Question

There are 50 persons employed in harvesting rice. They will be harvesting 2-hectare rice farm. If they started harvesting 8 o’clock in the morning, what time would they finish the harvesting operation? (Assuming 60 persons-hr/ha).

 

A. 2:30

B. 2:40 A.M

C. 10:24 A.M

D. 9:42 A.M

Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,