Intermediate Accounting (2nd Edition)
2nd Edition
ISBN: 9780134730370
Author: Elizabeth A. Gordon, Jana S. Raedy, Alexander J. Sannella
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 8, Problem 8.18BE
To determine
The percent completed, revenue and gross profit for the current year.
Given information:
Contract price is $85,000.
Actual construction cost for 2018 is $12,000.
Estimated total cost for 2018 is $60,000.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Cosmo Computer Consultants (CCC) signed a contract in 2022 to develop a computer network system for Platinum Entertainment. Cosmo uses the percentage-of-
completion method and determines its measure of progress using the cost-to-cost approach. The firm provided the following information for 2022.
Contract Price
Actual construction costs incurred during the year
Estimated total costs
Progress billings made during the year
Cash collections during the year
$85,000
2022
$12,000
60,000
30,500
25,000
This problem has subparts that still need to be answered
Assume Avaya contracted to provide a customer with Internet infrastructure for $2,350,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below:
2024
2025
Costs incurred during the year
$ 328,000
$ 1,830,000
Estimated costs to complete as of 12/31
1,312,000
0
Billings during the year
436,000
1,690,000
Cash collections during the year
341,000
1,785,000
Required:
Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming Avaya recognizes revenue over time according to percentage of completion.
Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming this project does not qualify for revenue recognition over time.
Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time…
Recording Long-Term Construction: Recognize Revenue at a Point in Time and Over Time
Watson Construction Company contracted to build a plant for $500,000. Construction started in January 2020 and was completed in November 2021. Watson uses the cost-to-cost method to measure the completion of its performance obligations. Data relating to the contract follow.
2020
2021
Costs incurred during year
$290,000
$120,000
Estimated additional costs to complete
125,000
0
Billings during year
270,000
230,000
Cash collections during year
250,000
250,000
Revenue Recognized at a Point in Time
Revenue Recognized Over Time
a. Provide the 2020 and 2021 journal entries for Watson assuming revenue is recognized at a point in time. Provide entries for (1) construction costs incurred, (2) progress billings, (3) cash collections, and (4) revenues and expenses.
Note: If a journal entry isn't required for the transaction, select "N/A" as the account names and leave the Dr. and Cr.…
Chapter 8 Solutions
Intermediate Accounting (2nd Edition)
Ch. 8 - What are the primary issues involved in revenue...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - Prob. 8.4QCh. 8 - Prob. 8.5QCh. 8 - How is a performance obligation defined?Ch. 8 - What are the two criteria to define a good or...Ch. 8 - Prob. 8.8QCh. 8 - What principles regarding timing and measurement...Ch. 8 - Prob. 8.10Q
Ch. 8 - What is variable consideration and what factors...Ch. 8 - Describe and contrast the two approaches used to...Ch. 8 - Prob. 8.13QCh. 8 - What factors should accountants consider to...Ch. 8 - Prob. 8.15QCh. 8 - How does a seller account for any consideration...Ch. 8 - Prob. 8.17QCh. 8 - What are the two exceptions to the general rule...Ch. 8 - What are the three criteria required to recognize...Ch. 8 - When an entity does not meet the three criteria...Ch. 8 - Prob. 8.21QCh. 8 - Prob. 8.22QCh. 8 - How does a firm estimate the degree completed...Ch. 8 - Can a firm record inventory out on consignment as...Ch. 8 - What method do agents in a transaction use to...Ch. 8 - Prob. 8.26QCh. 8 - What qualitative disclosures do the standards...Ch. 8 - All of the following are elements of a contract...Ch. 8 - Prob. 8.2MCCh. 8 - Telecom Co. enters into a two-year contract with a...Ch. 8 - The transaction price must reflect the time value...Ch. 8 - Prob. 8.5MCCh. 8 - When allocating the transaction price to separate...Ch. 8 - Which of the following indicators is not...Ch. 8 - During Yoar 1 Moriwothor Construction Company...Ch. 8 - All of the following are indicators that the...Ch. 8 - Prob. 8.10MCCh. 8 - Prob. 8.11MCCh. 8 - Identify a Contract with a Customer. Complete the...Ch. 8 - Prob. 8.2BECh. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Estimating Variable Consideration. Gear Garage...Ch. 8 - Estimating Variable Consideration. Using the...Ch. 8 - Estimating Variable Consideration. Sellet...Ch. 8 - Estimating Variable Consideration. Seliet...Ch. 8 - Prob. 8.9BECh. 8 - Allocation of Transaction Price. Martin Software...Ch. 8 - Prob. 8.11BECh. 8 - Allocation of Transaction Price. Sycamore Sidewalk...Ch. 8 - Allocation of Transaction Price. Sycamore enters...Ch. 8 - Prob. 8.14BECh. 8 - Allocation of Transaction Price. Using the...Ch. 8 - When to Recognize Revenue. For each scenario...Ch. 8 - Prob. 8.17BECh. 8 - Prob. 8.18BECh. 8 - Percentage-of-Completion Method, Journal Entries....Ch. 8 - Prob. 8.20BECh. 8 - Sales with the Right of Return. Both incorporated...Ch. 8 - Sales with the Right of Return. Using the...Ch. 8 - Sales Returns. Historically, about 5% or the...Ch. 8 - Sales on Consignment. Hanna Lighting recertify...Ch. 8 - Determining Performance Obligations. Pagit Inc, a...Ch. 8 - Prob. 8.2ECh. 8 - Estimating Variable Consideration. King Rat Pest...Ch. 8 - Prob. 8.4ECh. 8 - Prob. 8.5ECh. 8 - Prob. 8.6ECh. