Intermediate Accounting (2nd Edition)
2nd Edition
ISBN: 9780134730370
Author: Elizabeth A. Gordon, Jana S. Raedy, Alexander J. Sannella
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 8, Problem 8.15E
To determine
To prepare: The
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Pharoah Construction entered into a contract to construct a bridge for a contract price of $2.95 million. Construction began in 2019 and was completed in 2021. Below are the details of the transactions related to the contract:
2019
2020
2021
Costs incurred during the year
$649,000
$836,000
$693,900
Estimated costs to complete
1,427,800
515,000
0
Calculate the revenue, expenses and gross profit to be recognized each year using the percentage-of-completion method. (Round the percentage completion to 2 decimal places, e.g. 52.75% and other answers to 0 decimal places, e.g. 1,525.)
2019
2020
2021
Revenue
$
$
$
Expenses
Gross Profit
$
$
$
On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which
The
is estimated
cost
P31,200,000.
company recognizes construction
to
Data on this project for 2022-2024 follow:
Est'd Costs
revenue over time.
Contract
Costs
Billings
10,500,000
12,500,000
14,440,000
incurred
to Complete
20,540,000
13,156,000
2022
5,460,000
9,984,000
2023
2024
15,756,000
The contract contains a penalty clause that penalizes the company a reduction
of P70,000 from the contract price for every week of delay.
contract was delayed for 8 weeks
In 2024, the
What is the gross profit for 2024?
1,164,000
1,466,400
1,724,000
1,824,000
А.
с.
в.
D.
Casio Co. recognizes construction revenue and expenses using the percentage-of-completion method. During 2020, a single long-term project was begun, which continued through
2018 Information on the project follows:
12/31 Accounts Receivable balance
Construction expenses for year
Gross Profit recognized in year
Bangs during year
The 12/31/21 CIP balance is
Select one
O $50,000
Ob 1322,000
O 1619.000
Od $106.000
O $112,000
2020
$100,000
105,000
122,000
100,000
20121
$300.000
192,000
200,000
420.000
Chapter 8 Solutions
Intermediate Accounting (2nd Edition)
Ch. 8 - What are the primary issues involved in revenue...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - Prob. 8.4QCh. 8 - Prob. 8.5QCh. 8 - How is a performance obligation defined?Ch. 8 - What are the two criteria to define a good or...Ch. 8 - Prob. 8.8QCh. 8 - What principles regarding timing and measurement...Ch. 8 - Prob. 8.10Q
Ch. 8 - What is variable consideration and what factors...Ch. 8 - Describe and contrast the two approaches used to...Ch. 8 - Prob. 8.13QCh. 8 - What factors should accountants consider to...Ch. 8 - Prob. 8.15QCh. 8 - How does a seller account for any consideration...Ch. 8 - Prob. 8.17QCh. 8 - What are the two exceptions to the general rule...Ch. 8 - What are the three criteria required to recognize...Ch. 8 - When an entity does not meet the three criteria...Ch. 8 - Prob. 8.21QCh. 8 - Prob. 8.22QCh. 8 - How does a firm estimate the degree completed...Ch. 8 - Can a firm record inventory out on consignment as...Ch. 8 - What method do agents in a transaction use to...Ch. 8 - Prob. 8.26QCh. 8 - What qualitative disclosures do the standards...Ch. 8 - All of the following are elements of a contract...Ch. 8 - Prob. 8.2MCCh. 8 - Telecom Co. enters into a two-year contract with a...Ch. 8 - The transaction price must reflect the time value...Ch. 8 - Prob. 8.5MCCh. 8 - When allocating the transaction price to separate...Ch. 8 - Which of the following indicators is not...Ch. 8 - During Yoar 1 Moriwothor Construction Company...Ch. 8 - All of the following are indicators that the...Ch. 8 - Prob. 8.10MCCh. 8 - Prob. 8.11MCCh. 8 - Identify a Contract with a Customer. Complete the...Ch. 8 - Prob. 8.2BECh. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Estimating Variable Consideration. Gear Garage...Ch. 8 - Estimating Variable Consideration. Using the...Ch. 8 - Estimating Variable Consideration. Sellet...Ch. 8 - Estimating Variable Consideration. Seliet...Ch. 8 - Prob. 8.9BECh. 8 - Allocation of Transaction Price. Martin Software...Ch. 8 - Prob. 8.11BECh. 8 - Allocation of Transaction Price. Sycamore Sidewalk...Ch. 8 - Allocation of Transaction Price. Sycamore enters...Ch. 8 - Prob. 8.14BECh. 8 - Allocation of Transaction Price. Using the...Ch. 8 - When to Recognize Revenue. For each scenario...Ch. 8 - Prob. 8.17BECh. 8 - Prob. 8.18BECh. 8 - Percentage-of-Completion Method, Journal Entries....Ch. 8 - Prob. 8.20BECh. 8 - Sales with the Right of Return. Both incorporated...Ch. 8 - Sales with the Right of Return. Using the...Ch. 8 - Sales Returns. Historically, about 5% or the...Ch. 8 - Sales on Consignment. Hanna Lighting recertify...Ch. 8 - Determining Performance Obligations. Pagit Inc, a...Ch. 8 - Prob. 8.2ECh. 8 - Estimating Variable Consideration. King Rat Pest...Ch. 8 - Prob. 8.4ECh. 8 - Prob. 8.5ECh. 8 - Prob. 8.6ECh. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Prob. 8.9ECh. 8 - Prob. 8.10ECh. 8 - Determination of When to Recognize Revenue. Far...Ch. 8 - Prob. 8.12ECh. 8 - Percentage-of-Completion Method. Gary Construction...Ch. 8 - Prob. 8.14ECh. 8 - Prob. 8.15ECh. 8 - Prob. 8.16ECh. 8 - Sales with the Right of Return. Webster Hall, Inc....Ch. 8 - Prob. 8.18ECh. 8 - Prob. 8.19ECh. 8 - Other Principal Agent Transactions, Net Revenue...Ch. 8 - Prob. 8.1PCh. 8 - Prob. 8.2PCh. 8 - Comprehensive Revenue Recognition Problem. Casale...Ch. 8 - Prob. 8.4PCh. 8 - Determining When to Recognize Revenue. Megrew...Ch. 8 - Prob. 8.6PCh. 8 - Prob. 8.7PCh. 8 - Prob. 8.8PCh. 8 - Percentage-of-Completion Method. R Wayne Computer...Ch. 8 - Prob. 8.10PCh. 8 - Prob. 8.11PCh. 8 - Sales on Consignment. Pablo Products. Ltd sells...Ch. 8 - Prob. 1JCCh. 8 - Prob. 1FSCCh. 8 - Prob. 1SSCCh. 8 - Basis for Conclusions Case 1: Control According to...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- On March 1, 2019, Elkhart enters into a new contract to build a specialized warehouse for 7 million. The promise to transfer the warehouse is determined to be a performance obligation. The contract states that if the warehouse is usable by November 30, 2019, Elkhart will receive a bonus of 600,000. For every week after November 30 that the warehouse is not usable, the bonus will decrease by 150,000. Elkhart provides the following completion schedule: Required: 1. Assume that Elkhart uses the expected value approach. What amount should Elkhart use for the transaction price? 2. Assume that Elkhart uses the most likely amount approach. What amount should Elkhart use for the transaction price? 3. Next Level What is the purpose of assessing whether a constraint on the variable consideration exists?arrow_forwardGinebraCorporation recognizes construction revenue and cost using the percentage of completion method. During 2021, a single long-term project was begun which continued through 2021. Information on the project follows: 2021. 2022 Partial billing on contract 1,000,000. 4,200,000 Accounts receivable 1,000,000 3,000,000 Construction cost 1,050,000 1,920,000 Construction in progress 1,220,000 3,640,000 What is the gross profit recognized from this long-term construction contract in year 2021 and 2022, respectively? 2021 2022 A.220,000. 2,280,000 B.170,000. 500,000 C.220,000. 1,000,000 D.170,000. 1,280,000arrow_forwardRequired information (The following information applies to the questions displayed below) In 2021 the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,016,000 $2,808,000 $2,613,000 Estimated costs to complete as of year-end 5,184,000 2,376000 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the year 1,890,000 2,500,000…arrow_forward
- Required information (The following information applies to the questions displayed below). In 2021 the Westgate construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023, Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $2,016,000 $2,800,000 $2,613,600 Estimated costs to complete as of year-end 5,184,000 2,376,000 $ 0 Billings during the year 2,180,000 2,644,000 5,176,000 Cash collections during the year 1,890,000 2,500,000 5,610,000 Westgate recognizes revenue over time according to percentage of completion Complete the information required below to…arrow_forwardOn January 1, 2021. Robredo Co. started the construction of a building with a fixed contract price of P10,000,000. The outcome of the construction project can be estimated reliably and the contractor decided to employ cost to cost method. The following data are provided by the accountant and project manager concerning the construction costs for the three years of construction: Year 12/31/2021 12/31/2022 12/31/2023 P 3740000 Costs incurred during the year Realized gross profit/(loss) during the year Percentage of completion as of the end of the year ? ? P750,000 (P250,000) (P800,000) 50% 37.5% ? What is the balance of Construction in Progress on December 31, 2023?arrow_forwardSunshine Bhd. entered a contract to build a building for its customer with the agreed total price of $3,200,000. The project is expected to last for 3 years with the total cost of $1,600,000. The following table shows the progress of the work: 31 Dec 2018 31 Dec 2019 31 Dec 2020 Completion (Market Value) $950,000 $2,600,000 $3,200,000 Cost incurred to date $400,000 $1,000,000 $1,600,000 Required: For each year, compute the recognized profit based on input method. For each year, compute the recognized profit based on output method. Please answer required 1,2arrow_forward
- Fender Construction Company receives a contract to construct a building over a period of 3 years for a price of $700,000. The contract represents a single performance obligation that will be satisfied over time. Information relating to the performance of the contract is summarized as follows: 2019 2020 2021 Construction costs incurred during the year $150,000 $242,000 $168,000 Estimated costs to complete 350,000 168,000 — Billings during the year 120,000 250,000 330,000 Collections during the year 100,000 260,000 340,000 Required: 1. Prepare journal entries for all 3 years. 2. Assume that the contract represents a single performance obligation that will be satisfied at a point in time. Prepare journal entries for all 3 years. 1. Assume the contract represents a single performance obligation that will be satisfied over time. Prepare journal entries on December 31 for all 3 years -to record costs of construction for cash -to record partial…arrow_forwardFender Construction Company receives a contract to construct a building over a period of 3 years for a price of $700,000. The contract represents a single performance obligation that will be satisfied over time. Information relating to the performance of the contract is summarized as follows: 2019 2020 2021 Construction costs incurred during the year $150,000 $242,000 $168,000 Estimated costs to complete 350,000 168,000 — Billings during the year 120,000 250,000 330,000 Collections during the year 100,000 260,000 340,000 Required: 1. Prepare journal entries for all 3 years. 2. Assume that the contract represents a single performance obligation that will be satisfied at a point in time. Prepare journal entries for all 3 years. Please dont provide image based answers thank youarrow_forward1.On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31,200,000. The company recognizes construction revenue over time. Data on this project for 2022-2024 follow:Contract BillingsCosts incurredEst’d Costs to Complete2022 10,500,000 5,460,000 20,540,0002023 12,500,000 9,984,000 13,156,0002024 14,440,000 15,756,000 -The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. In 2024, the contract was delayed for 8 weeksWhat is the gross profit for 2024?A. 1,164,000 C. 1,724,000B. 1,466,400 D. 1,824,000 2.MOC Construction Company started work on three job sites during the current year. Any costs incurred are expected to be recoverable. Data relating to the three jobs are given below:Site Contract PriceCost IncurredEstimated Costs to CompleteBillings on ContractCollections on Billings1 5,000,000 3,750,000 - 5,000,000 5,000,0002 7,000,000 1,000,000 4,000,000 900,000…arrow_forward
- SMDC Construction signed a contract to build a building over a period 3 years for a price of P10,000,000. Information relating to the performance of the contract is summarized as follows: 2017 2018 2019 contribution costs incurred during the year 2,500,000 2,400,000 1,800,000 estimated costs to complete 4,500,000 1,800,000 - buildings during the year 2,200,000 2,800,000 5,000,000 collections during the year 2,000,000 2,500,000 5,500,000 Prepare the entries under the percentage of completion.arrow_forwardBlossom Construction, which follows ASPE entered into a contract to construct a bridge for a contract price of $2.3 million. Construction began in 2022 and was completed in 2024. Below are the details of the transactions related to the contract: Costs incurred during the year Estimated costs to complete Revenue Expenses Gross Profit Calculate the gross profit to be recognized each year using the completed-contract method. $ 2022 $661,000 $822,000 1,519,000 705,000 2023 2022 2024 $685,900 0 2023 $ 2024arrow_forwardIn 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara Countyfor $10,000,000. The road was completed in 2020. Information related to the contract is as follows:2018 2019 2020Cost incurred during the year $2,400,000 $3,600,000 $2,200,000Estimated costs to complete as of year-end 5,600,000 2,000,000 –0–Billings during the year 2,000,000 4,000,000 4,000,000Cash collections during the year 1,800,000 3,600,000 4,600,000Westgate recognizes revenue over time according to percentage of completion.Required:1. Calculate the amount of revenue and gross profit to be recognized in each of the three years.2. Prepare all necessary journal entries for each of the years (credit “various accounts” for construction costsincurred).3. Prepare a partial balance sheet for 2018 and 2019 showing any items related to the contract. Indicate whetherany of the amounts shown are contract assets or contract liabilities.4. Calculate the amount of revenue and gross…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning