recognized in 2021: Gross…arrow_forwardSuppose a company spends $100,000 on research and development in 2021. As a result of the products developed, additional revenue is generated over the next five years totaling $600,000. When is the cost of the research and development in 2021 recognized as an expense? Multiple Choice Evenly over the period 2022-2026. Full amount in 2026. Evenly over the period 2021-2025. Full amount in 2021.arrow_forwardHow much is the Gross Profit/Loss Realized in 2018? Triple Take Construction Co. began construction of a project in 2017 for a contract price of P9,600,000. The project is to be completed in 4 years or in the year 2021. The following are the details regarding the construction project: 2017 2018 2019 Costs incurred to date 2160,000 4,500,000 7,520,000 Estimated cost to complete Progress Billings to date Cash Collections for the year 6,840,000 5,500,000 1,880,000 2304,000 4,320,000 7,680,000 1,728,000 3,240,000 5,760,000arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning