Interpretation: Number of workers to be hired and duration to hire.
Concept Introduction: Inventory management is the process of managing the company’s stock so that there are no stock-outs. It includes ordering, storing, and managing the stock.
a
Explanation of Solution
Required unit of production = 2,000,000
Number of workers employed = 500
Time required to assemble one unit = 3 minutes
Capacity needed to produce 2000000 units, which is planned.
Since 500 workers are presently available, Number of workers to be hired is 125.
Month | Aug | Sept | Oct | Nov | Dec |
Demand | 1,000,000 | 1,000,000 | 2,000,000 | 4,000,000 | 1,000,000 |
Production plan | 2,000,000 | 2,000,000 | 2,000,000 | 2,000,000 | 2,000,000 |
Beginning inventory | 0 | 1,000,000 | 2,000,000 | 2,000,000 | 0 |
Ending inventory | 1,000,000 | 2,000,000 | 2,000,000 | 0 | 1,000,000 |
Average inventory | 500,000 | 1,500,000 | 2,000,000 | 1,000,000 | 500,000 |
b
Interpretation: Quantity of inventory at the end of October.
Concept Introduction: Materials Requirement Planning is a process in which planning is made for the requirement of raw material required for the manufacturing of the finished product.
b
Explanation of Solution
The given
Month | Aug | Sept | Oct | Nov | Dec |
Demand | 1,000,000 | 1,000,000 | 2,000,000 | 4,000,000 | 1,000,000 |
Production plan | 2,000,000 | 2,000,000 | 2,000,000 | 2,000,000 | 2,000,000 |
Beginning inventory | 0 | 1,000,000 | 2,000,000 | 2,000,000 | 0 |
Ending inventory | 1,000,000 | 2,000,000 | 2,000,000 | 0 | 1,000,000 |
Average inventory | 500,000 | 1,500,000 | 2,000,000 | 1,000,000 | 500,000 |
At the end of October, 2 million inventory will be held.
c
Interpretation: Average inventory level of each month.
Concept Introduction: Materials Requirement Planning is a process in which planning is made for the requirement of raw material required for the manufacturing of the finished product.
c
Explanation of Solution
Average inventory for august month:
Average inventory for September month:
Average inventory for October month:
Average inventory for November month:
Average inventory for December month:
Note: M stands for millions.
Want to see more full solutions like this?
Chapter 11 Solutions
Practical Operations Management
- Tots Toys makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. Please note that each tricycle requires two rear wheels, the front wheel is included in the front wheel-pedal assembly. The company has orders for 15,000 of these tricycles. Current schedules yield the following information: component plastic time space cost to manufacture cost to purchase front 2 11 2 7 11 seat/frame 3 7 2 6 10 rear 0.5 2.5 0.2 2 5 available 60000 180000 35000 The company obviously does not have the resources available to manufacture everything needed for the completion of 15,000 tricycles so has gathered purchase information for each component. Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 15,000 fully completed tricycles at the minimum cost. (state the objective function, decision…arrow_forwardTots Toys makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. Please note that each tricycle requires two rear wheels, the front wheel is included in the front wheel-pedal assembly. The company has orders for 15,000 of these tricycles. Current schedules yield the following information: component plastic time space cost to manufacture cost to purchase front 2 11 2 7 11 seat/frame 3 7 2 6 10 rear 0.5 2.5 0.2 2 5 available 60000 180000 35000 Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 15,000 fully completed tricycles at the minimum cost. Use Excel's Solver to obtain the optimal solution. How many of each component should be manufactured vs. purchased? What is the overall cost? What are the binding constraints? Upload a screenshot of the spreadsheet that you used…arrow_forwardYou have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 300 attendees. Assume that there is no inventory on hand of any of the items. Explode the bill of material. (Subscripts indicate the number of units required.) K(1) L(5) M(3) J Determine the number of units of each item required. Item K: Item L: Item M:arrow_forward
- In production plan 3, if the production requirement in June is 2000 and the actual production is 500, how many units need to be subcontracted in June?arrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 2 housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 1 shaft. There is no inventory on hand. A. Design a product structure noting the quantities for each item and show the low-level coding. B. Determine the gross quantities needed of each item if you are to assemble 50 brackets. C. Compute the net quantities if there are 25 of the base and 100 of the clamp in stock.arrow_forwardYou have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You forecast 250 attendees. Assume that there is no inventory on hand of any of the items. Explode the bill of material. (Subscripts indicate the number of units required.) J K(1) L(3) M4) ..... Determine the number of units of each item required. Item K: units (enter your response as a whole number). Item L: units (enter your response as a whole number). Item M: units (enter your response as a whole number).arrow_forward
- WSS company makes weatherproof surveillance systems for parking lots. Demand estimates for the next four quarters are 25, 9, 13, and 17 units. Prepare an aggregate plan that uses inventory, regular time and overtime and back orders. Subcontracting is not allowed. Regular time capacity is 15 units for quarters 1 and 2, 18 units for quarters 3 and 4. Overtime capacity is 3 units per quarter. Regular time cost is $2000 per unit, while overtime cost is $3000 per unit. Back order cost is $300 per unit per quarter; inventory holding cost is $100 per unit per quarter. Beginning inventory is zero. Questions At the end of quarter 3, what is the ending inventory of finished systems? Answer: No ending Inventory =0 What is the total cost? 15*2000 + 6*2300 +4*2600 + 9*2000 + 13*2000 + 17*2000 =$132, 200 What is the average cost per unit? Answer 132200 / 64 = $2,066.arrow_forwardHeather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Subscripts indicate quantity required for each parent. Assume lot-for-lot ordering. b. Choose correct time phased-structures c. Develop a net material requirements plan for F (enter your responses as whole numbers).arrow_forwardDescribe a production environment in which MRP wouldbe useful. Describe a production environment in whichMRP would not be useful.arrow_forward
- An assembly plant for the Blood Pressure RX, a portable blood pressure device, has 400 minutes available daily in the plant for the device, and the average demand is 80 units per day. Final assembly requires 6 separate tasks. Information concerning these tasks is given in the following table. Task Performance Time (minutes) Task Must Follow Task Listed Below A 4 - B 1 - C 1 A, B D 3 C E 4 D F 2 E b) Given the demand, what is the cycle time for this operation? The cycle time for this operation is enter your response here minutes/unit (enter your response as a whole number). c) What is the theoretical minimum number of workstations? The theoretical minimum number of workstations is enter your response here stations (enter your response as a whole number and, if your unrounded answer includes decimal values,…arrow_forwardWhat are the net requirements of each item in the MPS? Item Net Requirements X A B C D E F Garrow_forwardAs the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 4 clamps. The base is assembled from 1 clamp and 1 housing. Each clamp has 1 handle and 2 castings. Each housing has 1 bearing and 2 shafts. There is no inventory on hand. Part 2 a) Design a product structure noting the quantities for each item and show the low-level coding. Match each number in the structure below with the corresponding item. Number Item I Spring Subscript left parenthesis 2 right parenthesisSpring(2) II Housing Subscript left parenthesis 1 right parenthesisHousing(1) III Casting Subscript left parenthesis 2 right parenthesisCasting(2) IV Shaft Subscript left parenthesis 2 right parenthesisShaft(2) Bracket Base(1) Clamp(1) Handle(1) Clamp(4) Bearing(1) Handle(1) Casting(2) IIIIIIIV Part 3 b) Determine the…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,