Question
Chapter 4, Problem 3.6GAP
To determine
Concept introduction:
Activity Based Costing (ABC):
ABC costing method is generally used to allocate the
To calculate:
The Production cost per unit for each product using the ABC system
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Chrzan, Incorporated, manufactures and sells two products: Product EO and Product NO. Data concerning the expected production of each product and the expected total direct labor-hours (DLHs) required to produce that output appear below:
Product E0
Product Ne
Total direct labor-hours
Activity Cost Pools
Labor-related
Production orders
Order size
The company is considering adopting an activity-based costing system with the following activity cost pools, activity measures, and expected activity:
Estimated
Overhead
Cost
Multiple Choice
$33.94 per MH
$54.20 per MH
Direct
Expected Labor-Hours
Production
Per Unit
10.1
410
1,550
9.1
$51.98 per MH
$21.40 per MH
Activity
Measures
DLHS
orders
MHs
Total
Direct
Labor-
Hours
$ 301,890
61,087
585,366
$948,343
The activity rate for the Order Size activity cost pool under activity-based costing is closest to:
4,141
14, 105
18,246
Product E
4,141
850
5,550
Expected Activity
Product NO
14, 105
950
5,250
Total
18,246
1,800
10,800
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows:
Activity Cost Pools
Total Cost of Pool
Cost Driver
Estimated Cost Driver
Machining
$
183,300
Number of machine hours
61,100
Designing costs
47,725
Number of design hours
5,750
Setup costs
71,150
Number of batches
500
Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows:
Product A
Product B
Product C
Number of machine hours
21,000
31,000
9,100
Number of design hours
2,300
1,350
2,100
Number of batches
60
180
260
How would you find the total overhead?
Requ
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows:
Activity Cost Pools
Machining
Designing costs
Setup costs
Number of machine hours
Number of design hours
Number of batches
Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows:
Product A Product B Product C
26,000
2,800
40
Total Cost
of Pool
Cost Driver
$250,600 Number of machine hours
61,600 Number of design hours
66,402 Number of batches
Product A
Product B
Product C
Total Overhead
Assigned
36,000
1,600
170
Estimated
Cost Driver
71,600
7,000
465
9,600
2,600
255
Required:
1. Using activity proportions, determine the amount of overhead assigned to each product. (Do not round your intermediate
calculations. Round your final answers to nearest whole number.)
Chapter 4 Solutions
Managerial Accounting
Ch. 4 - What is the difference between a volume-based cost...Ch. 4 - Explain the statement that traditional costing...Ch. 4 - Prob. 3QCh. 4 - How does activity-based costing differ from...Ch. 4 - What types of business might use activity-based...Ch. 4 - Prob. 6QCh. 4 - Prob. 7QCh. 4 - Prob. 8QCh. 4 - Why must costs be classified into different...Ch. 4 - Prob. 10Q
Ch. 4 - Prob. 11QCh. 4 - Explain the difference between the activity-rate...Ch. 4 - Define activity-based management and explain how...Ch. 4 - Prob. 14QCh. 4 - Prob. 15QCh. 4 - What is non-value-added activity. Considering the...Ch. 4 - Prob. 17QCh. 4 - Prob. 18QCh. 4 - Prob. 19QCh. 4 - Prob. 20QCh. 4 - Prob. 1MCCh. 4 - Both traditional and ABC cost systems focus on...Ch. 4 - Prob. 3MCCh. 4 - Number of setups is an example of a a. Unit-level...Ch. 4 - Prob. 5MCCh. 4 - Prob. 6MCCh. 4 - Prob. 7MCCh. 4 - Prob. 8MCCh. 4 - Prob. 9MCCh. 4 - Prob. 10MCCh. 4 - Prob. 1MECh. 4 - Prob. 2MECh. 4 - Prob. 3MECh. 4 - Identifying terms in ABC and ABM Use the following...Ch. 4 - Prob. 5MECh. 4 - Prob. 6MECh. 4 - Assigning Costs Using Activity Proportions Refer...Ch. 4 - Calculating Activity Rates for ABC System Lakeside...Ch. 4 - Prob. 9MECh. 4 - Prob. 10MECh. 4 - Prob. 11MECh. 4 - Prob. 12MECh. 4 - Classifying Activities According to Level,...Ch. 4 - Prob. 2ECh. 4 - Prob. 3ECh. 4 - Assigning Costs Using Activity Rates Refer to the...Ch. 4 - Prob. 5ECh. 4 - Prob. 6ECh. 4 - Prob. 7ECh. 4 - Prob. 8ECh. 4 - Prob. 9ECh. 4 - Prob. 10ECh. 4 - Comparing Traditional Costing Systems and...Ch. 4 - Prob. 12ECh. 4 - Prob. 13ECh. 4 - Prob. 14ECh. 4 - Prob. 15ECh. 4 - Identifying Value-Added and Non-Value-Added...Ch. 4 - Prob. 17ECh. 4 - Prob. 18ECh. 4 - Calculating Target Cost Majesty Company uses...Ch. 4 - Assigning Costs using Traditional System, ABC...Ch. 4 - Assigning Costs using Traditional System, ABC...Ch. 4 - Prob. 1.3GAPCh. 4 - Prob. 1.4GAPCh. 4 - Prob. 1.5GAPCh. 4 - Prob. 2.1GAPCh. 4 - Prob. 2.2GAPCh. 4 - Prob. 2.3GAPCh. 4 - Prob. 2.4GAPCh. 4 - Prob. 2.5GAPCh. 4 - Prob. 3.1GAPCh. 4 - Prob. 3.2GAPCh. 4 - Prob. 3.3GAPCh. 4 - Prob. 3.4GAPCh. 4 - Prob. 3.5GAPCh. 4 - Prob. 3.6GAPCh. 4 - Prob. 3.7GAPCh. 4 - Prob. 3.8GAPCh. 4 - Prob. 4.1GAPCh. 4 - Describing the Impact of ABM and TQM on a Company...Ch. 4 - Prob. 4.3GAPCh. 4 - Prob. 4.4GAPCh. 4 - Describing the Impact of ABM and TQM on a Company...Ch. 4 - Prob. 4.6GAPCh. 4 - Prob. 4.7GAPCh. 4 - Prob. 4.8GAPCh. 4 - Prob. 5.2GAPCh. 4 - Prob. 1.1GBPCh. 4 - Prob. 1.2GBPCh. 4 - Prob. 1.3GBPCh. 4 - Prob. 1.4GBPCh. 4 - Prob. 1.5GBPCh. 4 - Prob. 2.1GBPCh. 4 - Prob. 2.2GBPCh. 4 - Prob. 2.3GBPCh. 4 - Prob. 2.4GBPCh. 4 - Prob. 2.5GBPCh. 4 - Prob. 3.1GBPCh. 4 - Selecting Cost Drivers, Assigning Costs using...Ch. 4 - Prob. 3.3GBPCh. 4 - Prob. 3.4GBPCh. 4 - Prob. 3.5GBPCh. 4 - Prob. 3.6GBPCh. 4 - Prob. 3.7GBPCh. 4 - Prob. 3.8GBPCh. 4 - Prob. 4.1GBPCh. 4 - Prob. 4.2GBPCh. 4 - Prob. 4.3GBPCh. 4 - Prob. 4.4GBPCh. 4 - Selecting Cost Drivers, Assigning Costs Using...Ch. 4 - Prob. 4.6GBPCh. 4 - Prob. 4.7GBPCh. 4 - Prob. 4.8GBPCh. 4 - Defining Concepts of Target Costing, Just-in-Time,...Ch. 4 - Defining Concepts of Target Costing, Just-in-Time,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Bumblebee Mobiles manufactures a line of cell phones. The management has identified the following overhead costs and related cost drivers for the coming year. The following were incurred in manufacturing two of their cell phones, Bubble and Burst, during the first quarter. REQUIREMENT Review the worksheet called ABC that follows these requirements. You have been asked to determine the cost of each product using an activity-based cost system. Note that the problem information is already entered into the Data Section of the ABC worksheet.arrow_forwardElectan Company produces two types of printers. The company uses ABC, and all activity drivers are duration drivers. Electan Company is considering using DBC and has gathered the following data to help with its decision. A. Activities with duration drivers: B. Activities with consumption ratios and costs: C. Products with cycle time and practical capacity: Required: 1. Using cycle time and practical capacity for each product, calculate the total time for all primary activities. Comment on the relationship to ABC. 2. Calculate the overhead rate that DBC uses to assign costs. Comment on the relationship to a unit-based plantwide overhead rate. 3. Use the overhead rate calculated in Requirement 2 to calculate (a) the overhead cost per unit for each product, and (b) the total overhead assigned to each product. How does this compare to the ABC assignments shown in Part B of the Information set? 4. What if the units actually produced were 10,000 for Printer A and 18,000 for Printer B. Using DBC, calculate the cost of unused capacity.arrow_forwardMedical Tape makes two products: Generic and Label. It estimates it will produce 423,694 units of Generic and 652,200 of Label, and the overhead for each of its cost pools is as follows: It has also estimated the activities for each cost driver as follows: How much is the overhead allocated to each unit of Generic and Label?arrow_forward
- Evans, Inc., has a unit-based costing system. Evanss Miami plant produces 10 different electronic products. The demand for each product is about the same. Although they differ in complexity, each product uses about the same labor time and materials. The plant has used direct labor hours for years to assign overhead to products. To help design engineers understand the assumed cost relationships, the Cost Accounting Department developed the following cost equation. (The equation describes the relationship between total manufacturing costs and direct labor hours; the equation is supported by a coefficient of determination of 60 percent.) Y=5,000,000+30X,whereX=directlaborhours The variable rate of 30 is broken down as follows: Because of competitive pressures, product engineering was given the charge to redesign products to reduce the total cost of manufacturing. Using the above cost relationships, product engineering adopted the strategy of redesigning to reduce direct labor content. As each design was completed, an engineering change order was cut, triggering a series of events such as design approval, vendor selection, bill of materials update, redrawing of schematic, test runs, changes in setup procedures, development of new inspection procedures, and so on. After one year of design changes, the normal volume of direct labor was reduced from 250,000 hours to 200,000 hours, with the same number of products being produced. Although each product differs in its labor content, the redesign efforts reduced the labor content for all products. On average, the labor content per unit of product dropped from 1.25 hours per unit to one hour per unit. Fixed overhead, however, increased from 5,000,000 to 6,600,000 per year. Suppose that a consultant was hired to explain the increase in fixed overhead costs. The consultants study revealed that the 30 per hour rate captured the unit-level variable costs; however, the cost behavior of other activities was quite different. For example, setting up equipment is a step-fixed cost, where each step is 2,000 setup hours, costing 90,000. The study also revealed that the cost of receiving goods is a function of the number of different components. This activity has a variable cost of 2,000 per component type and a fixed cost that follows a step-cost pattern. The step is defined by 20 components with a cost of 50,000 per step. Assume also that the consultant indicated that the design adopted by the engineers increased the demand for setups from 20,000 setup hours to 40,000 setup hours and the number of different components from 100 to 250. The demand for other non-unit-level activities remained unchanged. The consultant also recommended that management take a look at a rejected design for its products. This rejected design increased direct labor content from 250,000 hours to 260,000 hours, decreased the demand for setups from 20,000 hours to 10,000 hours, and decreased the demand for purchasing from 100 component types to 75 component types, while the demand for all other activities remained unchanged. Required: 1. Using normal volume, compute the manufacturing cost per labor hour before the year of design changes. What is the cost per unit of an average product? 2. Using normal volume after the one year of design changes, compute the manufacturing cost per hour. What is the cost per unit of an average product? 3. Before considering the consultants study, what do you think is the most likely explanation for the failure of the design changes to reduce manufacturing costs? Now use the information from the consultants study to explain the increase in the average cost per unit of product. What changes would you suggest to improve Evanss efforts to reduce costs? 4. Explain why the consultant recommended a second look at a rejected design. Provide computational support. What does this tell you about the strategic importance of cost management?arrow_forwardSabby Industries has three activity cost pools and two products. It expects to produce 2,900 units of Product S209 and 1.200 of Product NZ16. Having identified its activity cost pools and the cost drivers for each pool, Sabby accumulated the following data relative to those activity cost pools and cost drivers. Activity Cost Pool Machine set-ups Assembling Inspection (a) Cost Driver Assembling Set-ups Machine hours Calculate the overhead rates. Inspection Inspections Machine set-ups $ $ Estimated Overhead $78,660 323,000 6,400 Estimated Use of Cost Drivers per set-up 190 per inspection 17,000 100 per machine hour 5709 NZ16 130 10,100 60 60 6,900 40arrow_forwardDurban Metal Products makes specialty metal parts and uses activity-based costing for internal decision-making purposes. The company has four activity cost pools as follows: Activity Cost Pool Order size Customer orders Product testing Selling Activity Measure Number of direct labor-hours Number of customer orders Number of testing hours Number of sales calls The company's owner wants to know the cost of a customer order requiring 200 direct labor-hours, 11 hours of product testing, and 5 sales calls. Required: What is the total overhead cost assigned to this order? Activity Cost Pool Order size Customer orders Product testing Selling Total overhead cost Activity Rate $ 17.90 per direct labor-hour $ 351.00 per customer order $ 77.00 per testing hour $ 1,496.00 per sales call ABC Costarrow_forward
- Pharoah Industries has three activity cost pools and two products. It expects to produce 2,800 units of Product SZ09 and 1,300 of Product NZ16. Having identified its activity cost pools and the cost drivers for each pool, Pharoah accumulated the following data relative to those activity cost pools and cost drivers. Activity Cost Pool Machine set-ups Assembling Inspection Machine set-ups Calculate the overhead rates. Assembling Inspection SZ09 $ Cost Driver Set-ups Machine hours NZ16 $ Inspections GA LA $ LA Assign the overhead cost to the two products. ta Estimated Overhead $63,600 354,000 6,160 Estimated Use of Cost Drivers per set-up 200 17,700 per inspection 110 per machine hour SZ09 130 NZ16 60 70 10,300 7,400 50arrow_forwardFletes Corporation manufactures two products: Product O95C and Product M31N. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products O95C and M31N. Activity Cost Pool Activity Measure Total Cost Total Activity Machining Machine-hours $ 207,000 9,000 MHs Machine setups Number of setups $ 140,000 350 setups Product design Number of products $ 98,000 2 products Order size Direct labor-hours $ 340,000 10,000 DLHs Activity Measure Product O95C Product M31N Machine-hours 6,000 3,000 Number of setups 190 160 Number of products 1 1 Direct labor-hours 4,000 6,000 Using the ABC system, how much total manufacturing overhead cost would be assigned to Product O95C?arrow_forwardOrear Corporation manufactures two products: Product Z34D and Product J25M. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Z34D and J25M. Activity Cost Pool Activity Measure Total Cost Total Activity Machining Machine-hours $ 120,000 6,000 Machine-hours Machine setups Number of setups $ 90,000 150 setups Product design Number of products $ 84,000 2 products Order size Direct labor-hours $ 300,000 10,000 Direct labor-hours Activity Measure Product Z34D Product J25M Machine-hours 4,000 2,000 Number of setups 90 60 Number of products 1 1 Direct labor-hours 7,000 3,000 Using the plantwide overhead rate, the percentage of the…arrow_forward
- Hails Corporation manufactures two products: Product Q21F and Product H44W. The company uses a plantwide overhead rate based on direct labor- hours. It is considering implementing an activity-based costing (ABC) system that allocates its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Q21F and H44W. Activity Cost Pool Machining Machine setups Product design Order size Machine-hours Number of setups Number of products Direct labor-hours 26.71% 50.00% 34.18% Activity Measure O 60.89% Machine-hours Number of setups Number of products Direct labor-hours Activity Measure Total Cost Total Activity $ 195,000 13,000 MHs 90,000 150 setups $ $ 64,000 $ 280,000 Product Q21F 9,000 80 1 6,000 Using the ABC system, the percentage of the total overhead cost that is assigned to Product Q21F is closest to: 2 products 10,000 DLHs Product H44W 4,000 70 1 4,000arrow_forwardHarbour Company makes two models of electronic tablets, the Home and the Work. Basic production information follows: Direct materials cost per unit Direct labor cost per unit Sales price per unit Expected production per month Harbour has monthly overhead of $168,340, which is divided into the following activity pools: Setup costs Quality control Maintenance Total Number of setups Number of inspections Number of machine hours $86,400 54,940 27,000 $ 168,340 The company also has compiled the following information about the chosen cost drivers: Home 37 340 1,600 Required 1 Home Required 2 Required 3 $ 41 16 360 770 units Work 71 330 1,100 Home Model Work Model Total Overhead Cost Required: 1. Suppose Harbour uses a traditional costing system with machine hours as the cost driver. Determine the amount of overhead assigned to each product line. 2. Calculate the production cost per unit for each of Harbour's products under a traditional costing system. 3. Calculate Harbour's gross margin per…arrow_forwardGable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Total Cost of Pool Cost Driver Estimated Cost Driver Machining $ 250,000 Number of machine hours 84,900 Designing costs 56,000 Number of design hours 7,200 Setup costs 80,000 Number of batches 360 How do you find the activity rate?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningExcel Applications for Accounting PrinciplesAccountingISBN:9781111581565Author:Gaylord N. SmithPublisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Excel Applications for Accounting Principles
Accounting
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Cengage Learning
Cost Classifications - Managerial Accounting- Fixed Costs Variable Costs Direct & Indirect Costs; Author: Accounting Instruction, Help, & How To;https://www.youtube.com/watch?v=QQd1_gEF1yM;License: Standard Youtube License