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Prob. 8.9ECh. 8 - Prob. 8.10ECh. 8 - Determination of When to Recognize Revenue. Far...Ch. 8 - Prob. 8.12ECh. 8 - Percentage-of-Completion Method. Gary Construction...Ch. 8 - Prob. 8.14ECh. 8 - Prob. 8.15ECh. 8 - Prob. 8.16ECh. 8 - Sales with the Right of Return. Webster Hall, Inc....Ch. 8 - Prob. 8.18ECh. 8 - Prob. 8.19ECh. 8 - Other Principal Agent Transactions, Net Revenue...Ch. 8 - Prob. 8.1PCh. 8 - Prob. 8.2PCh. 8 - Comprehensive Revenue Recognition Problem. Casale...Ch. 8 - Prob. 8.4PCh. 8 - Determining When to Recognize Revenue. Megrew...Ch. 8 - Prob. 8.6PCh. 8 - Prob. 8.7PCh. 8 - Prob. 8.8PCh. 8 - Percentage-of-Completion Method. R Wayne Computer...Ch. 8 - Prob. 8.10PCh. 8 - Prob. 8.11PCh. 8 - Sales on Consignment. Pablo Products. Ltd sells...Ch. 8 - Prob. 1JCCh. 8 - Prob. 1FSCCh. 8 - Prob. 1SSCCh. 8 - Basis for Conclusions Case 1: Control According to...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Required: Calculate the following: a. estimated total cost of completion, b. estimated profit on completion, c. estimated profit to date. Lim Construction is building Univ tower Near Unicity, Sibu. The date of commencement of construction is 1 January 2021 and the date of completion is on 31 December 2026. During the year ending 31 December 2021, the following information reported: RM Contract price Plant sent to site Purchasing of materials Wages paid Direct expenses Overhead incurred 13,000,000.00 2,000,000.00 3,000,000.00 1,500,000.00 1,000,000.00 500,000.00 At the end of December 2021, the following available: 1. Material unused on site amounted RM1,000,000.00 2. Wages owing RM500,000.00 3. Value of work certified RM6,000,000.00 4. Cost of work done but not yet certified amounted to RM500,000.00 5. Plant at site RM1,500,000.00arrow_forwardGinebraCorporation recognizes construction revenue and cost using the percentage of completion method. During 2021, a single long-term project was begun which continued through 2021. Information on the project follows: 2021. 2022 Partial billing on contract 1,000,000. 4,200,000 Accounts receivable 1,000,000 3,000,000 Construction cost 1,050,000 1,920,000 Construction in progress 1,220,000 3,640,000 What is the gross profit recognized from this long-term construction contract in year 2021 and 2022, respectively? 2021 2022 A.220,000. 2,280,000 B.170,000. 500,000 C.220,000. 1,000,000 D.170,000. 1,280,000arrow_forwardOn March 1, 2022, ABC Co. was contracted to construct a building for a customer at a total contract price of P16,500,000. The building was estimated to be completed in 2024. The following data were made available: 2022 2023 2024 Contract costs incurred P6,400,000 P5,200,000 P2,900,000 Estimated costs to complete 6,400,000 2,900,000 - Progress billings each year 6,400,000 7,000,000 3,100,000 How much is the realized gross profit for 2023?arrow_forward
- BnD Construction Co. successfully tendered for a 3-year contract to erect some warehouse facilities in Gros Islet. The following information has been provided. Time left 2:20:2 Contract price - $25 000 000 2021 $ 4 000 000 Cast during year Estimated cost to complete Progress billings to date Cash collected to date Cast to date Estimated cost to complete Total estimated cost Percentage complete (Round to nearest whole number) Total contract price Total estimated cast i Complete the following Workings Schedule. Do not enter negative values in the schedule. Estimated gross profit or loss Revenue to recognize to date Less Revenue previously recognized Revenue to recognize in year Estimated gross profitto recognize to date 16 000 000 4 500 000 4 200 000 Less Gross profit or lass previously recognized 2022 2021 $8 000 000 8 050 000 11 500 000 11 000 000 2023 2022 $8 100 000 0 25 000 000 25 000 000 2023 %arrow_forwardAssume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below:2018 2019Costs incurred during the year $ 300,000 $ 1,575,000Estimated costs to complete as of 12/31 1,200,000 –0–Billings during the year 380,000 1,620,000Cash collections during the year 250,000 1,750,000Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming Nortelrecognizes revenue over time according to percentage of completionarrow_forwardOn March 1, 2022, AGGREGATES Company enters a contract to build a hotel which The is estimated cost P31,200,000. company recognizes construction to Data on this project for 2022-2024 follow: Est'd Costs revenue over time. Contract Costs Billings 10,500,000 12,500,000 14,440,000 incurred to Complete 20,540,000 13,156,000 2022 5,460,000 9,984,000 2023 2024 15,756,000 The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. contract was delayed for 8 weeks In 2024, the What is the gross profit for 2024? 1,164,000 1,466,400 1,724,000 1,824,000 А. с. в. D.arrow_forward
- Please assits with this cost accounting question Contract Masters Ltd has entered into a contract with Creative Dealers Ltd. for the construction of a new branch office. The contract began on March 1, 2022 and was completed on December 28 2022. The total value of the contract was $12,000,000. On December 30, 2022, an engineer inspected the project and issued a final certificate for work done. The following information is available with regards to the contract: $Site labour costs 3,120,000 Materials direct to site 2,000,000Materials returned 30,500 Materials from store and workshops 500,000 Maintenance of plant and use 980,000 Direct expenses 1,090,000 General overheads 750,000 Materials…arrow_forwardOn January 1, 2016, AVIDA was contracted to construct a townhouse for SM Corp. for a total contract price of P50,400,000. The building was completed by November 31, 2018. The following are the data of AVIDA: 2016 2017 2018 Contract cost incurred during the 19,200,000 15,600,000 8,700,000 year Estimated cost at completion 38,400,000 43,500,000 43,500,000 Billing during the year 19,200,000 21,000,000 10,200,000 The entry to record the recognized profit in 2018 includes credit to O CIP 1,380,000 Contract revenue 10,080,000 O CIP 50,400,000 Contract cost 8,700,000arrow_forward+ Use the following information for Problems #13-15: Percentage Completion Method: Done Right Company is doing contract work for Good Homes Company. Use the grid below to complete the required accounting information: 2010 2011 2012 Contract Price $2,025,000 $2,025,000 $2,025,000 Estimated Total Cost of Project: $1,800,000 $1,800,000 $1,800,000 Cost Incurred Current Year $450,000 $858,000 $492,000 Estimated Cost to Complete $1,350,000 $492,000 Billings to Customer Current Yr. $405,000 $1,080,000 $540,000 Cash Receipts from Customer Current Yr. $337,500 $787,500 $900,000 Cost Incurred to Date Estimated Cost to Complete Estimated Total Contract Cost Estimated Percent Complete Contract Price Revenue Recognizable Revenue Recognized Prior Year Revenue Recognized Currently Costs Incurred Currently Gross Profit Recognized 13) The gross profit recognized for year 2010 is 14) The gross profit recognized for year 2011 is 15) The gross profit recognized for year 2012 is 2010 2011 2012arrow_forward
- Question Three: $960,000. The job was completed in 2022. The following information is available: During 2020 Nass Company started a construction job with a contract price of Costs to date Estimated costs to complete Billings to date Collections to date 2020 $240,000 360,000 180,000 162,000 (a) Percentage-of-completion Date 2021 2021 $495,000 165,000 540,000 486.000 Required: a) Preparing all the journal entries for 2021 Assuming Nass uses the percentage-of-completion method. Account b) Assume that Nass uses the cost-recovery method, record the revenue, and gross profit if any, recognized in 2021 and 2022. c) Show the presentation of construction-in-process and billings in construction-in-process accounts in the statement of financial position in 2020 under both the percentage-of-completion and the cost-recovery method. 2022 $642,000 0 960,000 855,000 Debit Credit ASI -991E ATUarrow_forwardOn March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31,200,000. The company recognizes construction revenue over time. Data on this project for 2022-2024 follow: Contract Billings Costs incurred Est'd Costs to complete 2022 10,500,000 5,460,000 20,540,000 2023 12,500,000 9,984,000 13,156,000 2024 14,440,000 15,756,000 - The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. In 2024, the contract was delayed for 8 weeks. What is the gross profit for 2024?A. 1,164,000 C. 1,724,000B. 1,466,400 D. 1,824,000arrow_forwardsir answer as soon as possible Beta Construction Ltd. executed various types of construction projects. The details of the contract amount, costs incurred and to be incurred and payment particulars are given in the following table for 2014-15. All figures are in Millions. All costs were fully settled in cash and all payments were received in cash. Assume that all projects were started during 2014-15. Project Billings Contract Value 20.00 1 20.00 Costs to Costs to date complete 19.00 Completed 9.60 6.40 16.60 Completed 2.40 13.60 2 15.00 10.00 3 16.00 16.00 2.00 4 20.00 Assume that the company uses the Percentage of Total Cost Method to account for its contracts. Fill in the blanks for each of the three contracts: Project 1 Project 2 Project 3 Project 4 Increase in Earnings Unearned Rev. Un-incurred Cost Change in Liabilities WIP Unbilled Revenue Change in Assets Assume that the company uses the Physical Progress Method Based on Billing to account…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education