Practical Operations Management
Practical Operations Management
2nd Edition
ISBN: 9781939297136
Author: Simpson
Publisher: HERCHER PUBLISHING,INCORPORATED
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 11, Problem 28P

a

Summary Introduction

Interpretation: Ending inventory at the end of month 4 is to be calculated.

Concept Introduction: Holding cost or inventory cost is the cost of warehousing in which unsold goods are kept. It includes transportation, warehousing, insurance etc.

a

Expert Solution
Check Mark

Explanation of Solution

Demand of the product for 5 months is given as 200,50,200,200 and 150 respectively. Beginning inventory is 50 units and the company planned to produce 150 units per month for 5 months.

Calculation of inventories for next 5 months:

    Month12345
    Demand20050200200150
    Production150150150150150
    Inventory on hand (50)01005000

The demand for the product is given and it is stated that units are planned for production for months. The beginning inventory is 50 units.

Calculation of ending inventory for month 1:

Ending inventory is calculated by adding beginning inventory and production. Then, subtract the attained value with demand of the product.

  Endinginventory=Beginninginventory+Production-Demand

  Endinginventory=50units+150units-200units

  Endinginventory=0units

Hence, the ending inventory for the product is 0 units.

Hence, the same continues for all the months.

Calculation of ending inventory of month 4:

Ending inventory is calculated by adding beginning inventory and production. Then, subtract the attained value with the demand of the product.

  Endinginventory=Beginninginventory+Production-Demand

  Endinginventory=50units+150units-200units

  Endinginventory=0units

Hence, the ending inventory for the product is 0 units.

b

Summary Introduction

Interpretation: Average inventory during the month of 2 is to be calculated.

Concept Introduction: Holding cost or inventory cost is the cost of warehousing in which unsold goods are kept. It includes transportation, warehousing, insurance etc.

b

Expert Solution
Check Mark

Explanation of Solution

Calculation of average inventory during month 2:

Average inventory is calculated by taking the average of beginning and ending inventory of the certain period.

  Averageinventory=Beginninginventory+Endinginventory2

  Averageinventory=0+1002

  Averageinventory=50units

Hence, the average inventory for month 2 is 50 units.

c

Summary Introduction

Interpretation: Total inventory holding cost is to be calculated.

Concept Introduction: Holding cost or inventory cost is the cost of warehousing in which unsold goods are kept. It includes transportation, warehousing, insurance etc.

c

Expert Solution
Check Mark

Explanation of Solution

Calculation of inventory holding cost:

It is given that the inventory holding cost per units is $0.50. Total inventory holding cost is calculated by multiplying the holding cost per unit with the sum of stock on hand over 5 months.

  Inventoryholdingcost=Sumofinventoryonhand×Holdingcostperunit=(0+100+50+0+0)×$0.50=$75

Hence, the total inventory holding cost is $75.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Capacity planning requires a demand forecast for an extended period of time into the future. What concerns would you have regarding an extended forecast as a capacity planner?
For the Toy Car table above, what are the Planned Order Receipts in the week of 8/31? For the Toy Car table above, what are the Planned Order Releases in the week of 9/21? For the Wheel Assembly table above, what are the Gross Requirements in the week of 9/7? For the Wheel Assembly table above, what is the Projected On-Hand Inventory in the week of 8/31? For the Wheel Assembly table above, what are the Net Requirements in the week of 8/24? For the Axle table above, what are the Gross Requirements in the week of 9/7? For the Axle table above, what are the Gross Requirements in the week of 9/14? For the Axle table above, what are the Planned Order Releases in the week of 8/17?
LMNO Gaskets has formulated a production plan for a product to meet demand over the upcoming four quarters. Demand in each of the four quarters and production, overtime, and subcontracting capacities are reported in the table below, in addition to the feasible production plan. The relevant costs are: • Regular time production cost is $10/unit. Overtime production cost is $14/unit. Subcontracting cost is $18/unit Inventory is held at a cost of $1/unit/quarter. • Units may be backordered at a cost of $4/unit/quarter. Production Resource Regular Time Q1 Overtime Q1 Subcontract Q1 Regular Time Q2 Overtime Q2 Subcontract Q2 Regular Time Q3 Overtime Q3 Subcontract Q3 Demand in Quarter Demand in Quarter Q2 0 20 0 550 Q1 550 230 0 0 0 0 40 40 0 860 250 470 0 40 0 1330 What is the inventory cost for the year? What is the backorder cost for the year? What is the total cost for the year? Q3 0 0 0 0 0 30 510 160 0 700 What is the total overtime production cost for the year? Capacity 550 250 500…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY