Operations Management
Operations Management
13th Edition
ISBN: 9781259667473
Author: William J Stevenson
Publisher: McGraw-Hill Education
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 6, Problem 4P

A producer of inkjet printer is planning to add a new line of printers, and you have been asked to balance the process, given the following task time and precedence relationship. Assume that cycle time is to be the minimum possible.

Chapter 6, Problem 4P, A producer of inkjet printer is planning to add a new line of printers, and you have been asked to

a. Do each of the following:

(1) Draw the precedence diagram.

(2) Assign tasks to stations in order of most following tasks. Tiebreaker, greatest positional weight.

(3) Determine the percentage of idle time.

(4) Compute the late of output in printers per day that could be expected for that line assuming a 420-minute working day.

b. Answer these questions:

(1) What it the shortest cycle tone that will permit use of only two workstations? Is this cycle time feasible? Identify the tasks you would assign to each station.

(2) Determine the percentage of idle time that would results if two stations were used.

(3) What is the daily output under this arrangement?

(4) Determine the output rate that would be associated with the maximum cycle time.

a) 1

Expert Solution
Check Mark
Summary Introduction

To draw: The precedence diagram.

Answer to Problem 4P

Answer: Precedence diagram:

Operations Management, Chapter 6, Problem 4P , additional homework tip  1

Explanation of Solution

Given information:

Task Length (minutes) Immediate (Predecessor)
a 0.2 Nil
b 0.4 a
c 0.3 Nil
d 1.3 b, c
e 0.1 Nil
f 0.8 e
g 0.3 d, f
h 1.2 g

Precedence diagram:

Operations Management, Chapter 6, Problem 4P , additional homework tip  2

The precedence diagram is drawn circles and arrows. The tasks are represented in circles and weights for each task are represented outside the circle. The arrows are represented to show which task is preceding the other task and so on.

2)

Expert Solution
Check Mark
Summary Introduction

To assign: Tasks to workstations in the order of most following tasks.

Explanation of Solution

Given information:

Task Length (minutes) Immediate (Predecessor)
a 0.2 Nil
b 0.4 a
c 0.3 Nil
d 1.3 b, c
e 0.1 Nil
f 0.8 e
g 0.3 d, f
h 1.2 g

The positional weight of a task is the sum of the task times of the task itself and all of the following tasks.

Task Following tasks Number of following tasks Calculation of positional weight Positional weight
a b, d, g, h 4 0.2 + 0.4 + 1.3 + 0.3 + 1.2 3.4
b d, g, h 3 0.4 + 1.3 + 0.3 + 1.2 3.2
c d, g, h 3 0.3 + 1.3 + 0.3 + 1.2 3.1
d g, h 2 1.3 + 0.3 + 1.2 2.8
e f, g, h 3 0.1 + 0.8 + 0.3 + 1.2 2.4
f g, h 2 0.8 + 0.3 + 1.2 2.3
g h 1 0.3 + 1.2 1.5
h Nil 0 1.2 1.2

Calculation of cycle time:

The cycle is said to be the minimum time possible.

Minimum cycle time=Length of longest task .

Therefore, the cycle time is 1.3 minutes / unit.

Assigning tasks to workstations:

Workstation number Eligible task Assigned task Task time Unassigned cycle time Reason
1.3
1 a, c, e a 0.2 1.1 Task 'a' has more number of following tasks
b, c , e b 0.4 0.7 Task 'b' has greatest positional weight
c, e c 0.3 0.4 Task 'c' has greatest positional weight
d, e e 0.1 0.3 Task 'e' has greatest positional weight
d, f None 0.3 (Idle time) The task time is greater than the unassigned cycle time.
1.3
2 d, f d 1.3 0 Task 'd' has greatest positional weight
1.3
3 f f 0.8 0.5 Task 'f' is the only eligible task available
g g 0.3 0.2 Task 'g' is the only eligible task available
h None 0.2 (Idle time) The task time is greater than the unassigned cycle time.
1.3
4 h h 1.2 0.1 Task 'h' is the only task remaining
0.1 (Idle time) All tasks completed

Overview of tasks assignment:

Workstation Assigned tasks Total cycle time used Idle time
1 a, b, c, e 1 0.3
2 d 1.3 0
3 f, g 1.1 0.2
4 h 1.2 0.1

3)

Expert Solution
Check Mark
Summary Introduction

To determine: The percentage of idle time.

Answer to Problem 4P

The percentage of idle time is 11.54%.

Explanation of Solution

Formula to calculate percentage of idle time:

Idle time=Total idle timeNumber of workstations×Cycle time×100

Calculation of percentage of idle time:

Idle time=0.3+0.2+0.14×1.3×100=0.65.2×100=0.1154×100=11.54%

The percentage of idle time is 11.54%.

4)

Expert Solution
Check Mark
Summary Introduction

To determine: The rate of output printers per day.

Answer to Problem 4P

The rate of output printers per day is 323.08 printers / day.

Explanation of Solution

Given information:

Operating time per day = 420 minutes

Formula to calculate output printers per day:

Output=Operating time per dayCycle time

Calculation of output printers per day:

Output=4201.3=323.0769=323.08 printers / day

The rate of output printers per day is 323.08 printers / day.

b) 1

Expert Solution
Check Mark
Summary Introduction

To determine: The shortest cycle time that will permit the use of only 2 workstations and to check if it is feasible.

Explanation of Solution

Given information:

Task Length (minutes) Immediate (Predecessor)
a 0.2 Nil
b 0.4 a
c 0.3 Nil
d 1.3 b, c
e 0.1 Nil
f 0.8 e
g 0.3 d, f
h 1.2 g

Calculation of shortest cycle time:

The shortest cycle time is calculated by summing all the task times and dividing the resultant value by 2 workstations.

Shortest cycle time=Sum of all task times2 Workstations=0.2+0.4+0.3+1.3+0.1+0.8+0.3+1.22 Workstations=4.62=2.3 minutes / workstation

The obtained shortest cycle time is feasible based on the task times. Every task time is either equal to or less than 2.3 minutes. The feasibility is checked by assigning the tasks to the 2 workstations.

Assigning tasks to workstations:

Workstation number Eligible task Assigned task Task time Unassigned cycle time Reason
2.3
1 a, c, e a 0.2 2.1 Task 'a' has more number of following tasks
b, c , e b 0.4 1.7 Task 'b' has greatest positional weight
c, e c 0.3 1.4 Task 'c' has greatest positional weight
d, e e 0.1 1.3 Task 'e' has more number of following tasks
d, f d 1.3 0 Task 'd' has greatest positional weight
2.3
2 f f 0.8 1.5 Task 'f' is the only eligible task available
g g 0.3 1.2 Task 'g' is the only eligible task available
h h 1.2 1.2 Task 'h' is the only task available

Overview of tasks assignment:

Workstation Assigned tasks Total cycle time used Idle time
1 a, b, c, e, d 2.3 0
2 f, g, h 2.3 0

The shortest cycle time of 2.3 minutes is feasible.

2)

Expert Solution
Check Mark
Summary Introduction

To determine: The percentage of idle time.

Answer to Problem 4P

The percentage of idle time is 0.00%.

Explanation of Solution

Formula to calculate percentage of idle time:

Idle time=Total idle timeNumber of workstations×Cycle time×100

Calculation of percentage of idle time:

Idle time=0.0+0.02×2.3×100=0.04.6×100=0.00%

The percentage of idle time is 0.00%.

3)

Expert Solution
Check Mark
Summary Introduction

To determine: The daily output under this arrangement.

Answer to Problem 4P

The daily output under this arrangement is 182.61 units / day.

Explanation of Solution

Given information:

Operating time per day = 420 minutes

Formula to calculate output under this arrangement:

Output=Operating time per dayCycle time

Calculation of output under this arrangement:

Output=4202.3=182.608=182.61 units / day

The rate of output under this arrangement is 182.61 units / day.

4)

Expert Solution
Check Mark
Summary Introduction

To determine: The output rate associated with cycle time.

Answer to Problem 4P

The output rate associated with cycle time is 91.30 units / day.

Explanation of Solution

Given information:

Operating time per day = 420 minutes

Formula to calculate output under this arrangement:

Output=Operating time per dayMaximum cycle time

Calculation of output under this arrangement:

The maximum cycle time is the sum of all task times.

The sum of all task times is:

Sum of all task times=0.2+0.4+0.3+1.3+0.1+0.8+0.3+1.2=4.6 minutes

Output=4204.6=91.304=91.30 units / day

The rate of output under this arrangement is 91.30 units / day.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
A local toy manufacturer is using a production line that runs hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 201 01, 2.13, 2.0, 2.61 2.71. and 2.95 minutes for A, BC, D , and G, respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task A does not need any predecessors; task B requires task A to be completed. To start task and task each require task B to be completed. Task must be completed prior to stating task E. Task F needs both task Dand task E to be completed. Finally, task G can start only once task Fis completed . What should be the calculated cycle time in minutes?
Given the following information, assign tasks to work stations using the most followers rule. Assume the cycle time is 60 seconds. Submit for each workstation (1,2,3 etc.), the tasks assigned in order of assignment, the idle time for each work station and the total idle time. (It will help for you to make the diagram but you are not required to submit the diagram) Immediate Task Task Time (seconds) Predecessor 35 50 A. 20 10 25 F\ C.E 40 Edit Format Table Paragraph V BIUA 12pt v Immediate Predecessor Task Time (seconds) Task
Find the value of X in the following Flow Shop data consisting of 5 jobs which are to be processed on two machines M1 & M2 in that order. M2 Jobs A 7 B 5 C D E M1 5 2 1 4 13 3 6 3 For the sequence using Johnson's Rule, the Average Flow Time X

Chapter 6 Solutions

Operations Management

Ch. 6.5 - Prob. 1.1RQCh. 6.5 - Prob. 1.2RQCh. 6 - Explain the importance of process selection in...Ch. 6 - Briefly describe the five process types, and...Ch. 6 - Prob. 3DRQCh. 6 - Briefly describe computer-assisted approaches to...Ch. 6 - What is a flexible manufacturing system, and under...Ch. 6 - Prob. 6DRQCh. 6 - Why might the choice of equipment that provides...Ch. 6 - Prob. 8DRQCh. 6 - Prob. 9DRQCh. 6 - Briefly describe the two main layout types.Ch. 6 - Prob. 11DRQCh. 6 - Prob. 12DRQCh. 6 - What is the goal of Line balancing? What happens...Ch. 6 - Why are routing and scheduling continual problems...Ch. 6 - Prob. 15DRQCh. 6 - Prob. 16DRQCh. 6 - The City Transportation Planning Committee must...Ch. 6 - Identify the fixed-path and variable-path...Ch. 6 - Prob. 19DRQCh. 6 - Prob. 20DRQCh. 6 - Prob. 21DRQCh. 6 - Prob. 22DRQCh. 6 - What is cellular manufacturing? What are its main...Ch. 6 - Prob. 24DRQCh. 6 - Prob. 25DRQCh. 6 - Prob. 1TSCh. 6 - What trade-offs are involved when deciding how...Ch. 6 - Who needs to be involved in process selection?Ch. 6 - Prob. 4TSCh. 6 - Prob. 5TSCh. 6 - Prob. 1CTECh. 6 - Prob. 2CTECh. 6 - What are the risks of automating a production...Ch. 6 - Consider an assembly line such as the burrito...Ch. 6 - Prob. 1PCh. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A producer of inkjet printer is planning to add a...Ch. 6 - As part of a major plant renovation project, the...Ch. 6 - Twelve tasks, with times and precedence...Ch. 6 - For the given set of tasks, do the following: a....Ch. 6 - A shop works a 400-minute day. The manager of the...Ch. 6 - Arrange six departments into a 2 3 grid so that...Ch. 6 - Using the information given in the preceding...Ch. 6 - Using the information in the following grid,...Ch. 6 - Arrange the eight departments shown in the...Ch. 6 - Arrange the departments so they satisfy the...Ch. 6 - a. Determine the placement of departments fix a...Ch. 6 - Prob. 15PCh. 6 - Develop a process layout that will minimize the...Ch. 6 - Prob. 17PCh. 6 - Rebalance the assembly line in Problem 7. This...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY