Determine the total estimated cost at completion and estimated cost to complete for the project in Problem 14, assuming the CPI remains the same through the remainder of the job.

The ACWP at the end of the second week for the project in Problem 12 is $37,900. Determine the CPI for the project.

A project consists of three tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 3. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is scheduled to begin at the start of Week 2 and end at the end of Week 3. The budgeted cost for Task A is $22,000, for Task B is $17,000, and for Task C is $15,000. At the end of the second week, Task A is 65% complete, Task B is 95% complete, and Task C is 60% complete. What is the SPI for the project at the end of the second week?

Blurred answer
Students have asked these similar questions
The ABC company has the following estimated costs for the next year: Direct materials: $15,000 Indirect materials: $5,000 Direct labor: $55,000 Salary of production supervisor: $35,000 Rent on factory equipment: $16,000 Sales commission: $75,000 Advertising expenses: $11,000 It is estimated that 53,000 machine hours and 8,000 direct labor hours will be worked during the next year. What will be the predetermined overhead rate if company applies manufacturing overhead cost to jobs on the basis of direct labor hours. Select one: a. $14 b. $17 C. $7 d. $15 23°C uao
SPL Enterprises assigns overhead based on number of machine hours. For the upcoming year, they plan to use a total of 250,000 machine hours and 50,000 direct labor hours. Total overhead cost is expected to be $500,000. The predetermined overhead rate
The Larry plant has two categories of overhead: maintenance and inspection. Costs expected for these categories for the coming year are as follows: Maintenance - P100,000; Inspection - P150,000. The plant currently applies overhead using direct labor hours and expected capacity of 50,000 direct labor hours. The following data have been assembled for use in developing a bid for a proposed job: (refer to image) Total expected machine hours for all jobs during the year is 25,000, and the total expected number of inspections is 1,500.Using activity-based costing and the appropriate activity drivers, the total cost of the potential job would be * Nimet malerials Direcd lubor Mechine houre Number of inspections Niret labor hours P1 C00 P4.000 600 800 O a. P2,400 О Б. Р3,600 c. P7,400 O d. P7,750
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY